Professional Documents
Culture Documents
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Summery
With the introduction of new fleet of super critical turbine of 660 and 800 MW unit,
there have been various turbine design installed in NTPC, supplied by various OEMs
like Hitachi, Toshiba, MHI, GE/Alstom apart from Siemens/BHEL. There have been
two broad category of turbine design, one is single casing, where blades are assembled
directly on the casing and another being Diaphragm type machine, where fixed blades
stages are made of individual ring installed in inner casings.
Apart from fixed blade design, there have been diverge assembly structure for turbine
casing, bearing pedestal and bearing design itself.
The main content of this ask and learn maintenance write up includes design and
maintenance philosophy of diaphragms type of machine with horizontally split double
shell construction. Bearing and pedestal design includes sliding pedestal design, tilting
pad and elliptical self-aligning bearings.
Capturing the learning from the beginning is important for future preparedness.
Improvement and refinement of learning will be ongoing process to gain complete
expertise.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 1:
Answer:
CV#1, #2, #3 opens with sliding Control main steam flow by opening all
pressure. CV#4 opens further to control valve at same time.
control steam flow
Question No 2:
Answer:
Heat balance is a diagram, which shows the thermal condition of heat cycle of a power
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
plant. The HBD shows the steam flow quantities and their thermal condition for each
section. HBD is the basis for design of turbine cycle of
Question No 3:
Answer:
Heat rate is a number that shows performance of power cycle. It is expressed as Kcal
per kWh (KJ/kWh). It is the measure of how much energy is required to generate one
kWh power.
Question No 4:
What is a diaphragm?
Answer:
Partitions between pressure stages in a turbine's casing are called diaphragms. They
hold the vane-shaped nozzles and seals between the stages. Usually labyrinth-type
seals are used. One-half of the diaphragm is fitted into the top of the casing, the other
half into the bottom.
Question No 5:
Answer:
function fixed blade or Nozzle diaphragm is to convert the thermal energy into kinetic
energy. The steam expands through fixed blades and its speed becomes very high.
High speed steam flows on to the blades and moves them by its kinetic energy.
Question No 6: (level-2)
What are the different types of fixed blade or nozzle assembly structure?
Answer:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
a) Assembly type where blades are assembled in the diaphragm ring. Blade
covers are integrally machined with blade and forms the inner ring of
diaphragms.
b) Welded type: Diaphragm are divided into three parts. Inner ring, nozzle
partition and outer ring. Blades are welded in between inner and outer
ring.
Question No 7:
Answer:
In an impulse turbine, the stage is a set of moving blades behind the nozzle. In a
reaction turbine, each row of blades is called a "stage." A single Curtis stage may
consist of two or more rows of moving blade.
Question No 8:
Answer:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
section of the turbine.
Question No 9:
Which type labyrinth seals are adopted in LP turbine last stage and gland?
Answer:
Straight type see through seals are adopted in LP turbine last stage and gland area. LP
rotor has large differential expansion, adopting hi-low type labyrinth packing would
require large axial clearance.
Question No 10:
Question No 11:
Answer:
Steam flow path clearance is the radial and axial clearance of rotating and stationary
component of steam turbine.
Question No 12:
Specify the area where steam flow path clearances are to be measured?
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Answer:
Steam flow path clearances are generally mentioned in the clearance diagram provided
by the manufacturer. Generally following are the area where it is to be measured.
1. Radial clearances between moving blade tip to outer ring of fixed blade.
2. Radial clearances between rotor shaft to inner ring of the fixed blade. It is called
inter stage clearance.
4. Axial clearance of moving blade with fixed blade at root and shroud area.
5. Axial clearance between moving blade tip fin to fixed blade outer ring.
Following are the typical location for steam flow path clearance measurement
Moving
Rotor Blade
Question No 13:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 14:
Answer:
Design clearances are specified in the clearance diagram are the values measured at
cold condition. When the turbine components are heated up and operates at different
load condition, due to thermal growth of turbine components, clearances are changed.
If the cold values are not maintained, there is a chance of contact between stationary
and rotating parts if the clearance set are less than specified. On the contrary, excessive
clearance may lead to losses and decrease of efficiency.
Question No 15:
Question No 16:
Answer:
A. Impulse design
B. Reaction design
Question No 18:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
What is difference between reaction and impulse design of stages?
Answer
Reaction stage: The force acting on the moving blade is a combination of pressure
difference and velocity force. There is both pressure and velocity drop across moving
blade. The ratio of force from velocity component and pressure components is called
degree of reaction.
Impulse stage: The force action on moving blade is the velocity of steam and there is
no pressure drop across the moving blade.
Velocity force acts on moving blade Reaction force due to pressure difference
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Pressure drop and velocity increase Pressure drop and velocity increase across
across fixed blade. fixed blade.
