Group No.

: 3 Members: Monterde, Darlene Kate


Course & Year: BSCE-3 Sarvida, Jeremy L.
Tuba, Jullifer Joseph O.

Project Name: Proposed One - Storey Residential


Location: National Highway, Poblacion West, Moalboal Cebu
Name of Owner: Dr. Rober Forger, M.D.
Project Contractor : Westalis Construction

Perspective:
REPUBLIC OF THE PHILIPPINES
Department of Public Works & Highways

N OFFICE OF THE BUILDING OFFICIAL


MUNICIPALITY OF MOALBOAL

RECOMMENDING APPROVAL:

W E

PE
HEAD SECTION DATE:
APPROVED BY:

RP
4

E TU
BUILDING OFFICIAL DATE:

4.
60 S LAND USE AND ZONING

AL
2.
NE 10
3.

99
LI

RO
TY
ER HEAD : DATE:
OP

A
PR

D
LINE AND GRADE

00

RI
PR
9.

3.

OP

G
00

BU
3

11
FO

HT
ER
.5
HEAD : DATE:

TY
IL PRI

0
OT
ARCHITECTURAL

DI N
00

OF
LI
2.

N
NG T

E
92
2. 42

W
9.
4.

AY
0
HEAD :
85
DATE:

15 4. CIVIL / STRUCTURAL

2.
4.

(3
50

. 00
00
2.
O

M
MOALBOAL
ED

THIS HEAD : DATE:

A
PR
GUESTHOUSE

ET
RO - TOL

LO 53.
ELECTRICAL

OP
SITE

=
00
AD

3.

ER
I

T 0S
ER
RIL

4
TY
BA

51 Q

S
TO

LI

)
3- .M
NE
50 50
HEAD : DATE:

1. 1.

B
YAMAHA 1 MECHANICAL

PREMIO

.
E
LIN HEAD : DATE:
TY
AY

SANITARY
MCDONALD'S ER
W

OP
GH

PR
HI
L

GAISANO GRAND
NA

MALL MOALBOAL
TIO

N HEAD : DATE:
NA

2 PLUMBING
TECHNICAL DESCRIPTION
PHOENIX PETRON
LINES BEARINGS DISTANCES

W E HEAD :
ELECTRONICS
DATE:
L
L H AL
AL
CI BO

S HEAD : DATE:
NI AL
PA

GEODETIC ENGINEER
MU MO
TO

HEAD : DATE:

DR. ROBERT FORGER, M.D.


- 2022
REPUBLIC OF THE PHILIPPINES
Department of Public Works & Highways
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF MOALBOAL

RECOMMENDING APPROVAL:

A B C A B C HEAD SECTION DATE:


APPROVED BY:

9.00 9.00
BUILDING OFFICIAL DATE:
4.30 4.70 1.00 4.30 4.70 1.00
3.30 2.50

1.70 1.00

1.70 1.00
W2
5 D3 5
1.70
1.40

1.70
W3
D4 KITCHEN
4 4

5.20

5.20
D2
5.50 5.50
3.50

3.50

3.50

3.50

3.50
W1 BEDROOM 2 DINING W1
9.00

9.00
4.00

3 3
11.50

11.50

11.50

11.50
4.00
4.55
3.80

3.50

3.80

3.80

3.80
W1 BEDROOM 1 LIVING W1

6.30

6.30
D2
D1
2 2

1.00
W1 W1
2.50

2.50

2.50

2.50
ENTRY
PORCH 3.43 3.43
4.15

2.50
1 1

1.00
4.30 4.70
9.00 4.30 4.70 1.00
9.00

A B C A B C

DR. ROBERT FORGER, M.D.


- 2022
REPUBLIC OF THE PHILIPPINES
Department of Public Works & Highways
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF MOALBOAL

A B C RECOMMENDING APPROVAL:

9.00
1.00 4.30 4.70 1.00 HEAD SECTION DATE:
APPROVED BY:
+6.40m APEX OF ROOF +6.40m APEX OF ROOF

0.85
1.65 0.85

1.65 0.85
0.85
+5.55m EDGE OF LOWER ROOF +5.55m EDGE OF LOWER ROOF BUILDING OFFICIAL DATE:

2.50

2.50
+3.90m BOTTOM OF +3.90m BOTTOM OF
ROOF EAVES/ GUTTER ROOF EAVES/ GUTTER

6.40

6.40
5.55

5.55
W1 W1 D1

3.50

3.50
3.90

3.90
F F

+0.40m GROUND FLOOR LINE +0.40m GROUND FLOOR LINE

+0.00m NATURAL GRADE LINE +0.00m NATURAL GRADE LINE


0.40

0.40
0.35
5 4 3 2 1
11.50
1.00 1.70 3.50 3.80 2.50 1.00
+6.40m APEX OF ROOF +6.40m APEX OF ROOF
0.85
0.85

1.65 0.85
0.85
+5.55m EDGE OF LOWER ROOF +5.55m EDGE OF LOWER ROOF
2.50

2.50
1.65

+3.90m BOTTOM OF +3.90m BOTTOM OF


ROOF EAVES/ GUTTER ROOF EAVES/ GUTTER
6.40

6.40
5.55

5.55
W3 W1 W1
3.50

3.50
3.90

3.90
F F

+0.40m GROUND FLOOR LINE +0.40m GROUND FLOOR LINE

+0.00m NATURAL GRADE LINE +0.00m NATURAL GRADE LINE


0.40

0.40
0.35

DR. ROBERT FORGER, M.D.


-2022
REPUBLIC OF THE PHILIPPINES
Department of Public Works & Highways
OFFICE OF THE BUILDING OFFICIAL

C B A
MUNICIPALITY OF MOALBOAL

RECOMMENDING APPROVAL:

9.00
1.00 4.70 4.30 1.00
HEAD SECTION DATE:
+6.40m APEX OF ROOF +6.40m APEX OF ROOF APPROVED BY:

0.85
0.85

1.65 0.85
0.85
+5.55m EDGE OF LOWER ROOF +5.55m EDGE OF LOWER ROOF

2.50

2.50
BUILDING OFFICIAL DATE:

1.65
+3.90m BOTTOM OF +3.90m BOTTOM OF
ROOF EAVES/ GUTTER ROOF EAVES/ GUTTER

6.40

6.40
5.55

5.55
D3
W2

3.50

3.50
3.90

3.90
A A A

+0.40m GROUND FLOOR LINE +0.40m GROUND FLOOR LINE

+0.00m NATURAL GRADE LINE +0.00m NATURAL GRADE LINE


0.40

0.40
1 2 3 4 5
11.50
1.00 2.50 3.80 3.50 1.70 1.00
+6.40m APEX OF ROOF +6.40m APEX OF ROOF
0.85
0.85

1.65 0.85
0.85
+5.55m EDGE OF LOWER ROOF +5.55m EDGE OF LOWER ROOF
2.50

2.50
1.65

+3.90m BOTTOM OF +3.90m BOTTOM OF


ROOF EAVES/ GUTTER ROOF EAVES/ GUTTER
6.40

6.40
5.55

5.55
W1 W1
3.50

3.50
3.90

3.90
F F

+0.40m GROUND FLOOR LINE +0.40m GROUND FLOOR LINE

+0.00m NATURAL GRADE LINE +0.00m NATURAL GRADE LINE


0.40

0.40
0.35

DR. ROBERT FORGER, M.D.


- 2022
REPUBLIC OF THE PHILIPPINES
Department of Public Works & Highways
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF MOALBOAL

A B C RECOMMENDING APPROVAL:

9.00
1.00 4.30 4.70 1.00 HEAD SECTION DATE:
APPROVED BY:
+6.40m APEX OF ROOF +6.40m APEX OF ROOF

0.85
0.85

1.65 0.85
0.85
+5.55m EDGE OF LOWER ROOF +5.55m EDGE OF LOWER ROOF BUILDING OFFICIAL DATE:

2.50

2.50
1.65

0.40
+3.90m BOTTOM OF +3.90m BOTTOM OF
ROOF EAVES/ GUTTER ROOF EAVES/ GUTTER

6.40

6.40
5.55

5.55
D3
W2

3.50

3.50
3.90

3.10

3.90
A A A

+0.40m GROUND FLOOR LINE BEDROOM 1 LIVING +0.40m GROUND FLOOR LINE

+0.00m NATURAL GRADE LINE +0.00m NATURAL GRADE LINE


0.40

0.40
5 4 3 2 1
11.50
1.00 1.70 3.50 3.80 2.50 1.00
+6.40m APEX OF ROOF +6.40m APEX OF ROOF
0.85
0.85

1.65 0.85
0.85
+5.55m EDGE OF LOWER ROOF +5.55m EDGE OF LOWER ROOF
2.50

2.50
1.65

0.40

+3.90m BOTTOM OF +3.90m BOTTOM OF


ROOF EAVES/ GUTTER ROOF EAVES/ GUTTER
6.40

6.40
5.55

5.55
W1 W1
3.50

3.50
3.90

3.10

3.90
F F

+0.40m GROUND FLOOR LINE KITCHEN DINING LIVING PORCH +0.40m GROUND FLOOR LINE

+0.00m NATURAL GRADE LINE +0.00m NATURAL GRADE LINE


0.40

0.40
0.35
DR. ROBERT FORGER, M.D.
-2022
REPUBLIC OF THE PHILIPPINES
Department of Public Works & Highways
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF MOALBOAL

A B C A B C RECOMMENDING APPROVAL:

HEAD SECTION DATE:


APPROVED BY:

