Professional Documents
Culture Documents
CLASS PROJECT
TOPIC:
Submitted by
18CE10051
Introduction:
Item Description Particulars
I. GENERAL INFORMATION
Name of the Town KOTHAGUDEM
Service Reservoirs 5 Nos. Existing (900 kL, 1650 kL, 1800 kL, 1200kl,
1000kL Capacity)
•The major source of water for Kothagudem town is Kinnerasani Water Supply Scheme and is
commissioned during the year 2000 to provide potable water supply. Kinnerasani Reservoir is
the surface water source for the present scheme and is located at a distance of 25 Km from
the town.
• Past population data at the beginning of each decade starting from 1971 to 2011
(provisional) for Kothagudem town has been collected from Census of India for
analysis. The population growth rate of the town (within its municipal area) during the
last five decades been worked out to assess the growth pattern of Kothagudem
Municipality.
• Population projections have been done using standard population projection methods
viz. Arithmetical Increase Method, Geometrical Increase Method and Incremental
Increase Method etc. as recommended by CPHEEO’s “Manual on Water Supply &
Treatment - 1999” for various stages of the proposed scheme viz. base year (2018),
intermediate year (2033) and ultimate year (2048).
• Estimation of present and future estimation:
Zone-1 3, 4, 5 & 6 (100%) 15,543 1673 2052 2469 Existing ELSR of 900KL
capacity with 13m staging
height at Main hospital
Zone-2 25, 26, 27, 28, 29, 38643 4158 5101 6137 Existing ELSR of 1650 KL
30, 31, 32, 33 capacity with 15m staging
(100%) & part of 24 height at Rythu Bazaar
(80%)
Zone-3 7, 14, 15, 16, 17, 34871 3752 4603 5538 Existing ELSR of 1800KL
capacity with 15m staging
18, 19, 20 (100%) height at Writer Basthi
• The Hydrogen ion concentration (pH) varies from 7.14 to 7.27 as against the
standard of 6.5 - 8.5 and is within the acceptable limits.
• The Total Ha rd ne s s is observed in the range of 88 – 96 mg/l in all the stages as
against the standard of 200mg/l and is within the acceptable limits.
• The Chemical Oxygen Demand (COD) is ND in WTP outlet sample .
• The Bio- Chemical Oxygen Demand (BOD) is observed in the range of ND in the raw
water as well as in treated water indicating that no organic load.
• Fluoride concentration is found to be consistent in raw water, WTP outlet to be
• 0.20mg/L and is within the acceptable limits.
• The total coliform & E coli count in CFU/100mL are found to be ND .
Surface/ Drinking water quality Results
Raw IS:10500(2012)
S. Water WTP Requirement(Acceptable
Parameter(s)
No. (River/ Outlets Limit)
Canal)
1 pH 7.27 7.14 6.5 – 8.5
2 Turbidity 1.60 <1.00 1 max
3 TotalHardness(TH),as 96 88 200 max
caco3 mg/l
4 Chemical Oxygen -- --
Demand, mg/l
5 Bio-chemical ND ND ND
Oxygen
Demand, (3 d,27
0c)mg/l
6 Fluorides as F-, mg/l 0.2 0.2 1
7 Total Coliform, ND ND Shall not be detectable in
CFU/100ml any 100mL sample
It is evident from the results tabulated that all parameters monitored are within the desired limits of the drinking
water standards specified under IS:10500:20012.
From the below results it can be inferred that the water quality is within the desired limits of
the drinking water standards specified under IS:10500:20012.