Pressure remains constant and Pressure and velocity both reduces across
velocity reduces across moving blade moving blade
Question No 19:
What are the different types of moving blade root fixation configuration?
Answer:
1. T root type
2. Outside dovetail
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
5. Fork type
T root type
Outside dovetail
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Fork type
Question No 20:
Why should a steam or moisture separator be installed in the steam line next to a
steam turbine?
Answer:
All multistage turbines, low-pressure turbines, and turbines operating at high pressure
with saturated steam should have a moisture separator in order to prevent rapid blade
wear from water erosion.
Question No 21:
What are some conditions that may prevent a turbine from developing full power?
Answer:
1. The machine is overloaded.
2. The initial steam pressure and temperature are not up to design conditions.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
3. The exhaust pressure is too high.
4. The governor is set too low.
5. The steam strainer is clogged.
6. Turbine nozzles are clogged with deposits.
7. Internal wear on nozzles and blades.
Question No 22:
Why is it necessary to open casing drains and drains on the steam line going to the
turbine when a turbine is to be started?
Answer:
To avoid slugging nozzles and blades inside the turbine with condensate on start-up;
this can break these components from impact. The blades were designed to handle
steam, not water.
Question No 23:
Question No 24:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 25:
Question No 26:
Question No 27:
Besides lubrication, which are two functions of lubricating oil in some turbines?
Answer:
In large units, lube oil cools the bearings by carrying off heat to the oil coolers. Lube
oil in some turbines also acts as a hydraulic fluid to operate the governor speed-
control system.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 28:
Question No 29:
By monitoring the exhaust steam temperature, how can the blade deposition be
predicted?
Answer:
1. Immediately after the 1st commissioning, the different values of exhaust
temperature for different steam flow rates are precisely determined and plotted
against steam flow. This will produce the first actual graph. This is for a clean
turbine.
2. Similar graphs are to be drawn at later periods for comparing with the initial
graph.
3. A rise in exhaust steam temperature under the same conditions refers to deposit
formation.
4. An increase of exhaust steam temperature by more than 10% in the range of 70 to
l00% steam flow, indicates inadmissible blade depositions. Shutdown is to be
taken and blades are to be washed off deposits.
Question No 30:
Answer
1. Free standing blade, where each blade tip is extension of its aerofoil profile. Free
standing blades in a stage are sometimes connected to each other by lacing wire in the
midway of the blade section.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
2. Integrally shrouded blade (ISB) or continuous cover blade (snubber type), where
shroud is integral part of blade profile. Every blade in a stage are connected to each
other.
3. Tenon type shroud, where group of blade of a stage are covered with tenon.
Question No 31:
What is Integrally shrouded blade (ISB) or continuous cover blade (snubber type)?
what are the advantages of ISB or CCBs
Answer:
Blades and covers are integrally machined from single forging.
A. Continuous coupling 360 degrees
B. Low vibration stress
C. Resistance to corrosion fatigue
D. Improved tip sealing
E. Easy to assemble and dismantling
Pressure contact of the covers provides superior damping when excitation force
works
Continuously coupled structure greatly reduces dynamic response of the blades to
harmonic stimulating forces, thus vibration stresses are much lower compare to
conventional tenon and shroud design.
Continuously coupled integral covers provides an inter stage sealing with a
minimum of leakage losses.
Mutli tip fin on covers substantially reduces the tip leakages flow.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 32:
Question No 33:
Question No 34:
How do the problems of vibration and fatigue arise with steam turbine blades?
Answer:
1. These arise due to flow irregularities introduced because of manufacturing
defects, e.g. lack of control over tolerances.
2. System operating parameter, e.g. low flow may excite various modes of vibration
in the blades.
Question No 36:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
turbines of 400°C or more. When the turbine is being shut down, a motor-driven
turning gear is engaged to the turbine to rotate the spindle and allow uniform cooling.
Question No 37:
Question No 38:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 40:
In which part of the steam turbine does stress corrosion cracking (SCC) occur?
Answer:
In the wet stages of the low-pressure turbine
Question No 41:
Question No 42:
What are the stresses to which a steam turbine rotor is subjected during its service
life?
Answer:
1. Mechanical stress - The factors that contribute to mechanical stress in the
shaft are the centrifugal forces and torque’s generated due to revolving motion
of the shaft as well as bending arising during steady-state operation.
2. Thermal stress - Transient operating phases i.e. start-up and shutdown the
genesis of thermal stress induced to the turbine shaft.