9.00 9.00
4.30 4.70 1.00 4.30 4.70 1.00 BUILDING OFFICIAL DATE:

3.30 2.50

1.70 1.00

1.70 1.00
0.40
PL
5
W2
5 PL PL

0.70
D3 1.65
T&B
1.70
1.40

1.70
W3 30X30 FLOOR TILES T&B
ANTI-SKID TILE
+0.35 ELEV
D4 KITCHEN PL CEILING
MANHOLE PL PL PL
4 60X60 FLOOR TILES
+0.40 ELEV 4 0.40
KITCHEN

5.20
5.20

0.40
D2 0.40
SL
PL PL PL

3.50

3.50
3.50

3.50

3.50
BEDROOM 2 DINING 0.40 0.40
W1
60X60 FLOOR TILES 60X60 FLOOR TILES
W1 BEDROOM 2 DINING
+0.40 ELEV +0.40 ELEV

9.00

0.40
9.00

4.00 PL PL
PL

0.70
PL
3 3

11.50

11.50
PL
11.50

11.50
4.00

0.40
PL PL PL
4.55 PL

3.80

3.80
LIVING
3.80

3.50

3.80
BEDROOM 1 0.40 0.40 0.40 SL 0.40
W1 60X60 FLOOR TILES 60X60 FLOOR TILES W1
BEDROOM 1 LIVING
+0.40 ELEV +0.40 ELEV

6.30
PL PL PL

6.30
D2

2 D1
2

0.40

0.40
1.00
W1 W1 PL

0.40
0.40 0.40

2.50

2.50
ENTRY
2.50

ENTRY PORCH
60X60 FLOOR TILES
2.50 PORCH
PL PL
ANTI-SKID TILE 4.15

2.50
+0.35 ELEV

1 1

0.40

1.00
PL PL
4.30 4.70
9.00 4.30 4.70 1.00
9.00

A B C A B C

DR. ROBERT FORGER, M.D.


-2022
1.20 REPUBLIC OF THE PHILIPPINES
Department of Public Works & Highways
0.60 0.60 OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF MOALBOAL
4.70 0.90 2.50 1.56 0.74
0.10 RECOMMENDING APPROVAL:
0.15 1.00 0.43 2.40 0.43 0.15 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.36 0.40 0.40
D3 W1

2.10
W2

0.55

0.55
HEAD SECTION DATE:
APPROVED BY:
D3
RANGE KS A W2 A

0.95

0.95
2.35

2.35
1.70
BUILDING OFFICIAL DATE:

2.55
1.20

0.85

0.85

0.70
0.85
REF
2.50 0.40 0.40 0.40 0.40 0.30 0.60 0.40 0.40

2.50 0.60 0.95

KITCHEN PLAN ELEVATION - A ELEVATION - B TYPICAL CABINET PLAN

3.30

0.85

0.85

0.85

0.85

0.85
1.20 0.60 1.00 0.50

0.95
1.20

1.20
0.43
0.28

D4 W3

0.60

0.60
0.60

3.00

3.00

3.00
3.05

3.05

3.05

3.05

3.05
1.40

1.40
0.70

W3

2.15

2.15

2.15
0.80

2.10
T&B

1.85

1.85
D4
1.60

1.60
0.05

0.05

0.05
0.28

1.20 2.10
3.30

TOILET & BATH PLAN ELEVATION - A ELEVATION - B ELEVATION - C ELEVATION - D

SCHEDULE OF WINDOWS SCHEDULE OF DOORS


MARK W1 W2 W3 MARK D1 D2 D3 D4
1.00 0.90 1.00 0.80
1.80 2.40 0.70 0.90 0.80 0.90 0.70
0.73 0.75 0.73
0.60
1.25

0.60

F
A A A
2.15

2.15

2.15

2.15

2.15

2.15
2.10

2.10

2.10

2.10
1.80

1.55
1.20

0.90 0.90
0.90

ELEVATION ELEVATION ELEVATION


FIN. FLR. FIN. FLR. ELEV. ELEV. ELEV. ELEV.
LN. LN.
1.80 0.90

PLAN PLAN PLAN 0.90 PLAN 0.80 PLAN 0.90 PLAN 0.70 PLAN
CLEAR CLEAR CLEAR CLEAR
LOCATION BEDROOM 1 & 2, LIVING, DINING KITCHEN TOILET & BATH LOCATION LIVING MAIN DOOR BEDROOM 1 & 2 KITCHEN DOOR TOILET & BATH
NUMBER 6 SETS 1 SET 1 SET NUMBER 1 SET 2 SETS 1 SET 1 SET
TYPE SLIDING WINDOW WITH FIXED GLASS AWNING WINDOW JALOUSIE WINDOW TYPE SOLID DOOR SOLID DOOR SOLID DOOR PVC DOOR
FINISH ALL OPENING PROVIDE MOSQUITO SCREEN ALL OPENING PROVIDE MOSQUITO SCREEN ALL OPENING PROVIDE MOSQUITO SCREEN FINISH PROVIDE MOSQUITO SCREEN PROVIDE MOSQUITO SCREEN

DR. ROBERT FORGER, M.D.


REPUBLIC OF THE PHILIPPINES
OFFICE OF THE BUILDING
ELECTRICAL NOTES: N OFFICIAL

O
MOALBOAL

ED
ALL ELECTRICAL WORKS AND INSTALLATIONS HEREIN SHALL BE EXECUTED THIS GUESTHOUSE
MOALBOAL, CEBU

RO - TOL
SITE RECOMMENDING APPROVAL :

AD
IN ACCORDANCE WITH THE LATEST APPROVED EDITION OF THE

ILI
AR
PHILIPPINE ELECTRICAL CODE AND REGULATIONS OF THE LOCAL

B
TO POWER SUPPLY

TO
HEAD ELECTRICAL SECTION DATE
AND NATIONAL AUTHORITIES CONCERNED IN THE ENFORCEMENT W E
YAMAHA APPROVED BY :
OF ELECTRICAL LAW AND ORDINANCES PREMIO

WORKMANSHIP SHALL BE EQUAL TO THE BEST STANDARD PRACTICED @ 25mm RSC BUILDING OFFICIAL DATE
ADOPTED AND RECOGNIZED IN THIS TRADE
S

AY
MCDONALD'S
"PB"

HW
ALL MATERIALS TO BE USED SHALL BE NEW AND APPROVED TYPE TO

IG
LH
GAISANO GRAND
ANY PURPOSE INTENDED. ALL WIRES TYPE TW/THW SHALL BE

NA
MALL MOALBOAL

IO
40 AT

T
INSULATED FOR 600VOLTS.

NA
NO BRANCH CIRCUIT SHALL BE HAVE A LOAD OF MORE THAN 80% OF ITS RATING 2 POLE,230 VOLTS
PETRON

ELECTRICAL SERVICE REQUIREMENTS SHALL BE 220 VOLTS,1-PH 60HZ, SUPPLY


PHOENIX

10 AT 10 AT
LEGEND:
2 POLE 2 POLE A 1-GANG SWITCH
ADEQUATE AND EFFECTIVE GROUNDING SHALL BE DONE TO METALLIC
CONDUITS, CABINETS AND EQUIPMENTS 1 2 AB
VICINITY MAP 2-GANG SWITCH

L
L H AL
1

AL
CI BO
ALL ELECTRICAL INSTALLATIONS HEREIN SHALL BE DONE UNDER THE LIGHTS LIGHTS

NI AL
NOT TO SCALE

PA
E-1 ABC 3-GANG SWITCH
10 AT 30 AT

MU MO
SUPERVISION OF A DULY LICENSED ELECTRICAL ENGINEER

TO
2 POLE 2 POLE A(3-W) 3-WAY SWITCH

3 4
SCHEDULE OF LOADS PANEL BOARD

"PB A1 END UNIT A", 2 POLE, 240V, FLUSH MOUNTED, MINI CIRCUIT BREAKER WITH GROUNDING TERMINAL LIGHTS RANGE
20 AT 20 AT KWH METER

CKT. UNIT TOTAL I BRK NO. OF 2 POLE 2 POLE


LOAD DESCRIPTION WIRE SIZE CONDUIT SIZE KAIC
NO. QTY VOLT-AMP AB SIZE POLE 5 6 FLOUR. LIGHT

LIGHT CIRC.
1 50W SL, 20W PL 10 230 1.05 10 AT 2 10 REF C.O.
2 50W SL, 20W PL
20 AT 20 AT PL PINLIGHT
10 230 1.05 10 AT 2 10 2 POLE 2 POLE
WL WALL MOUNTED EXTERIOR LIGHTS
3 20W PL 9 180 0.91 10 AT 2 10 7 8
1 CONVENIENCE OUTLET(SINGLE)
4 RANGE 1 1500 6.82 30 AT 2 10 C.O. C.O.
5 REF 1 500 2.27 20 AT 2 10
20 AT 20 AT 2 CONVENIENCE OUTLET(DUPLEX)

2 POLE 2 POLE
3 CONVENIENCE OUTLET(TRIPLEX)
6 C.O. 8 1600 7.27 20 AT 2 10 9 10
REF CONVENIENCE OUTLET(REF)
7 C.O. 7 1400 6.36 20 AT 2 10 ACU ACU
RANGE CONVENIENCE OUTLET(RANGE)
8 C.O. 4 800 3.63 20 AT 2 10
2 POLE 2 POLE
9 WACU 3/4 HP 1 1107 5.03 20 AT 2 10 11 12
SPARE SPARE
10 WACU 3/4 HP 1 1107 5.03 20 AT 2 10 WP WATER PROOF CONVENIENCE OUTLET
SPARE SPARE
11 SPARE/ BLANK WH MULTI-POINT WATER HEATER
- - - - - - - 10
CTV CABLE/TV
12 SPARE/ BLANK - - - - - - - 10
MAIN BREAKER & FEEDER 8,654 39.42 40 AT 2 18 TEL TELEPHONE/INTERNET

ACU 3/4HP AIRCON CONVENIENCE OUTLET


MAIN FEEDER DESIGN " PB"
MAIN BREAKER DESIGN CAPACITY " PB1":
TOTAL CONNECTED LOAD = 39.42 AMPERES ACU 1HP AIRCON CONVENIENCE OUTLET

= 31.54 + (1.5 X 5.03)


COMBINED DEMAND AND LOAD FACTOR = 80%
= 39.08 AMPS
1 SINGLE LINE DIAGRAM PT PRESSURE TANK
DEMAND = 39.42 X 0.80 = 31.54 AMP USE : 40 AT, 2 P, 230 V, 18 KAIC E-1
NOT TO SCALE

WH WATER HEATER
WIRE SIZE = 1.25 x 31.54 = 39.42 AMPERES

USE =

DESIGNED BY:
PROFESSIONAL ELECTRICAL ENGINEER S E A L PROJECT : PROJECT OWNER: S H E E T N O.

