You are on page 1of 13

Annexure-I

1.0 Modification of scope under Western Region Expansion Scheme-XXV (WRES-


XXV) scheme on account of space constraints at Raigarh (Kotra) S/s

The Western Region Expansion Scheme-XXV (WRES-XXV) involved augmentation


of transformation capacity at Raigarh (Kotra) by 1x1500MVA, 765/400kV ICT at
Section-A (3rd ICT on Section A) and by 2x1500MVA, 765/400kV ICTs at Section-B
(3rd & 4th ICTs on Section B) along with associated ICT bays as elaborated below:

Raigarh(Kotra) Section-A

 765/400kV ICT: 1x1500MVA


 765kV ICT bay: 1 no.
 400kV ICT bay: 1 no.

Raigarh(Kotra) Section-B

 765/400kV ICT: 2x1500MVA


 765kV ICT bay: 2 nos.
 400kV ICT bay: 2 nos.

The above scheme was agreed in the 8 th NCT meeting held on 25.03.2022 to
facilitate N-1 compliancy of the 765/400kV ICTs at Raigarh (Kotra) S/s under
following 2 conditions (after bus split arrangement):

 With Raigarh – Pugalur HVDC line operating under blocked mode or reverse
mode (SR to WR) during high renewable generation in southern region and
high generation at Raigarh (Kotra) PS
 With Raigarh – Pugalur HVDC line operating under forward mode (WR to SR)
and under low generation at either of the bus section at Raigarh PS

The scheme was awarded to CTUIL for implementation under RTM mode to be
implemented by POWERGRID vide NCT letter dated 10.05.2022 with schedule of 15
months from date of allocation.

Subsequently, POWERGRID vide letter dated 19.05.2022 that as per site conditions,
space for installation of 2nd 765/400kV ICT on Section-B is not feasible. Further,
modification of bay orientation may be required for installation of ICT on Section-A.
The matter was discussed with POWERGRID and it was decided that a committee
comprising of members from CTUIL & POWERGRID shall visit the site and explore
options to implement the scheme. The committee visited the site on 31.05.2022 &
01.06.2022 and submitted its site visit report and made the following
recommendations:
a) 1st ICT in Section B: ICT to be installed in Space available for Future ICT. For
connection on 765kV side, Future Bay No. 726 to be constructed in existing
Half Dia. For connection in 400kV side, 400kV DB Power 2 Line (along with
Line side equipment) to be shifted from existing 400kV Bay No. 433 to Future
Bay 444 using additional BPIs. The vacated 400kV Bay no. 433 shall be used
to terminate this ICT in AIS. This arrangement requires sufficient outage of DB
POWER 2 Line for shifting in new Dia.

b) 1st ICT in Section A: ICT to be installed in Space available for Future ICT. For
connection on 765kV side the Dia consisting of Bays 710,711 & 712 to be
constructed in AIS (Presently this space has been used to Terminate the
Champa Champa-I Line in Bay 715).
 
765kV Champa-1 Line shall be shifted from Bay 715 to Bay 710. For
connection of ICT on 765kV side, Bay No. 712 shall be used. For connection
of ICT in 400kV side, Future Bay 421 shall be constructed in existing Half Dia.

c) 2nd ICT in Section B: ICT to be installed in Space available in the area


earmarked for Future ICT in Section A. For connection on 765kV side, 2 1
nos. 765kV GIS Bays (consisting of 2 nos. CBs) shall be constructed (Double
Bus Double Breaker Scheme) in Bus Section-B in the space available near
765k Bus Sectionaliser Area and using GIB (Gas Insulated Bus Duct), the ICT
shall be physically located in the area of Section A and connected to Bus in
Section B.
 
Likewise, for connection on 400kV side also, 2 1 nos. 400kV GIS Bays
(consisting of 2 nos. CBs) shall be constructed (Double Bus Double Breaker
Scheme) in the space available near 400kV Bus Sectionaliser Area and using
GIB (Gas Insulated Bus Duct), the ICT shall be physically located in the area
of Section A and connected to Bus in Section B.

To deliberate on DB Power line 2 shifting from existing 400kV Bay No. 433 to Future
Bay 444 using additional BPIs (proposed under Sl.(a) above), a meeting was held
amongst CEA, CTUIL, POSOCO, POWERGRID and DB Power on 20/07/22 wherein
DB power expressed their apprehensions in shifting of their bay and subsequently
DB Power vide e-mail dated 26.07.2022 informed that the above shifting is not
acceptable to them.