3. Electrically induced stress - They originate due to short circuits and faulty
synchronization.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 43:
1. Erosion
2. Corrosion
3. Stress/fatigue damage mechanism
4. According to EPRI (Electric Power Research Institute, USA) data stress
corrosion cracking and fatigue are the chief exponents for turbine-blade failures
in utility industries.
Question No 44:
Answer:
8. Deflection measurement during assembling of top half and parting plane studs
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
1. Die penetration check of babbitt surface.
7. Inner ring and outer ring spherical contact check on bottom half
9. Deflection measurement during assembling of top half and parting plane studs
Question No 45:
Answer:
Catenary is defined as the bearing or shaft center line elevation at different bearing. It
is calculated based on the thermal growth, sinking of pedestal support and dynamic
load during steam admission and vacuum pulled condition ?
Question No 46:
What are the different type of bearing used in large steam turbine?
Answer:
Following are some of the variant of turbine bearing used for large steam turbines
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 47:
Answer:
Tilting pad bearing provides maximum stability and freedom from turbine vibration.
Tilting pad design consists of generally six pads with babbitt lining on the pad inner
surface. The pads are installed in inner of the bearing ring and can tilt in radial and
axial direction, therefore, pads moves smoothly and maintain correct alignment at all
condition.
How can we measure the oil clearance for tiling pad bearing?
Answer:
Tilting pad bearing pads are normally loose and free to pivot in the shell, it is not
possible to measure the oil clearance in conventional manner. On the six pad bearing
design each pad and bearing inner ring is provided with tap holes, Temporary bolt can
be inserted through shell and screwed into the back of the pads. In this manner pads
can be pulled tightly against the shell. Bore diameter can be measured with this pad in
locked condition.
In three tilting pad design, where bottom three pads are tilting type and top pad is
fixed, Top oil clearance can be measured easily in conventional manner, However for
side oil clearance pads are to be pulled against the shell by locking screw.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Double tilting Pad
bearing with six pads.
Answer: Pin check is the reference reading of outer casing with respect to rotor in
radial direction. It is measure at both end of the casing at packing case area.
Rotor
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
After disassembling of bearing cover, Upper packing case on outer casing is
dismantled. Position of rotor and casing is confirmed with pin check.
Question No 50:
Answer:
Seal bore check is the position check of rotor with respect to pedestal bearing
housing. Since pedestal is the support for both rotor and turbine casing, the seal bore
reading indicates the position of rotor w.r.t common support. It is measured in the oil
guard / oil deflector area. Rotor position can be adjusted with a change in shim on the
support pad of the bearing. Any change in rotor position is reflected on the seal bore
reading. Reading shall be recorded every time after any modification of bearing
position and rotor positioning. It can be confirmed from the seal bore reading that
rotor and bearing are correctly positioned or not.
Figure: Seal bore position check: It is measured in left, right and bottom from
Seal Bore
reading
Rotor
Bearing
Pedestal
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 51:
Answer:
In diaphragm type machine, fixed blade are assembled in individual ring. Diaphragms
are assembled into inner casing or holders and finally inner casing are assembled
inside outer casing. Centering is the process where diaphragms and gland packing
case are set at equidistant or offset design position with respect to shaft centre line.
Question No 52:
Answer:
Centering is the process where diaphragms are set at equidistant or offset design
position with respect to shaft center line. Before starting the centering process
following two activity must be completed
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Special T&P requirement
Piano wire.
Hand light
Marker pen
NB: Centering can be carried out with laser alignment machine. However, most
OEMs prefer piano wire centering as the proven technique with required quality
control.
Left, right and bottom marking shall be done on smooth surface. Make sure that
bottom marking is at centre position.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
NB: There are three sets of centering reading t be taken with following conditions
2. Tops on condition (only top half outer casing in position. Parting plane stud to be
hot tightened and ensure that 0.03 filler does not pass through parting plane joint)
Parting plane gap and contact check also gets completed during the process)
3. Again after dismantling Tops off condition reading. Tops off reading shall be taken
only after cooling down of casing into ambient temperature.
Tops off to tops on variation to be recorded and incorporated for final correction of
diaphragms and packing case position.
Right and left are determined when viewed from the turbine front toward
generator.
L=Total length of Piano wire (mm), W=Weight of piano wire per unit (kg)
0.00154 kg/m for 0.5 dia wire.
Incorporate Rotor static sag value in to the corrected centering reading with Piano
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
wire sag.
Finally based on tops off to on variation and corrected centering reading with piano
wire and rotor sag.. Target value is calculated for correction of diaphragm and
packing case position on tops off condition.
