KEI/0013/202204/0012898777
Date: 19-Apr-2022
To,
SPECKLES DEVELOPERS PVT LTD,
421/J SRI KRISHNA TEMPLE ROAD,
INDIRA NAGAR 1ST STAGE,
BANGALORE-560038
Dear Sir,
Sub: Supply, Installation, Testing and commissioning of 2 Elevator(s) for your esteemed project at
Bangalore
This has reference to the subject; At the onset we would like to thank you for the valued enquiry made with us towards supply
and installation of elevators for your above esteemed project. In this connection, we have enclosed herewith our detailed
technical specification along with price schedule and other terms and conditions for your kind consideration.
We are a global leader in elevator and escalator industry. Our vision is to deliver the best People Flow™ experience by
developing and delivering solutions that enable people to move smoothly, safely and comfortably with reduced waiting times.
Headquartered at Chennai, KONE Elevator India is at the forefront of technological disruption, adopting best practices by
integrating digitalized solutions with its products for the Indian market. Its global technology and engineering centre, ITEC in
Chennai has R&D and Engineering capabilities, enables development of energy efficient solutions based on global designs &
requirements, which are further modified to suit Indian settings. KONE India serves customers all over the country through its
50+ branch offices and provides sustainable People Flow™ solutions for India’s rapidly growing cities.
KONE is a byword for innovation & technology and accords highest priority to Safety & Quality not only in terms of
manufacturing & installations but also in work culture & communities it operates in. Through our products, we bring to our
customers world-class professionalism backed by globally established systems, values & practices. Today, some of the most
advanced and safest elevator and escalator solutions are installed in some of the tallest buildings in the World, which stand
testimony to our innovative and sustainable offerings in the vertical transportation industry. For the 8th time in a row KONE has
been featured in the Forbes list of 100 Most Innovative Companies in the World.
With KONE products, we assure you and your building’s users a world class vertical travel experience, well supported by a
global network of experts and skilled professionals. We trust that our offer falls in line with your requirement and look forward to
the pleasure of being associated with you at your above esteemed project. We will be pleased to assist you in case of any
clarifications / queries and request you to contact the undersigned.
Thanking you and assuring you of our sincere support and services at all times,
Yours faithfully,
M Prakash
Deputy Manager- Sales
9900031275
m.prakash2@kone.com
Signed For Purchaser For KONE Elevator India Pvt Ltd 2(6)
282 - KONE I MonoSpace R20.2 - 2
Signed For Purchaser For KONE Elevator India Pvt Ltd 3(6)
Pricing summary
PLEASE NOTE: UNLESS PREVIOUSLY WITHDRAWN, THIS OFFER IS VALID ONLY FOR 30 DAYS. WHEN ACCEPTED, THIS PRICE WILL BE VALID FOR A
PERIOD OF 12 MONTHS FROM THE DATE OF SUBMISSION OF THIS OFFER.
The above prices are inclusive of all applicable Taxes GST@18% at the prevailing rates. Any additional liability due to increase
in rates due to changes imposed by the competent authorities would be payable by you at actual.
All other civil / electrical related works as mentioned in the terms & conditions of the contract will come under the scope of the
builder. Please be informed that our price excludes below works:-
Signed For Purchaser For KONE Elevator India Pvt Ltd 4(6)
PAYMENT TERMS :
10 % of contract value as interest free advance along with the work order or contract
80 % of contract values as material advance payment on pro-rata basis.
10 % on commissioning & handing over of the lift on pro-rata basis.
WARRANTY:
18 Months from the date of supply of materials / 12 months from the date of handing over of the lift whichever is earlier.
We will submit our GAD within one(1) weeks from the date of receipt of complete site details along with the order & advance
payment
We will deliver the materials for the subject project by the end of Four(4) Weeks from the date of receipt of approved General
Arrangement Drawings (GAD), site readiness as per our ‘CHECK LIST’ & payment terms complied with, whichever is later &
force majeure conditions on pro-rata basis.
On compliance of the above, we will complete the elevator installation & commissioning by the end of Six (06) Weeks on pro-
rata basis.
Providing a safe suitable lockable storage room for materials at ground floor by customer.
WORK:
Customer Scope of work (before start of Installation) is as mentioned in Page No. 5 & 7 under clause 1, 2 & 4 respectively of
Terms & Conditions of Contract in the referred proposal.
We have our Service Office at the following address where we have established a full-fledged service depot manned by skilled
and experienced service personnel and supported by adequate stock of spares and tools to render efficient after-sales services.
Kone elevator India private limited, No. 4/1, zenith chambers, Opp. 6th cross Wilson garden,
Bangalore-27.
Contact nos: telephone : 1800 4254 666\25524973/972/971-service call center, tele fax extn. : 203
Bank Name & Address Standard Chartered Bank, #19, Rajaji Salai, Chennai-600001
IFSC SCBL0036078
Signed For Purchaser For KONE Elevator India Pvt Ltd 5(6)
M
CHECK LIST POINTS TO BE COMPLETED BEFORE MATERIAL SUPPLY AT BUILDER COST
Lift Pit Filling to the required depth of (1600 mm from the finished floor level (FFL).
Water Proofing inside the Pit to be done.
Lift Shaft should be cleaned to match our General Arrangement Drawing (GAD) with clear plumb level.
Lift Shaft White washing to be done.
Bulkhead fittings (Iron Casing) with 3-pin socket & on -off switch should be provided.
Wooden scaffolding as per our requirement.
Template to be provided as per our drawings
Safe Lockable storeroom of approx. 40 sq. mt. for exclusive elevator materials (each elevator), well protected from
water entry /seepage, in the ground floor & close to the shaft.
Load Hook /steel channels to be provided in the Head Room.
3-phase panel (32 Amps with MCB) power supply should be available to the last floor landing
Single phase (5 Amps) power supply - 0ne for shaft lighting & one for lift car (fan, light) should be available.
5Amps 3 pin-socket for the inverter to be provided.
Exhaust window to be provided in the Head room as per GA drawings.
Double Earthing in the lift shaft with bus bar to be provided.
Entrance Safety barricades to be provided at all floors as per our drawings.
PARALLEL WORK TO BE DONE BY THE BUILDER DURING OUR INSTALLATION AT BUILDER COST
For any other details such as front wall, Lintel etc. Please refer the General Arrangement Drawing (GAD) which will be
given in due date.
Kindly indicate the tentative date of completion of the above-mentioned points, so that we can plan our activities accordingly.
Yours faithfully,
Prakash M
Deputy Manager-Sales
Mob:- 9900031275
Signed For Purchaser For KONE Elevator India Pvt Ltd 6(6)