In view of above, committee explored alternate arrangement for termination of


ICT bay in section-B using partly 400kV GIB duct and balance by BPI
arrangement as shown in the drawing at Flag-I.
Raigarh(Kotra) Section-A

Original Scope Site Visit Committee Revised Scope


Recommendation
765/400kV ICT: Space available 765/400kV ICT (Sec-A: 3rd):
1x1500MVA 1x1500MVA
765kV ICT bay: 1  New Diameter with bay nos. 765kV line bay: 2 nos. (1 no.
no. 710, 711 & 712 to be for change in termination of
constructed (AIS) in the space Champa-I line from existing
used for termination of bay to new bay
Champa-I 765kV line in Bay No. & 1 no. for termination of 3rd
715 (existing). ICT on Section A)
 Champa-I 765kV line to be Equipment of Existing Main
shifted from bay no. 715 to 710 bay of Champa-I line shall
(new) be shifted to New ICT Bay
 Equipment of Existing Main bay (ICT 3 bay) for utilization.
rd

(715) of Champa-I line shall be


shifted to New ICT Bay (ICT 3rd
bay no. 712)
 ICT to be terminated into bay
no. 712 (new)
 Bay no. 715 (existing) shall
remain vacant
400kV ICT bay: 1 Space available (Bay No. 421) 400kV ICT bay: 1 no.
no.

Raigarh(Kotra) Section-B

Original Scope Site Visit Report Recommendation Revised Scope


765/400kV ICT: ICT-I (3rd): 765/400kV ICTs (Sec-B: 3rd
2x1500MVA  Space Available & 4th): 2x1500MVA
ICT-II (4th):
 Space Available in area
earmarked for future ICT in the
other section (Section-A)
765kV ICT bay: 2 ICT-I (3rd): Sec-B: 3rd ICT
no.  Space Available (Bay No. 726)  765kV ICT bay (AIS): 1
ICT-II (4th): no.
 Due to space constraints / non Sec-B: 4th ICT
availability of required clearances  765kV ICT bay (GIS): 1
in Section-B, 1 no. 765kV GIS bay no. consisting of 2
(consisting of 2 breakers) to be breakers [with Double bus
constructed (Double bus double double breaker scheme
breaker scheme) in space near and the ICT (4th)
765kV bus sectionalizser area (physically located in the
and the ICT (physically located in space available near
section-A) to be connected with section-A) to be
Original Scope Site Visit Report Recommendation Revised Scope
the above bay through GIB Duct connected with the above
bay through GIB Duct]
400kV ICT bay: 2 ICT-I (3rd): Sec-B: 3rd ICT
no.  Space Available (Bay No. 444)  400kV ICT bay (AIS): 1
 Due to constraints w.r.t. no. (ICT shall be
available clearances on 400kV terminated into above bay
side, ICT shall be terminated using partly 400kV GIB
into above bay in section-B duct and balance by BPI
arrangement)
using partly 400kV GIB duct
and balance by BPI
arrangement

ICT-II (4th): Sec-B: 4th ICT


 Due to space constraints / non  400kV ICT bay (GIS): 1
availability of required clearances no. consisting of 2
in Section-B, 1 no. 400kV GIS bay breakers [with Double bus
(consisting of 2 breakers) to be double breaker scheme
constructed (Double bus double and the ICT (4th)
breaker scheme) in space near (physically located in the
400kV bus sectionalizer area and space available near
the ICT (physically located in the section-A) to be
space available near section-A) to connected with the above
be connected with the above bay bay through GIB Duct]
through GIB Duct

The cost of scheme was earlier mentioned as Rs. 210Cr. in the 8 th NCT meeting held
on 25.03.2022 and the same was arrived at considering Mar’20 price level. However,
considering Mar’22 level, the cost of scheme shall be about Rs. 274 Cr. Now, with
above changes in the scope of work, the revised cost of the scheme has been
worked out as Rs. 381 Cr. (i.e. increment by Rs. 107 Cr.).

POWERGRID vide letter dated 14.07.2022 has informed that although the scheme
was to be implemented by POWERGRID as per CTU OM dated 11.05.2022 in time-
frame of 15 months (i.e. Aug’23), the same is undergoing changes as per the site
visit held on 31.05.2022 & 01.06.2022 leading to cost and time escalation. Hence,
POWERGRID has requested approval for revised scheme with revised time-line of
implementation.