DRAFTED BY:
JONATHAN A. VILLAFLOR
PRC. CERT. NO.: 1790 TIN : 129-974-804
A PROPOSED ONE STOREY RESIDENTIAL HOUSE DR. ROBERT FORGER,
EARL EDRIS CANTILA M.D. DATE:
CSC
E
PTR NO.: 3226248 DATE ISSUED: -2022
01-04-2021
2022
2021

ADDRESS : LAMAC, CONSOLACION PLACE ISSUED: CONSOLACION


LOCATION: NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU P. CABARON, POBLACION WEST, MOALBOAL, CEBU
1 2
REPUBLIC OF THE PHILIPPINES
OFFICE OF THE BUILDING
OFFICIAL

A B C A B MOALBOAL, CEBU

RECOMMENDING APPROVAL :

HEAD ELECTRICAL SECTION DATE

APPROVED BY :

9.00
BUILDING OFFICIAL DATE

1.00 4.30 4.70 1.00 9.00


4.30 4.70
1.70 1.00

1.70 1.00
m k PL k WP CO WP CO

5 PL
g,h j,k,m
PL
5

1.70

1.70
RANGE GFCI/WPCO GFCI/WPCO
l GFCI/WPCO
PB-4
l T&B j j j
PL CEILING
MANHOLE PL PL PL KITCHEN
CO
4 KITCHEN
i
4 ACU 3/4HP
CO
CO
PB-8
PB-5 REF

5.20
5.20
n SPLIT TYPE
h SL h PB-11
PL n,o PL PL

3.50

3.50
3.50

3.50
BEDROOM 2 DINING
BEDROOM 2 DINING
g g
m

9.00
9.00

o PL PL CO

PL PL PB-2 CO
f
3 j 3

11.50

11.50
11.50

11.50
c PL CO CO
d ACU 3/4HP CO

p PL PL PL SPLIT TYPE PB-7 PB-6


PB-10 CO
PL e

3.80

3.80
1.00 3.80

3.80
SL BEDROOM 1 CTV LIVING
BEDROOM 1 TEL
p,q c LIVING CO
d

6.30
6.30
PL q PL PL CO
c,d e,f CO CO PB
PB
2 r
PL a,b,r
2 WP CO
a a

2.50

2.50
ENTRY ENTRY
2.50

2.50
PL PORCH PL PORCH
1.00

4.15
2.50

1 b
PL
PB-3 PB-1
PL
b 1
4.30 4.70
4.30 4.70 1.00 9.00
1 GROUND. FLOOR LIGHTING LAYOUT 9.00 2 GROUND FLOOR POWER LAYOUT
NOT TO SCALE NOT TO SCALE
E-2 E-2

A B C A B C
DESIGNED BY:
PROFESSIONAL ELECTRICAL ENGINEER S E A L PROJECT : PROJECT OWNER: S H E E T N O.

DRAFTED BY:
JONATHAN A. VILLAFLOR
PRC. CERT. NO.: 1790 TIN : 129-974-804
A PROPOSED ONE STOREY RESIDENTIAL HOUSE DR. ROBERT FORGER,
EARL EDRIS CANTILA M.D. DATE:
CSC
E
2022
2021
PTR NO.: 3226248 DATE ISSUED: 2022
01-04-2021
ADDRESS : LAMAC, CONSOLACION CONSOLACION
LOCATION: NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU P. CABARON, POBLACION WEST, MOALBOAL, CEBU
2 2
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF
PUBLIC WORKS & HIGHWAYS
OFFICE OF THE BUILDING OFFICIAL
MOALBOAL, CEBU

APPROVED:

BUILDING OFFICIAL DATE:

WATER CLOSET

FLOOR DRAIN

LAVATORY

URINAL

SHOWER DRAIN

AHU DRAIN

SLOPE SINK

WC( FLUSH VALVE)

WC( TANK TYPE)

LAVATORY

URINAL

HB

O
MOALBOAL

ED
THIS GUESTHOUSE

RO - TOL
N SITE

AD
ILI
AR
B
TO
W E YAMAHA
PREMIO

AY
MCDONALD'S

W
S

H
IG
LH
GAISANO GRAND

NA
MALL MOALBOAL

TIO
NA
PHOENIX PETRON

CARMEL ANGELI C. MATUNOG

0007364

L
L H AL
AL
CI BO
NI AL
PA
MU MO
VICINITY MAP

TO
SEAL PROJECT TITLE PROJECT OWNER: SHEET CONTENTS DESIGNED BY:
REGISTERED MASTER PLUMBER PRC NO: 0007364 SHEET NO.
AS BUILT ESTIMATE

T.I.N. : 316-323-527 DRAFTED BY BIDDING FABRICATION


CSC

CARMEL ANGELI C. MATUNOG 8902314 A PROPOSED ONE STOREY RESIDENTIAL HOUSE DR. EARL EDRISFORGER,
ROBERT CANTILA M.D. DRAWING INDEX, GENERAL NOTES, CAD LT LICENSE:
BUILDING PERMIT OWNER'S APPROVAL
P
PTR NO: LEGEND &SYMBOLS, ABBREVIATIONS, CONSTRUCTION PRESENTATION

01-04-2021
2022 EQUIPMENT SCHEDULE
DATE : IMPORTANT : THESE DRAWINGS AS INSTRUMENTS OF SERVICE ARE THE PROPERTY
AND INSTRUMENTS OF THE ARCHITECT. IT SHALL BE UNLAWFUL FOR ANY PERSON,
WITHOUT THE WRITTEN CONSENT OF THE ARCHITECT TO DUPLICATE OR COPY
1 3
CANJULAO, LAPU-LAPU CITY LAPU-LAPU CITY LOCATION: NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU P. CABARON ST., POBLACION WEST, MOALBOAL, CEBU SAID DOCUMENTS. ( R. A. 9266 SEC.36 )
PLACE
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF
PUBLIC WORKS & HIGHWAYS
OFFICE OF THE BUILDING OFFICIAL
MOALBOAL, CEBU

APPROVED:

BUILDING OFFICIAL DATE:

A B C A B C A B C
TO NEAREST
MANHOLE
9.00 9.00 9.00
4.30 4.70 4.30 4.70 1.00 4.30 4.70 1.00

1.00

1.00
MH MH MH
SEPTIC TANK
2 CU.M.
ROOF GUTTER

PROVISION
FOR RWT
VENT VENT

5
STACK STACK

DS WC DS 5 WC
5 DS WALL LINE DS
1.70

1.70

1.70

1.70

1.70

1.70
GT KS KS
SHO FD LAV SHO LAV
SD
KITCHEN KITCHEN
4 4 4

WALL LINE
ROOF GUTTER

ROOF GUTTER
5.20

5.20

5.20
5.50 5.50
3.50

3.50

3.50

3.50

3.50

3.50
BEDROOM 2 DINING BEDROOM 2 DINING
9.00

9.00

9.00
3 DS DS 3 3 DS DS
11.50

11.50

11.50

11.50

11.50

11.50
WALL LINE
3.80

3.80

3.80

3.80

1.00 3.80

3.80
BEDROOM 1 LIVING BEDROOM 1 LIVING
6.30

6.30

6.30
DS DS DS DS
2 2 2 WALL LINE
2.50

2.50

2.50

2.50

2.50

2.50
ENTRY ENTRY ROOF GUTTER
PORCH PORCH 3.43 3.43

1.00
4.15

2.50
DS DS DS DS
1 1 1
FROM
4.30 4.70 4.30 4.70 THE
NEAREST ROOF GUTTER
9.00 TO NEAREST 9.00 WATER
SOURCE
4.30 4.70 1.00
DRAINAGE
9.00

A B C A B C A B C

WATER LAYOUT DRAINAGE LAYOUT


SANITARY & DRAINAGE LAYOUT

REGISTERED MASTER PLUMBER SEAL PROJECT TITLE PROJECT OWNER: SHEET CONTENTS DESIGNED BY:
PRC NO: 0007364 L.M.P.
SHEET NO.
AS BUILT ESTIMATE

