Professional Documents
Culture Documents
Issue date
Revision No 00 - - 00
Revision date 13.01.2018 - -
Signature
Content:
1. Purpose..................................................................................................................................... 3
2. Scope........................................................................................................................................ 3
3. Responsibilities:........................................................................................................................ 3
1. Purpose
This procedure is used as work instruction for Electrician, Electrical Engineer, Desk Engineer, Shift In
charge.
2. Scope
This procedure explains the Effects / Steps to be taken in case of 220 Volt DC Supply Failure.
DEFINITION : ID Fan- Induced Draft Fan, APH- Air Preheater, DeE-Desk Engineer, FO-Field Operator, FD- Forced
Draft Fan
1. WORK INSTRUCTIONS :
1. Cause:
2. Unit Response:
3. Operator Action:
1 Immediately cut upper elevation mill. (DeE) and reduce the Load.
2 Put oil support for stabilizing furnace. (DeE)Maintain furnace draft +/-10 mmwc . (DeE)
3 Increases loading of running pass. (DeE)
4 Maintain drum level +/- 50 mm and SH/RH temperature 537 deg C.(DeE)
5 Isolate the tripped pass from air and flue gas side (DeE/FO)
6 Maintain APH outlet temperature of running pass ~132 deg C. (DeE)
Plant Operation SOP For One APH Trip
7 If APH cold end temp. is increasing then, Give PA air to reduce APH temperature . (DeE)
8 Check healthiness of air motor and air supply (Field operator)
2. Daily Monitoring :