Matter may be deliberated.


2.0 Modification of future space provision in "Establishment of Khavda Pooling
Station-2 (KPS2) in Khavda RE Park" & "Establishment of Khavda Pooling
Station-3 (KPS3) in Khavda RE Park" schemes

Transmission system for KPS2 & KPS3 establishment was deliberated and approved
in the 3rd WRPC(TP) meeting held on 14.06.2021 and in the 5 th NCT meeting held on
25.08.2021 and 02.09.2021. Ministry of Power vide Gazette notification 5032(E)
published on 06.12.2021 has appointed RECPDCL as BPC for implementation of the
subject transmission schemes through TBCB route.

Subsequently, REC vide letter dated 10.05.2022 informed that as per discussions
amongst CEA, RECPDCL & GPCL on 26.04.2022 & between CEA & RECPDCL on
04.05.2022 & 09.05.2022, the following space requirement (for future expansion) at
KPS2 was felt:
 765kV line bays (future): 10 nos. instead of 8 nos.
 400kV line bays (future): 12 nos. instead of 10 nos.
 Space for proposed 8000MW HVDC System as well as BESS

Accordingly, CEA was requested to convene meeting to finalize total land


requirement for KPS2 & KPS3 as well as transmission line routes in Khavda RE
Park. Accordingly, a meeting was held on 24.05.2022 amongst CEA, CTU,
RECPDCL, GPCL & RE developers to discuss the above issues and the revised
land requirement for KPS2 & KPS3 as well as transmission line corridor
requirements in Khavda RE park were firmed up and communicated to GPCL by
REC vide letter dated 17.06.2022 (copy of requirement attached at Flag-II).

In view of the above changes in space for future provisions at KPS2 & KPS3, the
changes in scope of the schemesKPS2 are given as under:

Establishment of Khavda Pooling Station-2 (KPS2) in Khavda RE Park:


Sl. Scope of the Transmission Scope of the Transmission Scheme
No. Scheme (Original) (Revised)
1. Establishment of 765/400 kV, Establishment of 765/400 kV,
4x1500MVA, 4x1500MVA,
KPS2 (GIS) with 2x330 MVAR 765 kV KPS2 (GIS) with 2x330 MVAR 765 kV
bus bus
reactor and 2x125 MVAR 400 kV bus reactor and 2x125 MVAR 400 kV bus
reactor. reactor.

Adequate space for future expansion of Adequate space for future expansion of
5x1500 MVA 765/400 kV ICT’s 5x1500 MVA 765/400 kV ICT’s

Bus sectionalizer at 765kV & 400kV. Bus sectionalizer at 765kV & 400kV.
On each bus section, there shall be On each bus section, there shall be
Sl. Scope of the Transmission Scope of the Transmission Scheme
No. Scheme (Original) (Revised)
2x1500MVA 765/400kV ICTs, 2x1500MVA 765/400kV ICTs,
1x330MVAr, 765 kV & 1x125MVAr 1x330MVAr, 765 kV & 1x125MVAr
420kV bus reactor with space for future 420kV bus reactor with space for future
expansion. expansion.

Bus sectionalizer at 765 kV level shall Bus sectionalizer at 765 kV level shall
normally be closed and bus normally be closed and bus
sectionalizer at 400 kV level shall sectionalizer at 400 kV level shall
normally be open normally be open

Future provisions: Future provisions:


Space for Space for
765/400 kV ICTs along with bays: 5 765/400 kV ICTs along with bays: 5
nos. nos.
765kV line bay with switchable line 765kV line bay with switchable line
reactor: 8 nos. reactor: 10 nos.
400kV line bay with switchable line 400kV line bay with switchable line
reactor: 10 nos. reactor: 12 nos.
To take care of any drawal needs of 8000MW, ±800kV HVDC Converter
area in station (LCC)
future: 2GWhr Battery Energy Storage
400/220 kV ICT: 2 nos. System (0.5GWx4hr) (space requirement
220 kV line bays: 4 nos. of 20 acres per GWhr to be considered)
To take care of any drawal needs of
area in
future:
400/220 kV ICT: 2 nos.
220 kV line bays: 4 nos.
2. LILO of one ckt. of KPS1- Bhuj PS LILO of one ckt. of KPS1- Bhuj PS 765
765 kV D/c line at KPS2 kV D/c line at KPS2