T.I.N. : 316-323-527 DRAFTED BY BIDDING FABRICATION


CSC

CARMEL ANGELI C. MATUNOG 8902314 A PROPOSED ONE STOREY RESIDENTIAL HOUSE DR.EARL
ROBERT
EDRISFORGER,
CANTILA M.D. SANITARY & DRAINAGE LAYOUT CAD LT LICENSE:
BUILDING PERMIT OWNER'S APPROVAL
P
PTR NO: CONSTRUCTION PRESENTATION
WATER LAYOUT
01-04-2021
2022
DATE : IMPORTANT : THESE DRAWINGS AS INSTRUMENTS OF SERVICE ARE THE PROPERTY
AND INSTRUMENTS OF THE ARCHITECT. IT SHALL BE UNLAWFUL FOR ANY PERSON,
WITHOUT THE WRITTEN CONSENT OF THE ARCHITECT TO DUPLICATE OR COPY
2 3
CANJULAO, LAPU-LAPU CITY LAPU-LAPU CITY LOCATION: NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU P. CABARON ST., POBLACION WEST, MOALBOAL, CEBU SAID DOCUMENTS. ( R. A. 9266 SEC.36 )
PLACE
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF
PUBLIC WORKS & HIGHWAYS
OFFICE OF THE BUILDING OFFICIAL
MOALBOAL, CEBU

APPROVED:

BUILDING OFFICIAL DATE:

SEAL PROJECT TITLE PROJECT OWNER: SHEET CONTENTS DESIGNED BY:


REGISTERED MASTER PLUMBER PRC NO: 0007364 SHEET NO.
L.M.P.
AS BUILT ESTIMATE

T.I.N. : 316-323-527 DRAFTED BY BIDDING FABRICATION


CSC

CARMEL ANGELI C. MATUNOG 8902314 A PROPOSED ONE STOREY RESIDENTIAL HOUSE DR. EARL
ROBERT
EDRISFORGER,
CANTILA M.D. CAD LT LICENSE:
BUILDING PERMIT OWNER'S APPROVAL
P
PTR NO: MISCELLANEOUS CONSTRUCTION PRESENTATION

01-04-2021
2022
DATE : IMPORTANT : THESE DRAWINGS AS INSTRUMENTS OF SERVICE ARE THE PROPERTY
AND INSTRUMENTS OF THE ARCHITECT. IT SHALL BE UNLAWFUL FOR ANY PERSON,
WITHOUT THE WRITTEN CONSENT OF THE ARCHITECT TO DUPLICATE OR COPY
3 3
CANJULAO, LAPU-LAPU CITY LAPU-LAPU CITY LOCATION: NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU P. CABARON ST., POBLACION WEST, MOALBOAL, CEBU SAID DOCUMENTS. ( R. A. 9266 SEC.36 )
PLACE
Moment Capacity of Plain Concrete Section Along XX and Z REPUBLIC OF THE PHILIPPINES
375
DEPARTMENT OF
PUBLIC WORKS & HIGHWAYS

300 #4 @243.45
#3 @120mm
C1 MARK DIMENSION
B D
(mm) BAR SCHEDULE
REMARKS mm STIRRUPS SPACING OFFICE OF THE BUILDING OFFICIAL
MOALBOAL, CEBU

375
1. CONSTRUCTION NOTES & TYPICAL DETAILS APPLY TO ALL DRAWINGS UNLESS
C1 300 300
D
B
OTHERWISE SHOWN OR NOTED, MODIFY TYPICAL DETAILS AS DIRECTED TO MEET
APPROVED:
SPECIAL CONDITIONS. 300
2. SHOP DRAWINGS WITH ERECTION & PLACING DIAGRAMS OF ALL STRUCTURAL

604
FILL FILL

1050
STEEL, MISCELLANEOUS IRON, PRE-CAST CONCRETE ETC. SHALL BE SUBMITTED

300
C1

EMBEDMENT
FOR ENGINEER'S APPROVAL BEFORE FABRICATION.
3. CONTRACTOR SHALL VERIFY ALL DIMENSIONS BEFORE ALL WORK IS TO BEGIN, 7 COLUMN SCHEDULE

300
CHECK WITH MECHANICAL & ELECTRICAL CONTRACTORS FOR CONDUITS, PIPE
SCALE NTS MTS
SLEEVES, ETC. TO BE EMBEDDED IN CONCRETE. S 1 BUILDING OFFICIAL DATE:

SHORINGS & BRACINGS OF THE STRUCTURE FOR ALL LOADS THAT MAYBE
IMPOSED DURING CONSTRUCTION. F1 #4 @243.45
F1

350

BAR POS.
38
BEAM BEAM CROSS LONGITUDINAL REINFORCEMENTS
1. ALL MATERIALS & WORKMANSHIP SHALL CONFORM WITH THE LATEST BUILDING
CODE OF AMERICAN CONCRETE INSTITUTE (ACI - 318) 1050
300X300mm STIRRUPS SPACING
2. ALL CONCRETE SHALL DEVELOP A MINIMUM COMPRESSIVE STRENGTH AT THE 50mm LEAN CONCRETE MARK WIDTH DEPTH SUPPORT MIDSPAN SUPPORT
END OF TWENTY EIGHT (28) DAYS WITH CORRESPONDING MAXIMUM SIZE
AGGREGATE & SLUMP AS FOLLOWS: TB 3 2 3
X Dir. Steel: 633.39 mm (5 #4) RB - 1 250 400 12 10
LOCATION 28 DAYS STRENGTH MAX. SIZE AGGREGATE MAX. SLUMP FOOTING ELEVATION REST @150 TO BB 2 3 2
CURBS & SLAB 2500 PSI(17.50 KPa) 1 IN. (25MM.) 4 IN. (100MM) BOTHWAYS
ON GRADE Y Dir. Steel: 633.39 mm (5 #4)
EXCEPT FOUND.

FOUNDATION, TIEBEAMS & 8 BEAM SCHEDULE


RETAINING WALL 3000 PSI(21 MPa) 3/4 IN. (19MM.) 4 IN. (100MM) BOTTOM REBAR PLAN 5 FOOTING DETAIL SCALE NTS MTS
ALL OTHERS
INCLUDING BEAMS S 1 SCALE 1:20 MTS 6 COLUMN DETAIL S 1
SUSPENDED SLABS 3000 PSI(21 MPa) 3/4 IN. (19MM.) 4 IN. (100MM) SCALE 1:20 MTS SUPPORT MIDSPAN SUPPORT
& COLUMNS S 1
3. ALL REINFORCING BARS SHALL CONFORM TO ASTM A615 GRADE 40 FOR DIA.12mm
& SMALLER BARS & GRADE 60 FOR DIA. 16 & LARGER BARS. COLUMN HOOPS ARE ALL
250 250 250
GRADE 40 BARS AND GRADE 60 FOR DIA.12mm FOR SHEARWALL VERT. BARS. 200 200 200
4. IN GENERAL, THE LATEST EDITION OF ACI-315, MANUAL OF STANDARD PRACTICE CHB WALL
DETAILING REINFORCED CONCRETE STRUCTURES SHALL BE ADHERED TO UNLESS

100
OTHERWISE SHOWN OR NOTED.

400
200

400

400
5. MAINTAIN MINIMUM CONCRETE COVER FOR REINFORCING STEEL AS FOLLOWS:

300

300

300
SUSPENDED SLABS ................................................. 3/4 IN. (19MM.)
200 O.C. 200 O.C. 200 O.C.

600
SLAB ON GRADE ......................................................1 1/2 IN. (38MM.)

300
WALLS ABOVE GRADE ..............................................1 IN. (25MM.) TIE BEAM
400
BEAM STIRRUPS & COLUMN TIES ............................1 1/2 IN. (38MM.)
START MIDDLE END

300
WHERE CONCRETE IS EXPOSED TO EARTH
BUT POURED AGAINST FORMS .................................2 IN. (50MM.)
TB - TIEBEAM REST @ 200 TO
WHERE CONCRETE IS DEPOSITED
DIRECTLY AGAINST EARTH .......................................3 IN. (75MM.)
RB - ROOF BEAM
6. SPLICES SHALL BE SECURELY WIRED TOGETHER & SHALL LAP OR EXTEND IN
ACCORDANCE WITH TABLE 1 (TABLE OF LAP SPLICE & ANCHORAGE LENGTH)
3 WALL FOOTING DETAIL 4 TIE BEAM DETAIL
SCALE 1:20 MTS SCALE 1:50 MTS
UNLESS OTHERWISE SHOWN ON DRAWINGS, SPLICES SHALL BE STAGGERED
WHENEVER POSSIBLE.
S 1 S 1
7. ALL ANCHOR BOLTS, DOWELS, & OTHER INSERTS, SHALL BE PROPERLY
POSITIONED & SECURED IN PLACE PRIOR TO PLACING OF CONCRETE.
A B C A B C
8. CONTRACTOR SHALL NOTE & PROVIDE ALL MISCELLANEOUS CURBS, SILLS,

O
STOOLS, EQUIPMENT, & MECHANICAL BASES THAT ARE REQUIRED BY THE MOALBOAL

ED
ARCHITECTURAL, ELECTRICAL, & MECHANICAL DRAWINGS. THIS GUESTHOUSE

RO - TOL
9000
9. ALL CONCRETE SHALL BE KEPT MOIST FOR A MINIMUM OF SEVEN (7) 9000
SITE

AD
CONSECUTIVE DAYS IMMEDIATELY AFTER POURING BY THE USE OF WET BURLAP, 4300 4700

I
PROVIDE

RIL
FOG SPRAYING, CURING COMPOUNDS OR OTHER APPROVED METHODS. 4300 4700
10. STRIPPING OF FORMS & SHORES: STIFFENER

BA
COLUMN
FOUNDATION ....................................................24 HRS.