Position Rotor Piano Tops off Tops on Tops off Tops on/off Target
sag wire sag Reading reading reading variation Centering
Calculation of centering correction with Example. (all values are in 1/100 mm)
T: 20
L:30 R:70
B:70
Measured value 20
10
T:
L:40 R:60
B:60 10
Target Value
Explanation:
Diaphragms is towards left side by 0.20 mm and toward top side by 0.20 mm as per
measured value. However, Diaphragms shall be towards left side by 0.10 mm and
toward top side by 0.10 mm as per measured value. SO we need to correct the
position of diaphragms and shift the position towards right side by 0.10 mm and
towards bottom side by 0.10 mm.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Diaphragm construction and correction plane are described below:
For vertical shifting of diaphragms add required shim of 0.10 mm at both left and
right side centering correction key. For Toshiba turbine diaphragms is adjusted by
adjusting screw provided in centering support key as shown in figure
Vertical adj
Shim plate
For left right adjustment of diaphragm center, addition and subtraction of shim to be
done from left and right support plate. For example if we want to shift diaphragm
towards right side we need to add move right side up and equal amount left side down
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
as described in the following figure
Question No 54:
Answer:
In multi rotor tandem compound turbine shafts are coupled together after carrying out
alignment. In the process of coupling both the rotor centre are to be matched to align
the center line. However, in practical it is always difficult to perfectly align the
coupling centre. To limit the misalignment of center coupling run out is measured at
the circumference of each rotor along with journal. Set up is prepared to put dial
guage from the top position as indicated in the picture. Dial reading are measured at
30-degree interval from zero position. For some manufacturer it is recommended to
take reading against each coupling bolt position. Recorded reading are plotted in a
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
polar plot sheet and distance between two shaft center point is measured. The
measured value shall be within the target value in terms of distance and angle between
the shaft center.
Dial indicator shall be set at journal for checking left right movement
especially for tilting pad bearing.
When rotating the shaft by overhead crane and JOP lift, Reading shall be
taken after stopping JOP and releasing the crane sling.
Dial indicator reading shall be taken from straight position to avoid angular
error.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 55:
Answer:
Journal bearing is a bearing with babbitt liner for supporting rotating shaft on fluid
film. For elliptical journal bearing total vertical diametrical clearance is 0.0013
mm/mm of journal diameter and total horizontal diametrical clearance is 0.0026
mm/mm of journal diameter thus making the internal bore of the bearing elliptical.
Elliptical bore is achieved by machining internal bore on major axis i.e. horizontal
diameter after inserting shim on parting plane. Shim is then removed for assembly.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 56:
Answer:
Elliptical journal bearing where oil is circulated through overshot groove machined on
top half of the bearing. The oil is fed to the rotor upcoming side of the journal and
flow towards top half and reach to opposite side parting plane. From ther part of oil is
drained through drain hole and part of the oil enter bottom for forming oil wedge.
Question No 57:
Answer:
Turbine rotor is anchored in thrust bearing for taking up residual unbalanced thrust or
thrust coming during transient condition. Thrust float is the axial gap between rotor
collar and thrust bearing. Thrust float is designed based on oil flow and clearance
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
requirement. Following is the figure representing thrust float.
Question No:
Why it is required to have all running load on turbine during carrying out final
alignment?
Answer:
Turbine cold alignment value is calculated based on the static load on TG deck,
dynamic load due to thermal growth, steam flow and condenser vacuum.
Cold condition alignment setting must include all the static loads on TG deck.
Question No 58:
Answer:
Alignment of multi-bearing turbine rotors are carried out during cold condition.
However the coupled rotor is subjected to dynamic load and thermal growth due to
steam force and condenser vacuum. Cold alignment offset is kept in radial and axial
face to compensate the dynamic force.
Following is the simple figure showing the change in rotor position during on load
condition.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 59:
Answer:
Excessive clearance in elliptical type journal bearing can create oil whrill and oil whip
resulting sub synchronous vibration of the shaft, where dominant frequency of
vibration spectrum is half of the shaft speed.
Question No 60:
Answer:
Nozzle diaphragm are supported inside inner casing or holders. It is supported on the
parting plane pocket at left and right side of the casing. Further to vertical support it is
axially locked in the slot of inner casing. Diaphragm also located on the bottom with a
center pin for restricting left-right movement. Top half of inner casing further lock the
diaphragms support key for restricting the vertical movement.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Horizontal
support on
bottom
inner casing Left right Centering pin
Question No 61:
Answer:
HP outer casing is mounted on both the front standard and No.2 middle standard, and
keyed to the front standard and No.2 middle standard in direction both axial and
perpendicular direction to the turbine axis with gib key structure
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 62:
Answer:
Toshiba and Hitachi turbine HP/IP module are double shell construction with
horizontally split casing. Top half outer casings of HP/IP are supported on its
horizontal center line at both end and keyed to the bearing standard at the vertical
center line for location in the traverse direction. Outer casing lower half is securely
fastened to upper half. As the support is attached to upper half, during OH and
Inspection support is required to be transferred to lower half for dismantling of upper
half. Support key for upper half during unit running is called running key and support
key for lower half for OH/Inspection is called assembly key.