Establishment of Khavda Pooling Station-3 (KPS3) in Khavda RE Park:


Sl. Scope of the Transmission Scope of the Transmission Scheme
No. Scheme (Original) (Revised)
1. Establishment of 765/400 kV, Establishment of 765/400 kV,
3x1500MVA, KPS3 (GIS) with 1x330 3x1500MVA, KPS3 (GIS) with 1x330
MVAR 765kV bus reactor and 1x125 MVAR 765kV bus reactor and 1x125
MVAR 400kV bus reactor. MVAR 400kV bus reactor.
Adequate space for future expansion Adequate space for future expansion
of of
Sl. Scope of the Transmission Scope of the Transmission Scheme
No. Scheme (Original) (Revised)
5x1500 MVA 765/400 kV ICT’s 5x1500 MVA 765/400 kV ICT’s

Future provisions: Future provisions:


Space for 765/400kV ICTs along with Space for 765/400kV ICTs along
bays: 5 nos. with bays: 5 nos.
765kV line bays: 4 nos. 765kV line bays: 4 nos.
400kV line bays: 10 nos. 400kV line bays: 10 nos.
9GWhr Battery Energy Storage
System (2.25GWx4hr) (space
requirement of 20 acres per GWhr to be
considered)

765kV Bus sectionalizer breaker: 2 765kV Bus sectionalizer breaker: 2


nos. nos.
400kV Bus sectionalizer breaker: 2 400kV Bus sectionalizer breaker: 2
nos. nos.

To take care of any drawal needs of To take care of any drawal needs of
area in future: area in future:
400/220kV ICT: 2 nos. 400/220kV ICT: 2 nos.
220kV line bays: 4 nos. 220kV line bays: 4 nos.
2. KPS3-KPS2 765kV D/c line KPS3-KPS2 765kV D/c line
3. 2 no. of 765kV line bays at KPS2 2 no. of 765kV line bays at KPS2
765kV S/s for KPS3-KPS2 765kV D/c 765kV S/s for KPS3-KPS2 765kV
line D/c line

It is re-iterated that GPCL has already been intimated regarding additional land
requirement at KPS2 & KPS3 considering above changes in future provision by REC
vide letter dated 17.06.2022. Further, additional corridor requirement for termination
of planned and future transmission lines from KPS1, KPS2 & KPS3 has also been
intimated to GPCL and it would be possible to award the scheme by REC only after
resolution of above land / corridor requirements in Khavda RE Park.Space for
Battery Energy Storage System (BESS) in Khavda RE Park:

As per discussions amongst CEA, CTU and RECPDCL in a meeting held under
chairmanship of Member(PS), CEA on 08.08.2022, it was preliminarily decided that
space for 5GW (for 4 hours) BESS (as considered in studies carried out for
integration of 181.5GW REZ under ISTS by 2030) may be reserved & distributed for
interconnectionjection with at each of KPS1, KPS2 & KPS3. For this purpose,
space may be kept reserved by GPCL outside the premises of KPS1 (under
implementation) & KPS2/KPS3 (under bidding). The above land requirement shall
not be under scope of future provisions of TSP implementing the above substations.

Members may deliberate.

3.0 Modification of future space provision in Transmission system for evacuation


of power from Chhatarpur SEZ (1500MW) scheme

MoP vide letter dated 13.06.2022 regarding location of new ISTS projects planned
under TBCB route has decided that where a proposed line is to connect to an
existing station, the transformers at terminal end must be located in the existing
station itself. A new substation will only be created if there is no space in the existing
substation after working out cost-benefit analysis of modernizing/reconfiguring
existing station vis-à-vis acquiring land and building new substation.

In view of above direction of MoP, it is proposed that Nnew ISTS substations (for
evacuation of power from potential RE Zones are planned based on RE Potential
data provided by MNRE/SECI with some additional space provisions to facilitate
future RE Injection / for meeting drawl requirements of STUs, etc) Drawl
requirements in the area. However, it is felt thatmay be planned with more space
provisions at such new substations need to be kept on account of following reasons:

 To be able to cater to significant enhancement of injection/drawl requirements


in the area in future, RE Generation Pooling sSubstations may be established
with a minimum transformation capacity of 4000-5000MVA.
 Outage of any single ICT unit should not overload the remaining ICT(s) or the
underlying system (i.e n-1 criterion to be followed)
 Where possible, Sspace provision for Battery Energy Storage Systems
(BESS) also needs tomay also be kept in vicinity of REZ Pooling Stations
(esp. considering appreciable space requirement of such systems). As a
thumb rule, space provision for BESS capacity of about 20% of REZ potential
identified by SECI/MNRE (for 4 hrs.) is proposed tomay be kept.

