You are on page 1of 1

REVISION

Rev. No Revision note Date Signature Checked


0 Issued for as built -
1 Revisi Sesuai API 650 16-4-21
2 2 PL Reinforcing pl.14mm 21-4-21

Key Plant

PART LIST
Itemref Qty Description Dimension Materials W/kg

DETAIL - A

1 2

FOR APPROVAL DRAWING

Note : * ALL DIMENSION ARE IN MILLIMETERS UNLESS OTHERWISE NOTED

Owner :
WILMAR NABATI INDONESIA

Contractor :
PT. SRIKAYA PUTRA MAS
SPM Jl. Raya By Pass Krian Km 28.6
Krian - Sidoarjo

Project

EXPANSION STAGE 2 ETP


Drawing Tittle
ACCIDENT TANK 3000 MT
MANHOLE
Drawn By :go Jan 20 Doc. No. Qty : Item No.

Checked By : Suprihadi, ST Jan 20 SO-2021-014 1 Unit xxx


Approved By :Suprihadi, ST Jan 20 Dwg. Reff : ETP II-03/TK-804

SECTION D - D Order No. Drawing Number : Rev.

21.014 SO-2021-014 2
Size Scale : Sheet

A3 1 : 90 15 Of 21