Question No 63:
Why color contact is checked between bearing support to pedestal? what will be
effect of lack of proper contact?
Answer:
Journal bearings are supported with adjusting pad on bottom half along the
circumference. Generally, there are 3 or 5 support pads for each bearing based on the
design philosophy of different OEMs. In some of the design oil is fed and drained
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
through hole on the support pad and bearing shell. The load of rotor on journal
bearing is transferred to the pedestal through these pads. Lack of proper contact will
result high point on the contact surface and load is concentrated to limited area. This
reduces bearing stiffness and lead to vibration of the bearing.
Question No 64:
What is hold down bolt? What is the function of hold down bolt?
Answer:
Hitachi and Toshiba make turbine HP/IP module is simply supported on bearing
standard. Most of the steam pipes are connected to lower half of the casing which can
push the casing in vertical direction. Hold down bolt is installed on lower half outer
casing arm and fastened securely the casing with bearing standard.
Question No 65:
Answer:
High and intermediate pressure turbine of large size turbine are assembled with inner
and outer casing. Inner casing holds diaphragms or fixed blades are directly
assembled. Inner casing is further supported inside outer casing. Outer casing, inner
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
casing and diaphragms are also split into two halves at horizontal centre line.
Following is the schematic diagram for Horizontally split double shell construction
Question No 66:
What is pre alignment of rotor, why pre alignment of rotor is carried out?
Answer:
In diaphragms type of machine casing and diaphragms are centered based on shaft
center line position. Pre alignment of rotor shall be carried out with tops on and tops
off correction factor for determining shaft center line for measurement and correction
of casing and diaphragms position.
Question No 67:
How top and bottom radial clearances are measured in diaphragm type turbine?
Answer:
Top and bottom radial clearance are measured with lead wire. Following are the
requirement for carrying out lead wire clearance measurement.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
For inter stage clearance lead wire shall be fixed on diaphragm inner ring.
For moving blade tip clearance lead wire shall be fixed on moving blade
shroud.
For fast and accurate measurement thickness micrometer with digital display
dial shall be used
Question No 68:
Answer:
Question No 69:
Answer:
Tops off centering measurement indicates the measurement of casing, diaphragms and
gland packing case position with respect to rotor center line (piano wire set at rotor
center line) when top half of casings are not in position and support is transferred to
lower casing
Question No 70:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Answer:
Tops on and tops off centering reading is taken to measure the variation in radial
clearance due to loading and unloading of top half casing and support shifting from
lower to upper casing. As the turbine clearances can only be measured in tops off
condition, change in radial clearances due to tops on and tops off variation shall be
incorporated.
Question No 71:
Answer:
Diaphragms are supported on inner casing at left and right side just below the parting
plane. Diaphragm top half is assembled over the lower half. Part of diaphragms left
right support key protruded and locked between inner casing lower and upper half.
Question No 72:
What is the technical requirement for diaphragm parting plane elevation? what is the
typical value?
Answer:
Diaphragms are supported on horizontal planer and keyed at bottom centre. Protruded
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
part of horizontal support key is locked between inner casing top and bottom half.
With this support arrangement diaphragm are free to expand radially. Parting plane
elevation is the clearance between protruded part of support key and lower half inner
casing parting plane. The diaphragm key shall be 0.15 to 0.20 mm lower than the
casing parting plane. This clearance will ensure following two technical requirement
Question No 73:
Answer:
Diaphragms centering pin is located at bottom half of inner casing. The purpose of the
centering key to hold the diaphragms at left and right horizontal centre
Question No 74:
Answer:
Diaphragms are keyed at bottom with center pin for restriction horizontal movement.
The clearance on the center pin is called diaphragm slip. It is measured as actual with
physical left and right movement with gentle push at parting plane with dial set from
inner casing to diaphragm.
Question No 75:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Answer:
In a diaphragm type turbine assembly, the diaphragms, casing and packing head are
subjected to different steam temperature and have different thermal expansion due to
different material. Thermal clearance are kept radially between diaphragms to inner
casing and inner casing to outer casing.
Question No 76:
Answer:
Main steam pipe from CV is connected to outer casing. Inner casing is connected to
outer casing for steam entry through sleeve pipe with bimetallic seal ring.
Question No 77:
How thrust balance is carried out in HP turbine of Toshiba make 800 MW unit?