In view of the above, space provision at Chhatarpur PS being established under


Transmission system for evacuation of power from Chhatarpur SEZ (1500MW)
scheme (currently under tendering process) was reviewed and revised space
provision is given below:

Transmission system for evacuation of power from Chhatarpur SEZ (1500MW)


Sl. Scope of the Transmission Scope of the Transmission Scheme
No. Scheme (Original) (Revised)

1. (i) Establishment of 3x500MVA, (i) Establishment of 3x500MVA,


400/220 kV Pooling Station at 400/220 kV Pooling Station at
Chhatarpur Chhatarpur
(ii) 1x125 MVAR, 420 kV bus reactor (ii) 1x125 MVAR, 420 kV bus reactor at
at Chhatarpur PS Chhatarpur PS
(iii) 5 nos. 220kV line bays for solar (iii) 5 nos. 220kV line bays for solar park
park interconnection interconnection

*out of Satna – Bina 2xD/c lines, one *out of Satna – Bina 2xD/c lines, one
circuit of 2nd D/c line has been circuit of 2nd D/c line has been LILOed
LILOed at Sagar (MPPTCL) at Sagar (MPPTCL) substation. The
substation. The proposed LILO is to proposed LILO is to be made on the
be made on the other (1st) D/c line other (1st) D/c line between Satna &
between Satna & Bina Bina

Future provisions: Space to


accommodate: Future provisions: Space to
accommodate:
 400/220 kV, 500 MVA ICT
along with associated bays -1  400/220 kV, 500 MVA ICT along
 4 nos. of 220kV line bays with associated bays -5
 Sectionaliser arrangement  400 kV line bays: 6 nos.
 3x125MVAr Bus Reactor with
bay
 13 nos. of 220kV line bays
 Sectionaliser arrangement at
220kV (2 Sets) & 400kV (1 Set)
levels
 300MWx4hr. Battery Energy
Storage System (i.e. 20% of
1500MW REZ at Chhatarpur)
2. LILO of Satna – Bina 400kV (1 st) D/c LILO of Satna – Bina 400kV (1st) D/c
line at Chhatarpur PS line at Chhatarpur PS

Note: As per the MoP Gazette, scheme implementation is to be taken only after
grant of LTA. In this respect, it may be noted that Generation Projects are yet to be
identified at Chhatarpur PS.

The 400kV & 220kV buses may be sectionalized in future as per space given above
so that they may be operated in normally open / normally closed mode as per
requirement. Each bus section shall have provision for 2x125MVAr bus reactors,
4x500MVA, 400/220kV ICTs.
Further, space for 300MW (for 4 hours) BESS (i.e. 20% of 1500MW REZ Potential)
may be reserved outside the premises of Chhatarpur PS. The above land
requirement shall not be under scope of future provisions of TSP implementing the
above substation.

As per the MoP Gazette, scheme implementation is to be taken only after grant of
LTA. In this respect, it may be noted that Generation Projects are yet to be identified
at Chhatarpur PS.

The matter was discussed and in-principally agreed in the 9 th CMETS-WR meeting
held on 28.07.2022. In the meeting, M/s RUMSL werewas requested to intimate had
informed that they shall get back to CTU w.r.t.regarding adequate space availability
for the above revised land requirementscope as well as for installation of BESS in
vicinity of Chhatarpur PS.
for Chhatarpur PS in vicinity of their Solar Park. Inputs from M/s RUMSL are
awaited.

Members may deliberate.

4.0 Transmission System for Evacuation of Power from RE Projects in Rajgarh


(2500 MW) SEZ in Madhya Pradesh

The transmission scheme was agreed in the 2nd WRSCT and 2nd WRPC(TP)
meetings held on 21.05.2019 and 04.09.2020 respectively for evacuation of Power
from RE Projects in Rajgarh (2500 MW) SEZ in Madhya Pradesh in two phases: Ph-
I (1500MW) & Ph-II (1000MW). The transmission system was discussed and agreed on
in the 4th NCT (re-constituted vide MOP office order 13.04.2018) meeting held on
31.07.2019 & 4th NCT (re-constituted vide MOP office order 04.11.2019) meeting held on
20.01.2021 & 28.01.2021.