Groundwater Sample Analysis Results
S.No Parameter Units Requirement Permissible GW1 GW2 GW3
acceptable Limit*
limit
1. pH -- 6.5-8.5 6.5-8.5 7.12 7.61 6.93
2. Turbidity NTU 5 10 1.4 4.2 1.4
3. Total Dissolved solids mg/l 500 2000 798 1288 1100
4. - mg/l 250 1000 301 455 379
Chlorides as Cl
5. Sulphates as SO4 mg/l 200 400 70 100 136
6. Total Hardness as CaCO3 mg/l 300 600 450 697 538
7. Calcium as Ca mg/l 75 200 86 167 110
8. Magnesium as Mg mg/l 30 100 57 68 64
9. Fluoride as F mg/l 1.0 1.5 0.44 0.86 0.32
10. Iron as Fe mg/l 0.3 No relaxation 0.48 1.11 0.56
11. Total Chromium as Cr mg/l 0.05 No relaxation <0.05 <0.05 <0.05
12. Copper as Cu mg/l .05 1.5 <0.0001 <0.0001 <0.0001
13. Arsenic as As mg/l 0.01 0.05 <0.0001 <0.0001 <0.0001
14. Cadmium as Cd mg/l 0.0003 No relaxation <0.0001 <0.0001 <0.0001
15. Nickel as Ni mg/l 0.02 No relaxation <0.0001 <0.0001 <0.0001
16. Mercury as Hg mg/l 0.001 No relaxation <0.0001 <0.0001 <0.0001
17. Lead as Pb mg/l 0.01 No relaxation <0.0001 <0.0001 <0.0001
18. Zinc as Zn mg/l 5 15 1.11 0.98 0.49
19. Boron as B mg/l 0.5 1 <0.0001 <0.0001 <0.0001
In the existing system disinfection through chlorine gas is practiced by following standard
operating procedures as stated:
• Installation of alarm and safety systems, including automatic shutoff valves, that
are automatically activated when a chlorine release is detected;
• Installation of containment and scrubber systems to capture and neutralize
chlorine should a leak occur;
• Use of corrosion-resistant piping, valves, metering equipment, and any other
equipment coming in contact with gaseous or liquid chlorine, and keep this
equipment free from contaminants, including oil and grease;
• Storage of chlorine away from all sources of organic chemicals, and protect from
sunlight, moisture, and high temperatures;
• Minimize the amount of chlorination chemicals stored on site while maintaining a
sufficient inventory to cover intermittent disruptions in supply; and
• Planned for responding to accidental releases.
Since chlorine gas will be used in treatment process it is necessary to follow SOP of chlorine
which indicates storage and handling, and emergency procedure during leaking.
WTP SLUDGE:
The sources of sludge in WTP are precipitate removed from a sedimentation basin,
settling tank, or clarifier and backwash water sludge. About 0.15 to 0.20% of sludge is
envisaged from the water treatment plant. The unit operations in sludge disposal are
sludge conditioning, thickening, dewatering and ultimate disposal. The ultimate disposal
of sludge entails through land filling or land applications. The major concern in
backwash/ sludge is presence of aluminum or iron salts with a mixture of organic
and inorganic materials and hydroxide precipitates. For alum sludge having more than
25% of solids requires an effective land filling and alum sludge having less than 25% of
solids can be directly used in crop land, marginal land, forests land etc.
TARIFFS:
• Domestic
• Commercial
• Industrial
• Fire fighting purposes.
A good distribution system should satisfy the followings:
• Adequate water pressure at the consumer's taps for a specific rate of flow (i.e,
pressures should be great enough to adequately meet consumer needs).
• Pressures should be great enough to adequately meet fire fighting needs.
• At the same time, pressures should not be excessive because development of the
pressure head brings important cost consideration and as pressure increases
leakages increases too. Note: In tower buildings, it is often necessary to provide
booster pumps to elevate the water to upper floors.
• Purity of distributed water should be maintained.
• Maintenance of the distribution system should be easy and economical.
• Water should remain available during breakdown periods of pipeline. System of
distribution should not such that if one pipe bursts, it puts a large area without
water.
• If a particular pipe length is under repair and has been shut down, the water to
the population living in the down-stream side of this pipeline should be available
from other pipeline.
• During repairs, it should not cause any obstruction to traffic.
LOSSES:
As per the records, there were 412 nos. leakages out of 3200 nos. joints in the
pipeline since commissioning of the scheme i.e. 18-01-2000 during the last 13
years. At present there are about 38 nos. leakages & four instances of pipe
breaks reported in the pipeline which occurred on 10-11-2005, 15-09-2007,
10-10-2010 & 23-06-2011 dates respectively.
Pumps
a) Operation: 23½ hours per day
b) Standby: 50% or 100% (for low capacity)
Clear Water Pipeline:
The clear water pipeline from WTP to the 2 new ELSR locations at
Gollagudem with 600mm dia for 1.5km, 500mm dia of 1.5km & 150mm dia
of 900m is proposed; 150mm dia of 600m from a nod to ELSR near Saibaba
temple near Tehsildar office in Kothagudem is proposed with DI pipeline.
The total length o f new DI pipeline is estimated to be 4.5 Km. The pipeline
will be laid within the ROW of proposed NH-30
ELSRs :
Two new ELSRs with capacity of 500KL each are proposed at Rajiv Gruhakalap,
Gollagudem, at Saibaba temple near Tehsildar office. The proposed land for the ELSRs
is belongs to Govt of Telangana and is in the process of transferring to Kothagudem
Municipality.
Distribution Network:
Providing distribution network system with DI & HDPE pipelines in 6 hydraulic
zones. The length of the total distribution network is estimated to be 62 Km. The entire
distribution line will be laid along the ROW of the existing Municipal roads.
MANAGEMENT REGIMES:
• The sufficiency of the existing gravity feeder mains of AC pipeline is checked and
accordingly the pipelines are retained in the proposed scheme with replacement
of pipes wherever necessary as parallel without disturbing and cutting the
existing AC Pipes.
