Professional Documents
Culture Documents
Project Location:
Project Owner:
Total Estimated Cost: 2,532,748.09 PHP
Bill of Quantities
Item No. Item Description Unit Quantity Unit Cost Amount
I Demolition of Existing Structure LS 1.00 - -
II Clearing and Grubbing sq.m 365.00 3.90 1,425.00
III Structure Excavation cu.m 71.19 371.24 26,430.00
IV Structural Concrete & Formworks cu.m 72.76 7,460.30 542,805.00
V Steel Reinforcement kg 4,205.04 127.86 537,654.37
VI Masonry Works Sq.m 72.76 813.32 59,176.50
VII Backfill Cu.m 8.31 1,011.36 8,400.00
VIII Plain Cement Plastering Sq.m 145.52 119.57 17,400.00
IX Tile Works Sq.m 414.00 1,234.86 511,230.00
X Analok Glass Window Sq.m 26.70 5,464.89 145,912.50
XI Wooden Framed Doors Sq.m 14.11 6,590.01 92,985.00
XII Roof Framing LS 1.00 56,175.00 56,175.00
XIII Roofing LS 1.00 226,106.25 226,106.25
XIV Painting Works Sq.m 270.52 201.03 54,382.50
XV Waterline Pipeline System m 59.60 314.85 18,765.00
XVI Storm Drainage and Sewerage System m 59.60 256.21 15,270.00
XVII Plumbing Fixtures LS 1.00 31,020.00 31,020.00
XVIII Electrical Layout (8% * I-XVII) LS 1.00 187,610.97 187,610.97
Total Estimated Cost: 2,532,748.09
Civil Engineer
PRC Reg. No. : PTR No.
Valid Until: Valid Until:
TIN No.: Issued @:
I Demolition of Existing Structure
Qty.: 1.00 LS
Unit Cost: - PHP
A+B+C Cost: - PHP
A. Material Cost Unit Quantity Unit Cost AMOUNT
-
-
-
Total Material Cost -
B. Equipment Cost No. of Eqt. No. of Days Rate AMOUNT
-
-
-
Total Equipment Cost -
C. Total Labor Cost (50% of Material Cost + Equipment Cost) -
A+B+c COST -
VI Masonry Works
Qty.: 72.76 Sq.m
Unit Cost: 813.32 PHP
A+B+C Cost: 59,176.50 PHP
A. Material Cost Unit Quantity Unit Cost AMOUNT
Cement bags 37.00 270.00 9,990.00
100mm Thick CHB kg 877.00 13.00 11,401.00
10mm dia RSB pcs 49.00 260.00 12,740.00
Sand s1 Cu.m 3.00 850.00 2,550.00
#16 tie wire kg 3.00 90.00 270.00
-
-
Total Material Cost 36,951.00
B. Equipment Cost No. of Eqt. No. of Days Rate AMOUNT
One Bagger Concrete Mixer 1.00 5.00 500.00 2,500.00
-
-
Total Equipment Cost 2,500.00
C. Total Labor Cost (50% of Material Cost + Equipment Cost) 19,725.50
Structural Concrete
Backfill
Wall Area
Window Area
Steel Reinforcement