Ministry of Power, GOI vide Gazette notification dated 24.01.2020 had appointed REC
as the Bid Process Coordinator (BPC) for selection of Bidder as Transmission Service
Provider (TSP) to establish the subject transmission scheme through Tariff Based
Competitive Bidding (TBCB) process. Subsequently, MoP vide gazette notification dated
19.07.2021 had modified the scope of the subject transmission scheme after examining
the recommendations of the 4 th NCT meeting (held on 20.01.2020 & 28.01.2020) and
CEA such that the scope covered only the Transmission system for evacuation of power
from RE projects in Rajgarh (1500 MW) SEZ in Madhya Pradesh under Phase-I.

Phase-I of the scheme is under implementation by M/s GR Infraprojects Ltd. with SCOD
of 30.11.2023.
Now, SECI vide letter dated 23.06.2022 (refer Flag-III) has requested to initiate the
development of Pooling Stations simultaneously at various locations specified in the
letter, irrespective of the receipt of connectivity applications including Rajgarh Phase-
II (1000MW). The Phase-II of the scheme as agreed in the 4 th NCT meeting is given
below:

Sl. Scope of the Transmission Capacity/km.


No. Scheme

1. 400/220 kV, 2x500 MVA ICT 400/220 kV, 500 MVA ICT – 2
augmentation at Pachora PS 400 kV ICT bays – 2
220 kV ICT bays – 2
400 kV line bays – 2
220 kV line bays – 4
(to be taken up as per Connectivity/LTA
applications received)
2. Pachora – Shujalpur 400kV D/c line Length – 80 km
(Quad/HTLS) (with minimum capacity
of 2100MVA/ckt at nominal voltage)

3. 2 no. of 400 kV line bays at Shujalpur 400kV line bays – 2


for Pachora – Shujalpur 400kV D/c
line (Quad/HTLS) (with minimum
capacity of 2100MVA/ckt at nominal
voltage)

Note:
(i) Powergrid to provide space for 2 no. of 400 kV line bays at Shujalpur for
termination of Rajgarh SEZ PP – Shujalpur 400 kV D/c line.
(ii) Phase-II scheme to be taken up only after grant of Connectivity/LTA applications
beyond 1500 MW at Pachora P.S.
(ii) The schedule of implementation of Phase-II of the scheme would be matching
with schedule of RE developers or 18 months from the date of transfer of SPV
whichever is later.

Earlier, the Phase-II of the scheme was to be taken up only after grant of
Connectivity/LTA applications beyond 1500 MW at Pachora PS. However,
based on request of SECI to expedite the Phase-II of the scheme irrespective
of connectivity applications, the matter needs to be deliberated.

Further, to provide clarity regarding the conductor configuration of Pachora –


Shujalpur 400kV D/c line as well as bus sectionalizsation which shall be required at
220kV level, the revised scope is given below (changes marked in bold):
Sl. Scope of the Transmission Capacity/km.
No. Scheme

1. 400/220 kV, 2x500 MVA ICT 400/220 kV, 500 MVA ICT – 2
augmentation at Pachora PS 400 kV ICT bays – 2
220 kV ICT bays – 2
400 kV line bays – 2
220 kV line bays – 4
(to be taken up as per Connectivity/LTA
applications received)
220kV Bbus Sectionaliser – 1 set
220kV TBC bay – 1 no.
220kV BC bay – 1 no.
2. Pachora – Shujalpur 400kV D/c line Length – 80 km
(Quad ACSR/AAAC/AL59 Moose
equivalent)

3. 2 no. of 400 kV line bays at Shujalpur 400kV line bays – 2


for Pachora – Shujalpur 400kV D/c
line (Quad ACSR/AAAC/AL59
Moose equivalent)

Note:
(i) Powergrid to provide space for 2 no. of 400 kV line bays at Shujalpur for
termination of Rajgarh SEZ PP – Shujalpur 400 kV D/c line.
(ii) Phase-II scheme to be taken up only after grant of Connectivity/LTA applications
beyond 1500 MW at Pachora P.S.
(ii) The schedule of implementation of Phase-II of the scheme would be matching
with schedule of RE developers or 18 months from the date of transfer of SPV
whichever is later.

Members may deliberate.

---xx--------xx---

You might also like