• However handling of Asbestos Cement products such as AC pipes encountered
accidentally also, is of environmental and health concern, hence a detailed AC
pipe handling protocol is prepared to safe guard worker and public health
Responsible for carrying out monitoring measures
STAKEHOLDER CONSULTATION:
The existing sludge is analysed by collecting the sludge in a 1000ml measuring jar
and allow them to settle for 1 hour, the supernatant is observed to be 120 - 140ml.
The WTP sludge settled at the bottom contains solids upto 12 - 14%. In view of the
above observations, the proposed WTP is envisaged to generate less than 25 %
solids.
PROPOSED SEWERAGE SYSTEM:
Sewage treatment facility will be designed to meet the STP disposal standards notified by
MoEFCC As discussed above, the treated wastewater will be disposed into Kothankulam
tank, from where water will be used for irrigation. It is critical that STP treats the sewage as
designed to meet the disposal standards. Operation and maintenance of STP and change in
incoming sewage quality will have impact on the treatment efficiency.
During its operation phase, STP will treat 21.85 million liters of wastewater every day. It is
proposed to dispose treated wastewater from the STP into Kothankulam tank, which is
located about 1.4 km north of the STP site.
The domestic wastewater shall be treated and reused for flushing the toilets, followed by on
land irrigation, cooling towers and HVAC make up water requirement, and on land
irrigation. Hence all the recycled water is utilized, No water is left out of the premises, hence
having a ZERO discharge.
In Kothagudem, the sewer system will collect only domestic sewage, and it will not cater to
industrial wastewater. STP will treat wastewater to disposal standards. The mixing with lake
water and retention period in lake will further improve the quality of water, and will also
reduce the bacteriological contamination greatly.
ADEQUACY OF EXISTING WATER AND WASTEWATER SYSTEM
• The water supply service in Kothagudem Municipality exhibits a linear relationship
between per capita water supply and sewage generation.. The existing water quality of
Kinnersani canal source is found to be potable and fit for drinking.
• The existing source of water supply for the town viz. KTPS canal is retained in the
proposed scheme since it is a sustainable source having permission from concerned
department for withdrawal of water sufficient till ultimate year 2048. However, off-take
point is shifted to near Kalvathanda, Regalla village reducing about 8km from the existing
point.
• Under the present Kinnerasani Water Supply Scheme, rising main of PSC (14
Kg/cm2) pipeline was laid for transmission of raw water from Head works to filter bed
and is operational since year 2000. The sufficiency of the existing rising main has
been checked for ultimate water demand (2048) and conditional assessment is carried
out.
• Given the current status of tank with negligible storage, polluted nature of water, no
dependent potable uses, no notable aquatic life, etc., there are no adverse impacts
likely due to disposal of STP treated wastewater meeting the set quality standards.
• One of the critical aspects in STP operation is, change in raw sewage characteristics at
inlet of STP may affect the process and output quality. The system is designed for
municipal wastewater, which does not include industrial effluent
• Presently, the sewerage system covers about 32 % of the area with a sewerage
network along with decentralized STP, while some areas have individual septic tanks
and no standard method of draining / cleaning septic tanks
CRITICAL ISSUES FACED:
The existing water supply system has several limitations both in terms of infrastructure
sufficiency, condition and operational convenience to ensure desired water supply to the
inhabitants of Kothagudem municipality. The key issues noticed in the existing water supply
system are enlisted below.
• Leakages in the raw water transmission main of PSC pipeline from Kinnerasani
headworks to filter bed at Yellandu ‘X’ roads resulting in deficient water supply to the
inhabitants.
• Frequent Power Failures & Pump Failures resulting in water hammer within the
raw water pumping main.
Since the scheme provides a continuous water supply resulting in the saving of labour and time
of the economically weaker sections of society, who are otherwise spending a lot of their
productive time in fetching water- that too unsafe from different sources, thereby improving
their health& economic status. The main objective of the sub-project is to provide safe and
adequate potable water to the consumers it serves to their satisfaction.
RECOMMENDATIONS:
Considering source of treated water from water grid intake location at Srinivas Gutta near
Palvoncha as an Alternative, which is about 9km from Kothagudem town neccesary steps to be
taken. As per the preliminary estimate, the cost works out to be Rs. 45.58Crores. Where as the
total cost of project considering existing assured source of water from Kinnersani is Rs. 34.98
Crores only. Hence, various techno-economical reasons and having assured water source from
Kinnarsani canal, hence under the comprehensive water scheme for Kothagudem, the source of
water from Kothagudem has not been opted.
Further, following are the advantages of shifting of the intake location (recommended
alternative)