Answer:
In Toshiba Make 800 MW Turbine HP module is single flow with balance drum
arrangement. Packing seal installed before the balance drum allows controlled leakage
rate on balance drum and packing ring clearance around the drum regulates further
steam flow to outer casing. By controlling the steam flow across these seals thrust can
be balanced. Following is the schematic representation of the above.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
CRH Pressure
b/w Inner and
Outer casing
Question No 78:
Answer:
Question No 79:
Answer:
Diaphragms are radially free to expand without any relative axial movement and and
lateral movement w.r.t inner casing. Horizontal and vertical diameter shall remain
same in all operating condition. However due to any of the following reason
diaphragm ovality can occur,
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Lack of uniform thermal clearance.
Deformation of diaphragm can occur because of any of the above reason. Extreme
care must be taken to identify any restriction during assembly. Any all thermal
clearances must be measured and corrected for any deviation.
Question No 80:
Answer:
Diaphragm ovality can reduce radial clearances between diaphragm and rotor. With
present day super critical turbine with high pressure and optimized turbine radial
clearance to reduce leakage losses, any change in radial clearance due to deformation
of diaphragms can lead to contact between stationary and rotating components and
severe damage to turbine component, prolonged outages and high repair cost.
Question No 81:
Why there is offset in left and right radial clearances of turbine rotor?
Answer:
Turbine is supported on fluid film journal bearing, during full speed operation turbine
position moves up due oil wedge pressure gradient and at the same time rotor also
moves towards upcoming side of the bearing. Thus based on the rotor direction of
rotation radial clearances are kept offset to have equal radial clearances during on
load operation.
Question No 82:
Answer:
Axial guage or taper guage is used for measuring axial clearances between rotor and
stationary parts.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 83:
Answer:
Segment packing ring are installed with coil spring or plate spring behind the
segment.
Following precaution shall be taken for measuring radial clearances with lead wire.
Lead wire diameter shall be approximately two times of the radial clearance
to be measured.
Packing segment shall be locked with wooden wedges for restricting the
movement.
Rotor shall be positioned slowly and lift the rotor immediately in the same
way.
Lead wire chart shall be prepared for keeping the lead wire stage and position
wise.
Lead wire reading shall be taken with digital push back micrometer with flat
line contact thimble
Question No 84:
Answer:
High temperature anti seize compound are applied on threaded connection to avoid
seizure of stud and bolts threads. Anti-seize compound forms a lubricating layer on
the surface and adhesive in nature and assists dismantling of equipment for
maintenance even after long operating hours.
Question No 85:
Answer:
High temperature anti seize compound are widely used Turbine and valves especially
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
threaded fasteners including keys, packers, parting plane stud and nut of HP & IP
turbine, stop & control valve of HP /IP, LP-Bypass stop & control valves etc in high
temperature zone of Turbine area.
Question No 86:
Answer:
Anti-seize compound must be applied ever time during trial or final assembly as it
protects the contact surface by providing lubrication and less friction for threaded
components.
Question No 87:
Answer:
Vortex gaskets are spirally wounded stainless strip with layer of graphite in between.
Steel strips are spot welded in first and last two round. Handling and assembly of the
gasket must be done carefully especially the large size used for cross over pipes.
The gasket shall be packed in hard shell box and cardboard paper.
The gasket shall be locked in different position around the circumference with
suitable spacing.
Question No 88:
What are the important measurement to be carried out during assembly of vortex
gasket?
Answer:
Vortex gasket are placed in the groove between flanges with metal to metal contact in
turbine assembly especially in valve and crossover pipe assembly. The thickness of
the gasket and depth of the groove are the two important measurement for ensuring
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
proper compression of the gasket after assembly.
Question No 89:
What is the different stage of measurement for ensuring required extension of Turbine
casing parting plane?
Answer:
Turbine casing studs and coupling bolts are extension tightened based on the design
and operation requirement. Uniform and recommended extension of stud/bolt must be
done to ensure uniform loading of each stud/bolt and clamping force across the
parting plane and coupling. Following are the stages to be adopted to avoid repeat of
the process and uniform value in one go in case of parting plane.
Clean stud/bolt and nut properly to remove all dirt, rust and sticky material
especially in thread portion.
Measure the cold length of each stud and record the same.
Install the bolts and hammer tight each stud/bolt to close the parting plane gap in
such a way that 0.05 filler does not pass through the parting plane
Again measure the stud/bolt length to check any extension during hammer
tightening.
Calculate revised value from the design value after incorporating any extension
happened during hammer tightening.
Remove all the previous marking on the stud/bolt, nut and nearby casing.
Mark the reference position on other side of the stud in case of double not stud.
Now hot tighten the stud/bolt as per the sequence recommended in the O&M
manual.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Allow the stud/bolt cool down to ambient temperature as measure earlier.
The process to be repeated on the specific stud/bolt which does not meet the
extension criteria.