TO
SUSPENDED SLAB EXCEPT WHEN
ADDITIONAL LOADS ARE IMPOSED.....................14 DAYS TB TB
WALLS/COLUMNS ..............................................24 HRS. 5 C1F1 C1F1 C1F1 5 N
YAMAHA
BEAMS ..............................................................14 DAYS
1400

1700
RB-1 RB-1

1700
PREMIO
1. ALL NON-LOAD BEARING TYPE CONCRETE BLOCKS SHALL HAVE A COMPRESSIVE
STRENGTH NOT LESS THAN 650 Psi. FOR LOAD BEARING TYPE CONCRETE BLOCKS, 4 C1F1 4 W E

RB-1

RB-1

RB-1
A MINIMUM COMPRESSIVE STRENGTH OF 1000 Psi SHALL BE DEVELOPED.

5200

5200
TB TB

AY
100 mm. THK MCDONALD'S

W
WALLS & EACH SIDE OF OPENINGS.
3500

3500
SLAB ON GRADE

H
3500

3500

IG
3. LINTEL BEAMS SHALL BEAR AT LEAST 8 INCHES (200 MM.) ON EACH SIDE OF
S

LH
MASONRY WALL OPENING. TEMP. BARS
GAISANO GRAND
9000

NA
9000
4. WALL REINFORCEMENTS SHALL BE AS FOLLOWS: MALL MOALBOAL

TIO
RB-1 RB-1
WALL THICKNESS VERTICAL REINFORCEMENT HORIZONTAL REINFORCEMENT
3 3

NA
8 IN. (200 MM.)
C1F1
11500

11500
C1F1 C1F1

11500

11500
6 IN. (150 MM.)
4 IN. (100 MM.)
PHOENIX PETRON

RB-1

RB-1

RB-1
3800

TB TB
3800
5. REINFORCING BARS SHALL BE LAPPED A MINIMUM OF 40 BAR DIAMETERS WHERE

3800

3800
SPLICED. DOWELS FROM CONCRETE FOOTINGS OR SLABS SHALL EXTEND INTO
THE BLOCK WALL A MINIMUM OF 40 BAR DIAMETERS, & DOWELS TO MATCH
VERTICAL REINFORCEMENTS OF WALL.
6300

6300
6. ALL CELLS CONTAINING REINFORCING BARS OR INSERTS SHALL BE SOLIDLY C1F1 C1F1 C1F1 RB-1 RB-1
FILLED WITH CONCRETE GROUT. (REFER TO SPECIFICATIONS)
2 TB TB 2

L
1. FOUNDATION IS DESIGNED FOR AN ASSUMED ALLOWABLE SOIL BEARING

L H AL
AL
RB-1

RB-1
2500

2500

CAPACITY OF 200 KPa.

CI BO
2500

2500
2. FOUNDATION SHALL REST ON NATURAL SOIL. UNLESS OTHERWISE NOTED BY

NI AL
PA
THE ENGINEER, NO PART OF THE FOUNDATION SHALL REST ON FILL.
C1F1 C1F1

MU MO
3. THE CONTRACTOR SHALL NOTIFY THE ENGINEER AFTER FOOTING EXCAVATION RB-1
1 1

TO
HAVE BEEN COMPLETED & PRIOR TO CONCRETING TO CONFIRM THE DESIGN

4300 4700
4300 4700
9000
9000
1 FOUNDATION PLAN 2 ROOF BEAM LAYOUT 3 VICINITY MAP
SCALE 1:100 MTS SCALE NTS MTS
S 1 SCALE 1:100 MTS
A B C S 1
A B C S 1

DESIGNED BY: THIS DRAWING IS ISSUED FOR:


CIVIL ENGINEER PRC NO : 0130862 SEAL PROJECT TITLE APPROVED BY : SHEET CONTENTS SHEET NO.
AS BUILT ESTIMATE
DRAFTED BY:
T.I.N. : 472-445-246 1. FOUNDATION PLAN 7. COLUMN SCHEDULE BIDDING FABRICATION

S
CSC
2. ROOF BEAM LAYOUT 8. BEAM SCHEDULES BUILDING PERMIT OWNER'S APPROVAL
CAD LT LICENSE:
CRISPANIE B. TABIGUE PTR NO.: 3807239 A PROPOSED ONE STOREY RESIDENTIAL HOUSE EARL
DR. EDRISFORGER,
ROBERT CANTILAM.D. 3. WALL FOOTING DETAIL CONSTRUCTION PRESENTATION

PROJECT OWNER 4. TIE BEAM DETAIL


DATE : 2022
01-26-2021 5.
6.
FOOTING DETAIL
COLUMN DETAIL
1 2
POOC, TALISAY CITY, CEBU PLACE : TALISAY CITY NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU P. CABARON ST., POBLACION WEST, MOALBOAL, CEBU
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF

A B C
PUBLIC WORKS & HIGWAYS

OFFICE OF THE BUILDING OFFICIAL


MOALBOAL, CEBU
9000
APPROVED:
4300 4700

BUILDING OFFICIAL DATE:

5 T-1

1700
4 533
5

5200
T-1

2230
3500

3500
9000

200

200
11500

11500
T-1
234 600 700 800 800 900 900 900 900 800 800 700 600 234
3800

3800
T-1

6300
T-1
2 HT-2 309
1

1376
2500

2500
C-PURLINS
C 100X50X15X1.5mm
SPACED @ 0.80m O.C.

200

200
1 T-2
234 825 900 900 900 900 800 259
4300 4700
1 ROOF FRAMING PLAN
9000
S 2 SCALE 1:70 MTS
T-2
A B C 309
1

1376
WEB - 2"x2" x 81"
3
TC - 2"x2" x 16 "
ROOF INSULATION: USE 5-MM THICK DOUBLE
ALUMINUM FOIL ON FOAM INSULATION

200
USE PREPAINTED HI-RIB
TYPE G.I METAL ROOFING
234 825 900 900

TOP OF BEAM
HT-2 3 TRUSS DETAIL
SCALE 1:40 MTS
S 2
BC - 2"x2" x 81"

PRE-PAINTED G.I. GUTTER


3
TOP OF WINDOW JAMB 2"x2" x 16 "

2 ROOF DETAIL
SCALE NTS MTS
S 2

DESIGNED BY: THIS DRAWING IS ISSUED FOR:


CIVIL ENGINEER PRC NO : 0130862 SEAL PROJECT TITLE APPROVED BY : SHEET CONTENTS SHEET NO.
AS BUILT ESTIMATE
DRAFTED BY:
T.I.N. : 472-445-246 1. ROOF FRAMING PLAN BIDDING FABRICATION

S
CSC
BUILDING PERMIT
2. ROOF DETAIL OWNER'S APPROVAL
CAD LT LICENSE:
CRISPANIE B. TABIGUE PTR NO.: 3807239 A PROPOSED ONE STOREY RESIDENTIAL HOUSE EARL
DR. EDRIS
ROBERT CANTILA
FORGER, M.D. 3. TRUSS DETAIL
CONSTRUCTION PRESENTATION

PROJECT OWNER
DATE : 2022
01-26-2021 2 2
POOC, TALISAY CITY, CEBU PLACE : TALISAY CITY NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU P. CABARON ST., POBLACION WEST, MOALBOAL, CEBU
SCOPE OF WORK

The contents of this section centers on the work of Contractor: Group 3 for the Project 1-Storey
Residential House. The contractors hereby claim responsibility for providing all necessary equipment,
tools, manpower including its proper supervision, testing devices, mobilization and transport of
necessary materials, installation of consumable supplies services, and all other costs pertaining to the
Pre-construction works, Structural Works, Architectural works, and etc. The specifications of the
equipment and materials, as well as the methodologies to be employed are provided within this section.

I. Site preparation

- The required facilities, equipment, manpower, materials, their mobilization and


transport, etc. essential for the implementation of the site preparation will be provided
by the Contractor.

1. Clearing and Grubbing


- The Contractor will provide all necessary equipment and tools required to
implement the clearing and grubbing of the site, along with the manpower, their
safety equipment, supervision, and etc. The contractor will complete the following
tasks: removal and disposal of trees, stumps, roots, logs, shrubs, grass, weeds, fallen
timber, miscellaneous surface litter, wherever they occur within the specified areas
staked out by the engineer.

1.1 Specifications:

a.) Equipment:
⮚ Backhoe – The contractor will provide 1 backhoe, along with 1
operator and 1 assistant laborer. It will be mobilized on site for 3
days to cover any necessary excavation for the clearing and
grubbing.
⮚ Dump Trucks – a 10 cubic meter dump truck will be mobilized
for 5 working days to dispose of waste materials at the end of
every day.
⮚ Wheelbarrows – The contractor will provide 15 wheelbarrows.

