HPC ESTIMATE

CHAINAGE
SPAN 1X1.2X12.5
1) 01+310
2) 02+464 PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM
3) 02+530
4) 02+693 Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM
5) 03+097
6) 04+282 Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM
7) 05+850
8) 06+260 TOTAL = 25.743 CUM
9) 06+495
10) 06+100 TOTAL OF 1X1200 = 643.57112
11) 08+505
12) 08+820 Total M15 Quantity = 28.494
13) 09+600
14) 10+584 Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM
15) 10+996
16) 11+162 Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM
17) 12+073
18) 12+971 TOTAL = 23.178 CUM
19) 13+064
20) 13+743 RCC Pipe = 1x12.5 = 12.500 CUM
21) 14+137
22) 14+826 TOTAL OF 1X1200 = 312.5
23) 15+390
24) 15+640
25) 15+720
HPC ESTIMATE LATERI ROAD

CH. 05+850
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD

CH. 08+820
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD

CH. 10+584
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD
CH. 11+162
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD
CH. 12+073
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD
CH. 12+971
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD
CH. 13+064
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD
CH. 14+137
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD
CH. 14+826
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD
CH. 15+390
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD

CH. 15+640
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM


HPC ESTIMATE LATERI ROAD

CH. 15+720
SPAN 1X1.2X12.5

PCC M15 = 2X6.55X1.4X0.150 = 2.751 CUM

Head Wall M15 = 2X6.4X0.825X2.690 = 28.406 CUM

Pipe Deduction = 2x0.785x2.074x0.818 = -2.664 CUM

TOTAL = 25.743 CUM

Total M15 Quantity = 28.494

Granular Material = 1x10.864x1.940x1.940 = 40.888 CUM

Pipe Deduction = 1x10.864x0.786x2.074 = -17.710 CUM

TOTAL = 23.178 CUM

RCC Pipe = 1x12.5 = 12.500 CUM