Question No 90:
What is the procedure for carrying out extension tightening of Coupling bolt ?
Answer:
Turbine rotor Coupling bolt are extension tightened to impart uniform and additional
clamping force across coupling flange of rotor. Extreme care shall be taken to ensure
that there is no change in coupling run out (CRO) during the process. A small
deviation is also not acceptable.
The following step wise process to be adopted during coupling bolt extension
Measure the length of the coupling bolt in free condition with outside
micrometer.
Coupling run out has been achieved within the design requirement.
Measure the coupling bolt length again after coupling and check for any
extension.
Coupling bolt extension shall be done with hydraulic torque wrench. Manual
extension with OH crane is not permitted.
Carry out 25% extension of four coupling bolt diagonally opposite and 90 deg
apart with hydraulic torque wrench. Record the torque required for 25 %
extension.
Carry out 50 % extension of same four bolt and check CRO reading for any
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
change. Record the torque required for 50% extension.
Repeat the process for another four diagonally opposite bolt equally spaced from
earlier four bolt.
Complete extension of all the coupling bolt up to 50 % extension and ensure there
is no variation in CRO reading.
After completion of 50% extension Carry out 100 % extension and check for
CRO reading deviation after extension of four bolt each time.
Question No 91:
What are the checks to be carried out after lifting of turbine casing before assembly?
Answer:
(a) Make sure that there are no damages and burrs on the horizontal joint surfaces.
(b) Make sure that there are no damages and burrs on the tongue-groove joint surfaces
and the horizontal joint surfaces. To make flat on the tongue-groove joint surfaces,
use oilstone, if required.
2. Coat the horizontal joint surfaces with linseed oil. Coat the tongue-groove joint
surfaces and touched surfaces between dowel pins and seal rings with lubricants.
Adjust level of the horizontal joint surfaces by the use of chain block while the casing
is kept lifted by crane.
Question No 92:
How correction is carried out if radial clearances of turbine rotor against a diaphragm
found less in one side only? (all other side as per requirement)
Answer:
If there is no margin for adjustment of radial clearances found less in one side,
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Scrapping of packing segment fin shall be done to increase the clearance.
Question No 93:
Answer:
Reference rotor position reference seal bore reading is recorded during pre-centering
of rotor. Piano wire of 0.5 mm dia with 20 kg plumb block shall be used. Piano wire
shall be set at rotor seal bore position to replicate rotor center line along the casing
and diaphragms.
Question No 94:
Answer:
Right and left are determined when viewed from the turbine front toward
generator.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Where X=Sag (1/100 mm), A= Distance from the support (mm)
L=Total length of Piano wire (mm), W=Weight of piano wire per unit (kg)
0.00154 kg/m for 0.5 dia wire.
Question No 95:
Answer:
HP inner casing is mounted on the HP outer casing at 4 points, and HP inner casing
height is adjusted with liner structure at the 4 points. HP inner casing is keyed to HP
outer casing in turbine axial direction with rebbet fit structure.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
HP inner casing is keyed to the HP outer casing in perpendicular direction to the
turbine axis with gib key structure and center key structure
Question No 96:
Answer:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
HP/IP outer casing is keyed to the axial direction on bearing standard. In Hitachi and
Toshiba make turbine Bearing standard 1, 2 are sliding pedestal and Bearing standard
3 is fixed one. Expansion of IP casing push the standard 2 towards HPT and
Expansion of HP casing further pushes the standard 1 towards turbine side. Axial key
basically transfer thermal expansion to thrust force to slide the pedestal in the
direction of expansion
Question No 97:
What is the difference tap stud and through stud? (far casing parting plane fastener)
Answer:
Tap stud and through stud both are mainly fasteners for Turbine casing and
diaphragms parting plane joint. Tap stud are directly threaded to the casing in one end
and other end is secured with nut. Through studs are secured with nuts at both ends
and stud are through from one end to other end.
Question No 98:
Answer:
Turbo machinery are installed on Concrete deck, Turbine deck are sometimes isolated
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
from its column support by vibration isolation spring set. Due to thermal growth and
different load condition decks are settled from the initial position. Bench marks are
various reference points installed in protected enclosure at both side of the turbine
deck. The elevation of each bench mark reading with reference point gives the change
and deflection of the deck from time to time. This change in position in different
condition and its effect on turbine running parameter helps to predict operating
parameter and corrective actions.
Question No 99:
How assembly key to running key change over done? what is the check point while
carrying out the change over?