⮚ Ropes, cables, chains and pulleys

⮚ Miscellaneous hand tools, including:


o Shovels,
o Trowels,
o Pry bars,
o Axes
o Etc.
⮚ Safety equipment including:
o Gloves,
o Hard hats,
o Work boots,
o Etc.
b.) Methodology
⮚ The site will be divided into three major areas, (east, middle,
and west). The clearing and grubbing work will be started in the
east area first.
⮚ All identifiable vegetation within the site will be uprooted and
disposed of; trees will be cut down and roots taken out, except
the ones specified to be left alone by the engineer and owner of
the project. The contractor will obtain a burning permit
beforehand, and thus the collected organic material will be
burned on-site, in the area farthest from the direction of the
public right of way and from any nearby trees and shrubs.
⮚ The Contractor will remove pre-existing concrete, rebars,
boulders, jutting rocks, and protruding topsoil from the grade
line, and other materials on site. These will be collected and
piled in the east side of the site, so as to make it accessible to
dumptrucks for disposal.
⮚ The burning of vegetative materials and the disposal of solid
materials (concrete, soil, rocks, etc.) will be carried out
simultaneously before the end of every working day, at around
4pm.
⮚ The clearing and grubbing is estimated to be completed within 5
working days.

2. Installation of Temporary Facilities


- The contractor will put up and install temporary facilities to aid in the construction
phase of the project. This includes public comfort rooms, storehouse, barracks, etc.
The contractor will provide the necessary equipment and manpower necessary to
complete this task.

2.1 Specifications:

a.) Equipment & materials:


⮚ Pickup trucks – The contractor will also provide 1 driver and
1 assistant along with every truck. 2 trucks will be deployed
for the first 5 days to facilitate the transport of materials.
⮚ Concrete mixer – The concrete mixer will be mobilized for 2
days to facilitate the construction of some temporary
facilities such as restrooms, and storehouses.
⮚ Wheelbarrows and pushcarts

⮚ Ropes and cords – Ropes and cords made of nylon and


assortment of natural fibers, with typical diameters of 10
mm, will be provided for use in various scenarios, such as
hoisting materials, construction of scaffolds, etc.
⮚ Nails and bolts – The nails and bolts will be provided as
specified in the plans.
⮚ Safety equipment including:
o Gloves,
o Hard hats,
o Work boots,
o Etc.
⮚ Miscellaneous handtools:
o Hammers
o Tamping tools,
o Levels.
o Etc.
➢ Wood materials (quantities specified in the BOQ) :
● 2x2 lumber
● 2x4 lumber
● ⅝ in plywood
● bamboo scaffolding
● etc., as specified in the plans
➢ Cement and aggregates (Sourced from local hardware stores):
● Ordinary Portland Cement
● ¾ inch Gravel
● River sand
● 10x20x40cm Concrete Hollow blocks
b.) Methodology
⮚ An area to the east of the construction site will be dedicated as the
main location for temporary storage and deployment of equipment
and materials.
⮚ As specified in the plan, the temporary facilities will be erected by
the south-east side of the site, closer to the road.

⮚ The contractor will prioritize construction of the following


temporary facilities in this particular order:
a.) Storehouses - erected as soon as possible to accommodate for
the storage of materials.

b.) Restrooms - erected simultaneously with the storehouses, to be


completed within the first day upon arrival of materials.

c.) Barracks - erected as soon as the restrooms are completed.


Expected to be finished within the 3 days.

d.) Field office - to be constructed simultaneously with the barracks.

II. Earthworks
– The Contractor will provide the necessary equipment, tools, manpower, mobilization, and
etc. to accomplish the following tasks under earthworks.
1) Excavation
- The contractor shall perform all excavations true to lines, widths and
depths shown on the Drawings or to such further lines, depths or
dimensions as may be directed by the Engineer.
a) Specifications:
i) Equipment/Materials
(1) Dump Trucks - The contractor will provide 1 truck with 1
driver and 1 assistant to mobilize and dispose of the
excavated materials.
(2) Wheelbarrows - These will aide transport for excavated
materials from the
(3) Safety Equipments includes:
(a) Gloves,
(b) Hard hats,
(c) Work boots,
(d) Etc.
(4) Other essential equipment
(a) Shovel,
(b) Pickaxe,
(c) Levels,
ii) Methodology
(1) The site shall be divided into two working areas which
compose of area A(A-B in reference to drawing plans)
and B(B-C in reference to drawing plans)
(2) Necessary markers shall be put in place before digging
can commence.
(3) The contractor will commence digging in specification
stated in the drawing plans
(4) Excavation shall start from Area A and finish at Area B.
(5) Excess or unwanted materials that are not necessary for
backfilling shall be disposed of in accordance with local
authorities mandates.
(6) Excavation is estimated to be complete in 3 working
days
2) Backfilling
- The contractor shall proceed with backfilling once the concrete has
sufficiently cured. Materials, equipment, manpower, etc. will be
provided by the contractor to accomplish backfilling.
a) Specifications
i) Equipment/Materials
(1) Wheelbarrows - Wheelbarrows will be the means of
transportation for filling materials to necessary
excavated sites or stations.
(2) Portable Compactor - The contractor shall provide 2
portable compactors to be used to compact loose
backfill materials.
(3) Safety Equipments includes:
(a) Gloves,
(b) Hard hats,
(c) Work boots,
(d) Etc.
(4) Other essential equipment
(a) Shovels,
(b) Rakes,
(c) Spades
ii) Methodology
(1) In connection with Excavation , Backfilling shall
approach the site in two working areas(Area A and Area
B).
(2) Backfill will be carried out in layers. Each layers shall
have a measure of more or less 4”
(3) After the 4” layer is met, compaction shall follow. This
will ensure backfilled materials are leveled with the
ground
(4) Backfilling is estimated to be finished in only one(1)
working day.
III. Plumbing

- All necessary equipment, materials and manpower in terms of plumbing installation will
be provided and taken care of by the contractor.

2.2 Specifications:

a.) Equipment/Materials:
➢ Carts and wheelbarrows - Carts and wheelbarrows are to be
used for aiding the transport of tubes, pipes, and other
materials necessary in the installation of plumbing. These will be
deployed for the duration of the plumbing phase.
⮚ Miscellaneous hand tools, including:
o Wrenches
o Slip-joint pliers
o Drain snake
o plungers
o hacksaws
o Etc.
- The hand tools will be provided for each
plumber on site, and will be active for the
duration of the pipes installation period.
⮚ Safety equipment including:
o Gloves,
o safety goggles
o Hard hats,
o Work boots,
o Etc.
- Each plumber will be provided with their own
safety equipment and mandated to wear them
for the duration of the pipes installation.

➢ Pipes and valves (as specified in the plumbing plans) :


○ ½” PVC pipes
○ 1in diameter PVC pipes
○ 45° PVC elbows
○ 90° PVC elbows
○ 150mm diameter Galvanized iron pipes
○ Metal pipe connectors
○ PVC ball valves and gate valves
○ etc.

➢ Fixtures and others


○ Standard Ceramic toilet bowl
○ 2-handle kitchen faucets
○ 2GPM standard stainless steel showerhead

B.) Methodology
i. The plumbers will lay down the iron pipes as the poured
concrete in essential areas are still hardening to
minimize wastage of concrete materials.

ii. The plumbers will prioritize finishing the kitchen sink


waterline to aid in the water supply for the construction
site. The restrooms will be finished later so as to avoid
unnecessary traffic in the site from workers who wish to
use the completed restroom on site.

IV. Electrical

- The contractor will provide for the necessary materials, equipment, manpower, as well
as ensuring safety in the installation of electrical systems on site.

2.3 Specifications:

a.) Equipment/Materials:
➢ Step ladders - made of aluminum and provides a 5 meter
vertical extension at maximum, these step ladders will aid the
electricians in reaching high places for installation of light
fixtures, wiring, etc. These will be deployed for use for the
whole duration of the electrical installation period
➢ Carts and wheelbarrows - Carts and wheelbarrows are to be
used for aiding the transport of cables, wires, and other
materials necessary in the electrical installations. These will be
deployed for the duration of the electrical installation phase.
⮚ Miscellaneous hand tools, including:
o Pliers
o hacksaws
o Voltmeters
o cable cutters
o screwdrivers
o Etc.
- The hand tools will be provided for each
electrician on site, and will be active for the
duration of the electrical installation period.
⮚ Safety equipment including:
o Gloves,
o safety goggles
o Hard hats,
o Work boots,
o Etc.
- Each electrician will be provided with their own
safety equipment and mandated to wear them
for the duration of the electrical installation
period.
➢ Wires, Cables (as specified in the electrical plans) :
○ 12 gauge electrical cables
○ 14 gauge electrical cables
○ etc.
➢ Outlets, switches, (as specified in the electrical plans):
○ 15A dual receptacles
○ 20A 3-gang receptacles
○ 2-gang light switches
○ etc.
➢ Fixtures and others
○ 36 watts fluorescent tube
○ 250 lumens Solhetta light bulb
○ Smoke detectors
○ Junction boxes

B.) Methodology
i. In this 1-storey project, the contractor plans to prioritize
electrical installations in this order, provided that
adequate roofing has been completed in the site:
1. Living room installations
2. Kitchen
3. Bedrooms

ii. The electricians are to prioritize the installation of the


main breaker, before installing the sockets and light
fixtures.
Project Type: One- Storey Residential Building
Project Name: Proposed One - Storey Residential
Location: National Highway, Poblacion West, Moalboal Cebu

Manpower Schedule
120 calendar days
Item# Description 1-15 C.D. 16-30 C.D. 31-45 C.D. 46-60 C.D. 61-75 C.D. 76-90 C.D. 91-105 C.D. 106-120 C.D.
1 Project Manager 1 1 1 1 1 1 1 1
2 Project-in-charge 1 1 1 1 1 1 1 1
3 Field Engineer 2 2 2 2 2 2 2 2
4 Materials Engineer 1 1 1 1 1 1 1
5 Quantity Surveyor 1 1 1 1 1 1 1
6 Architect 1 1 1 1 1 1 1 1
7 Safety Officer 2 2 2 2 2 2 2 2
8 Admin Support 1 1 1 1 1 1 1
9 Warehouse man 1 1 1 1 1 1 1 1
10 Warehouse helper 1 1 1 1 1 1 1
11 Timekeeper 1 1 1 1 1 1 1 1
12 Foreman 2 2 2 2 2 2 2 2
13 Watchman 1 1 1 1 1 1 1 1
14 Utilityman 1 1 1 1 1 1 1 1
15 Backhoe Operator 1 1 1
16 Laborer 10 15 30 40 40 30 30 20
17 Carpenter 5 5 10 10 10
18 Helper of Carpenter 5 5 10 10 10
19 Steelman 10 15 20 20
20 Helper of Steelman 5 5 10 10
21 Electrician 2 2 4 4 6 6 6 6
22 Helper of Electrician 2 2 4 4 6 6 6 6
23 Plumber 3 5 5 5 5
24 Helper of Plumber 3 5 5 5 5
25 Firepro 1 2 3 3 3
26 Helper of Firepro 1 2 3 3 3
27 Auxiliary 3 3 3
28 Auxilliary helper 2 2 2
29 Welder 3 3 5 5 7 8 5
30 Mason 3 18 20
31 Helper of Mason 1 9 10
32 Ceiling Installer 10 10 10
33 Labor of Ceiling Installer 5 7 7
34 Painter 30 30 20
35 Painter Helper 5 5 5 5
36 Windows and Glass Installer 6 5 5
37 Helper of Window and Glass Installer 6 6
38 Tilesetter 30 30
39 Helper of Tilesetter 15 15
40 Finishing Carpenter 5 5 7
41 Waterproofing installer 5 5
42 Roofing installer 8 5
43 Guard 1 1 1 1 1 1 1 1
Total 43 66 100 129 169 241 242 104
Work Breakdown Structure
Construction of 1-storey residential building

1. Foundation 2. Internal 3. External

1. 1 Excavation 2.1 Electrical 3.1 Masonry Work


Labor Crew Master Electrician Masonry crew

1. 2 Steel Laying 2.2 Plumbing 3.2 Roofing


G.C. Superintendent Master Plumber G.C. Superintendent


1.3 Concrete pour 2.3 Interior Finishes 3.3 Finishes


G.C. Superintendent Painting Crew Painting Crew

Project Type: One- Storey Residential Building


Project Name: Proposed One - Storey Residential
Location: National Highway, Poblacion West, Moalboal Cebu

Start Date Description Duration (Days)


12/06/2022 Bids & Contracts 28
10/07/2022 Contract Execution 1
Pre-Construction
12/07/2022 Obtain Permits 6
18/07/2022 Permits Approved 1
Construction 20/07/2022 Mobilization 2
24/07/2022 Rough Grading 3
Site Work & 26/07/2022 Footings 14
Foundation 10/08/2022 Foundation 21
02/09/2022 Inspection of Foundation 1
03/09/2022 Floors 5
08/09/2022 Walls 15
Rough Framing 23/09/2022 Roof 7
01/10/2022 Structural Repair 2
03/10/2022 Inspection of Framing 1
04/10/2022 Windows 4
Exterior
09/10/2022 Doors 3
Construction
13/10/2022 Roofing 7
21/10/2022 HVAC 5
26/10/2022 Masonry 5
MEP Rough-in 01/11/2022 Plumbing 3
04/11/2022 Electrical 2
06/11/2022 Inspection of MEP 1
08/11/2022 Insulation 2
Interior, Finishes 10/11/2022 Drywall 5
& Fixtures 15/11/2022 Painting 5
20/11/2022 Finishing 3
CONTRACT AND AGREEEMENT

for the

CONSTRUCTION of the One-Storey Residential House


for Dr. Robert Forger, M.D.

KNOWN ALL MEN BY THESE PRESENTS

This contract made and entered into this 18th day of June, 2022 by and betweeen:

DR. ROBERT FORGER, M.D. with an address at Moalboal, Cebu, Philippines, hereinafter
referred to as the OWNER.

-and-

WESTALIS CONSTRUCTION, with business address of Mambaling, Cebu City, Cebu,


duly represented by its Proprietor, ENGR. JEREMY L. SARVIDA, hereinafter referred to
as the CONTRACTOR;

WITNESSETH:

WHEREAS, a public bidding was conducted last June 12, 2022 at the Forger Engineering
Consultancy Conference Room, Ramos Street, Cebu city, for the Construction of the One-Storey
Residential Building for Dr. Robert Forger, M.D.

WHEREAS, the Bids and Awards Committee recommended to the OWNER that the project
shall be awarded to WESTALIS Construction, its offer being the most advantageous to the project.

WHEREAS, time is the essence of this contract

NOW, THEREFORE, for and in consideration of the foregoing premises and other covenants
hereinafter name, the parties agree as follows:

ARTICLE I - CONTRACT DOCUMENTS


The following documents shall be deemed to form and be interpreted and construed as part
of this agreement:

a) Design and Construction Agreement Contract


b) Invitation to Bid
c) Bidding Documents
d) Addenda and/or Supplemental/Bid Bulletins, if any
e) Bid Form including all the documents/statements
f) Eligibility requirements, documents and/or statements
g) Detailed Architectural and Engineering Design of the Project
h) Constructions Drawings, Plans, Designs and Specifications (setting forth in
detail the work required for architectural, structural, electrical, mechanical,
plumbing, sanitary and site development work
i) Statement of Probable Project Construction Cost
j) Resolution of the BAC recommending award of project of winning bidder
k) Construction plans and Phases and Timeline of the completion of the project

ARTICLE II - SCOPE OF WORK

The scope of work to be done by the CONTRACTOR consist of professional services for the
following:

1. The CONTRACTOR shall in accordance with the provisions of and subject to the
conditions contained in the documents referred to in Article 1 hereof, with a provision that
this construction activity belongs to WESTALIS Construction, and in consideration of the
sum of money hereinafter stated shall fully and faithfully perform all labor and furnish
needed equipment and services necessary to complete the Construction of the PROJECT as
per plan and specification of the OWNER;
2. The CONTRACTOR shall hire skilled workers as may be necessary
3. The CONTRACTOR shall construct the PROJECT under the supervision and management
of Forger Engineering Consultancy; and
4. The CONTRACTOR shall complete the PROJECT within the timeline provided herein.
5. The Contractor shall in no way suspend the works stipulated herein unless due to: bad
weather, fortuitous events or other justifiable causes.
ARTICLE III - TIME OF COMPLETION

1. The work to be performed by the CONTRACTOR under this contract shall commence
after ten (15) calendar days upon receipt and acceptance of the Notice to Proceed from the
OWNER by the CONTRACTOR.
2. The construction of the PROJECT shall be completed within One Hundred Twenty (120)
calendar days including Saturdays, Sundays and holidays.
3. Should the CONTRACTOR refuse or otherwise fail to complete the work stipulated herein,
the CONTRACTOR agrees to pay the OWNER liquidated damages in an amount equal to
One-Tenth of One Percent (0.1%) of the total contract sum for each calendar day of delay
until the work is completed and accepted by the OWNER or when the OWNER takes over
the project by administration or re lets it to other contractors until such time as the
OWNER may reasonably secure the completion of the works. Such amount shall be
deducted from any money due or which may become due the CONTRACTOR under this
contract.

EXTENSION. The following are grounds for the extension of the TIME OF COMPLETION, in
which case the CONTRACTOR shall not be held liable for the cost therefore:

a. Fortuitous events, such as but not limited to flood, typhoon, earthquake, accidents,
natural calamities, including those which affect the timely delivery of materials,
tools, equipment, facilities, and services provided in the Contract Documents;
b. Changes and alterations made or otherwise approved by the OWNER;
c. Delay in the payment of the fees by the OWNER; and
d. Delay caused by the OWNER;

Any other delays independent of the will of the CONTRACTOR.

ARTICLE IV – THE CONTRACT SUM

The OWNER for and in consideration of the faithful and satisfactory fulfillment of the
contract by the CONTRACTOR in accordance with the terms and conditions of all contact
documents and subject to the deduction herein provided, shall pay to the CONTRACTOR in
Philippine Currency the sum equivalent of ONE MILLION FIFTY-NINE THOUSAND SEVEN
HUNDRED EIGHTY SIX (Php 1,059,786.00) ONLY

Payment shall be in accordance with the following conditions:

a. Monthly payment shall be based upon the work satisfactorily completed as certified by
the CONTRACTOR and concurred by Forger Engineering Consultancy.
b. Final payment shall be made upon completion of the work and upon submission by the
CONTRACTOR of his sworn statement that all taxes due him and all obligations for
materials used and labor employed in accordance with this contract have been duly
paid.

ARTICLE V - GUARANTEE

The CONTRACTOR hereby guarantees the work stipulated in this contract and all the
materials it will apply and use in the construction as well as workmanship of all its work under this
contract and shall make good of its own account and/or its own expenses.

After final acceptance of the PROJECT by the OWNER, the CONTRACTOR shall assume
full responsibility for any damage or destruction of the works except those occasioned by force
majeure. They shall be required to put up a warranty security denominated in Philippine Pesos
provided in Section 62.2.3.3 of IRRA of R.A. 9184 and shall remain effective for one (1) year from
the date of issuance of the certificate of final acceptance and shall be returned only after the lapse of
the said one (1) year.

In addition, the provisions of Article 1723 of the New Civil Code shall also apply to
guarantee the work performance of the CONTRACTOR.