Answer:
Assembly key and running key are also called Tops off and Tops on Key. Change of
Running key to assembly Key for Outer casing vertical support from upper half to
lower half. After change over casing support from running key assembly key the
change in dial indicator shall remain same. If the dial indicator put on centre of the
upper casing to rotor is changed, suitable correction shim shall be added to assembly
key to ensure that the casing position remain same,
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 100:
Answer:
In spacer type turbine coupling spacer is installed between rotor coupling flange. The
advantage of spacer type of coupling is rotor axial position can be adjusted in case of
correction is required to achieve axial clearance.
Spacer
Question No 101:
What is journal slope? What is the technical requirement for measuring journal slope?
Answer:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Turbine rotor of large steam turbine are simply supported on journal bearing. In static
condition due to static sag of rotor and different elevation of bearing, rotor journal has
different inclination at different journal position. Based on the catenary and static sag
journal slope is calculated and indicated in the alignment diagram. Measurement of
journal slope indicates rotor position and elevation of different bearing.
Question No 102:
What are the important checks to be carried out in elliptical type journal bearing?
Answer:
Visual check for Babbitt metal for wipe or recess & for scratch.
Liquid penetrant test Babbitt metal for crack.
Visual inspection Contact to journal of shaft on both upper and lower bearings.
Assembly checks
Top and side oil clearance in both in board and out board side.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
What is ball seat clearance in elliptical journal bearing?
Answer:
Ball seat clearance in self-aligning elliptical journal bearing is the clearance between
babbitt liner inner ring to bearing housing outer ring clearance. This clearance allow
spherical movement of bearing with the movement of rotor.
Question No 104:
Answer:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
The following checks shall be carried out in turbine coupling bolt:
Hardness check
Question No 105:
Answer:
Run out of coupling bolt shall be carried out on a surface plate after placing it on V
block. Dial is set on top surface of the bolt and run out measured along the length.
Question No 106:
What is the reference check required for rotor before taking alignment and CRO
reading for rotor supporting of tilting pad bearing?
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Answer:
In tilting pad bearing rotor position can be changed during rotation. While taking
measurement for alignment and Coupling run out rotor shall be in centre position of
the bearing.
Question No 107:
What is the acceptance criteria for top oil and side oil clearance?
Answer:
Question No 108:
What is guide rail w.r.t pedestal? what shall be the ideal clearance on guide rail?
Answer:
Guide rail is required for sliding type of pedestal, which is sliding along with casing
expansion. Normally the clearance between guide rail and pedestal base shall be 0.13
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
to 0.18 mm
Question No 108:
What is sensitized packing ring ? What are the advantage of sensitized packing ?
Answer:
Sensitized packing are labyrinth packing ring segment with high low fin, for turbine
moving blade tip, inter stage and gland packing are.
As the packing float on weaker spring, there is less impact force and avoid severe
packing fin damage.
Reduce risk of rubbing and eliminate local heating of rotor. Less transient
vibration.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Sensitized packing operating condition during unit start up and on load operation
Question No 109:
Answer:
Vortex shedder are applied on labyrinth packing, it lowers the pressure on the
upstream side of the seal. This is accomplished by creating turbulent flow or vortices.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Question No 109:
Answer:
Thrust bearing active pad indicates the working pad, the normal tendency op rotor is
to move toward working when turbine loading is done.
Question No 110:
What is the zero position for coupled rotor train? (for Toshiba/Hitachi Turbine)
Answer:
The zero position is the position of rotor when pushed toward front pedestal and the
gap between thrust collar and generator side thrust pad is zero.
Question No 111:
What is the process to be adopted for elliptical bearing outer ring support pad to
pedestal colour contact check?
Answer:
Elliptical bearing is divided into two parts, one is inner ring in which babbitt material
is lined another is outer ring with spherical contact surface with inner ring and
spherical pad support on pedestal housing.
For checking the outer ring support pad contact with pedestal housing, following steps
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
are taken.
4. Outer ring top half is placed and parting plane bolt are fastened.
6. If 0.03 mm does not pass through any of the pad, then dismantle and check the
contact area.
7. If 0.03 filler pass through any of the pad, add 0.03 mm shim on that pad and repeat
the procedure again.
Question No 112:
Answer:
Minimum 0.20 to 0.50 mm rotor lifting is required for easy removal of bearing
Question No 113:
Answer:
The following are the main factor for changing the bearing load during unit operation
1. Condenser vacuum
Question No 114:
Answer:
Temporary bow of rotor can occur due to annular contact with stationary component.
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)
Corporate Operation Services – Steam Turbine
Once rotor contacts localized heat is generated and because of thermal gradient
temporary bow of rotor occurs. Generally the rotor bow died out once contact point
rubs out.
Question No 115:
What is the significance of inner and outer surface temperature of inner casing of
HP/IP turbine ?
Question No 116:
Answer:
Main Turbine assembly & maintenance (Hitachi & Toshiba – 800 MW unit)