ARTICLE VI – SAFEGUARDS AND WARRANTS

The CONTRACTOR shall provide and do everything necessary to perform its


obligations under this contract according to the true intent and meaning of the other contract
documents taken together particularly the drawings, plans and specifications provided that the same
shall be inferred therefrom and should the CONTRACTOR find any discrepancy in the drawings,
plans and specifications, he shall immediately refer the same to the OWNER or Forger Engineering
Consultancy whose decision shall be followed.
The OWNER reserves the right for an additional or increase in the number of laborers or
workers assigned to the construction site in the opinion of the OWNER or Forger Engineering
Consultancy as the exigencies of the circumstances may require.

The CONTRACTOR shall be considered as an independent CONTRACTOR and as such,


he assumes all obligations and liabilities arising out of the Employee’s Liability Act and any other
laws existing and those enacted thereafter that may affect the rights of the employees or laborers
employed in the performance of this contract. Should the OWNER be made liable for any of the
CONTRACTOR’s violation of any labor laws, the CONTRACTOR shall reimburse the OWNER
for whatever amount the latter is required to pay to said laborers.

Notwithstanding any provisions of this contract, the OWNER has the right and/or power to
terminate the contract without necessity of judicial action by giving written notice to the
CONTRACTOR upon his failure to comply strictly with any of the terms of this contract.

The CONTRACTOR is likewise mandated to implement the construction safety and health
program as may be provided by Forger Engineering Consultancy.

ARTICLE VII – VENUE OF COURT ACTION

Should any court action be instituted by the OWNER or the CONTRACTOR arising from
this contract, the parties hereby agree that the venue thereof shall be the proper court in the City of
Cebu.

IN WITNESS WHEREOF, the parties have hereunto set their hands this 18th day of June
2022 at Ramos Street, Cebu City, Cebu, Philippines.

ENGR. JEREMY L .SARVIDA


(CONTRACTOR)

DR. ROBERT FORGER, M.D.


(OWNER)
FORGER ENGINEERING CONSULTANCY
Ramos Street, Cebu City
Tel No. (032) 328- 5587 I Cell. No. 09954896388
Email: FEC.bac@gmail.com

INVITATION TO BID

1. Dr. Robert Forger, M.D. intends to undertake the construction of the One-Storey Residential
House. The house is located at Poblacion West, Moalboal, Cebu, Philippines.

2. Scope of work to be undertaken for this package includes labor and materials for general
requirements, excavation works, slope protection works, structural concrete works,
reinforcing steel works, formworks and scaffoldings.

3. Dr. Robert Forger, M.D. , through its Bids and Awards Committee now invites
contractors to bid for the project, One-Storey Residential House. Completion of the
project is required within One Hundred Twenty (120) working days from the effective
date of the contract.

4. A complete set of Bidding Documents will be sent through email to interested Bidders on
starting May 22, 2022 up to May 29, 2022.

5. The Bids and Awards Committee will hold a Pre-bid Conference on May 30, 2022 at
exactly 7:30 p.m. virtually using Zoom with this link provided
(https://us04web.zoom.us/j/78866750007?pwd=u-FbiXpYnfaE7T7mnbWqthF0_MBwh.1)
which shall be open only to all interested parties who have sent the Bidding Documents.

6. Bids should be submitted to this email FEC.bac@gmail.com in 3 copies on or before


12:00 p.m. of June 12, 2022. Late bids shall not be accepted.

7. Bid Opening shall be on June 12, 2022 at exactly 7:30 p.m. at the Forger Engineering
Consultancy Conference Room located in Ramos Street, Cebu City.

8. Dr. Robert Forger, M.D. assumes no responsibility whatsoever to compensate


or indemnify bidders for any expenses incurred in the preparation of the bid.

9. Dr. Robert Forger, M.D. reserves the right to accept or reject any bid, annul the bidding
process, and to reject all bids at any time prior to contract award, without thereby
incurring any liability to the affected bidder or bidders.

10. For further information, bid queries and other concerns please refer to:
BAC Technical Group

Email: FEC.bac@gmail.com

ENGR. JOSEPH
MALAPITAN
Chairperson
Bid and Awards
Committee

Ramos Street, Cebu City Tel No. (032) 328- 5587 I Cell. No. HYPERLINK
09954896388
FORGER ENGINEERING CONSULTANCY BIDDING REQUIREMENTS
00250 AFFIDSITEINSPEC Page 00250 - 1 of 1

May 25, 2022

BIDDER’S
AFFIDAVIT FOR SITE INSPECTION

This is to certify that WESTALIS CONSTRUCTION, through its authorized


representative, ENGR. JEREMY L. SARVIDA_, has conducted the inspection of the
site of the project: A PROPOSED ONE STOREY RESIDENTIAL located at the
NATIONAL HIGHWAY, POBLACION WEST, MOALBOAL, CEBU on this 25TH day of
MAY, 2022 in connection with our desire to participate in the bidding of the above
project; and we have gathered all data to ascertain permanent connections to the
tapping points for all utility lines including electrical power supply, telecommunications,
drainage, sewer and potable water to fulfill the requirements of our bid.

ENGR. JEREMY L. SARVIDA


(Printed Name & Signature of
Bidder)
REPUBLIC OF THE PHILIPPINES)
PROVINCE OF CEBU ) S.S.
CITY OF CEBU CITY )

SUBSCRIBED AND SWORN to before me this 25TH day of MAY, 2022, with affiant
exhibiting me his Government Issued ID with the following details: 0658567 issued
on November 21 , 2018 , at Cebu City, Philippines.

(Notary Public)

Doc. No. 322 Issuing Government Agency:


Page No. 02
Book No. 05
Series of 2022

END OF SECTION 00250

Read and accepted as part of the Contract:

ENGR. JEREMY L. SARVIDA


Bidder/Contractor
BID PROPOSAL

Proposed One-Storey Residential


Westalis Construction
Mambaling, Cebu City, Cebu,
Engr. Sarvida Project #53

TO:
Forger Engineering Consultancy
Ramos Street, Cebu City
Tel No. (032) 328- 5587 I Cell. No. 09954896388
Email: FEC.bac@gmail.com
Engr. Joseph Malapitan

Gentlemen:

The undersigned, having familiarized with the Contract Documents, site location, and
conditions as prepared by Architect Casper S. Carrasco, A. Minoza St., Talamban,
Cebu City, 09458429526, by submission of this Bid Proposal, hereby agrees to
complete the Work for the total sum as follows:

BASE BID:
One million seventy-nine thousand seven hundred eighty-six pesos
(Words)
1,079,786.00 php
(Figures)

ADDENDA: The bidder acknowledges receipt of the following addenda and execution
is included in the base bid listed herein.

Addenda: Permits Dated: June 19, 2022

ENGR. JEREMY L. SARVIDA


(Printed Name & Signature of Bidder)

Westalis Construction
Mambaling, Cebu City, Cebu,
FORGER ENGINEERING CONSULTANCY
Ramos Street, Cebu City
Tel No. (032) 328- 5587 I Cell. No.
09954896388
Email: FEC.bac@gmail.com

NOTICE OF AWARD
No. 2022-05-06

July 10, 2022

Engr. Jeremy L. Sarvida


Contractor
Westalis Construction
Mambaling, Cebu City, Cebu,
(032) 254 - 1056

Dear Engr. Sarvida,

This is to notify you that your bid dated June 20, 2022 for the project
Proposed One-Storey Residential for CY 2022, with an Approved Budget
Contract (ABC) of Php 1,079,786.00 under 2022 GAA for a Contract Price
equivalent to four hundred thirty-one thousand nine hundred fifteen pesos
(Php 431,941.00) only is hereby accepted.

You are therefore required to provide the performance security in the form
and amount stipulated in the instructions to Bidders within ten (10) calendar
days from receipt of Notice of Award. Contract signing will be done upon
submission of the required performance security. Failure to provide the
performance security on the said date shall constitute ground for cancellation
of the award and forfeiture of the bid security.

Very truly yours,

Engr. Joseph Malapitan


Chairperson
Bid and Awards Committee
NOTICE TO PROCEED

TO: Engr. Jeremy L. Sarvida - Westalis Construction

FROM: Forger Engineering Consultancy

DATE: July 15, 2022

SUBJECT: Notice to Proceed with Construction Contract

A Proposed One-Storey Residential, located at National Highway, Poblacion


West, Moalboal, Cebu City was awarded to Engr. Jeremy L. Sarvida, Westalis
Construction, Mambaling, Cebu City, Cebu, (032) 254 - 1056, in the amount
of Php 431,941.00, on June 18, 2022. Contractor is hereby notified to
commence work set forth in the contract on or before July 22, 2022.

All work is to be done in accordance with plans, specifications, and conditions


provided in the contract. The project must be fully complete within One
Hundred Twenty (120) working days from the effective date of the contract.
The date of completion of all work is, therefore November 26, 2022.
Contractor will pay as liquidated damages an amount equal to One-Tenth of
One Percent (0.1%) of the total contract sum for each calendar day of delay
until the work is completed and accepted by the Owner as specified in line 3
of Article III under Time of Completion.

Please acknowledge receipt of this Notice by signing the space below and
returning a copy to this office.

Please advise if there are any questions.

Sincerely,

Engr. Joseph Malapitan


Chairperson
Bid and Awards Committee

Acceptance of Notice

Receipt of the above Notice to Proceed is hereby acknowledged by Engr.


Jeremy L. Sarvida, this 18th day of July, 2022.

Authorized Signature: