CERTIFICATE OF COMPLETION

Date: October 13. 2020


Project Title: Design, Supply and Installation of Booster Pumps
Location of Project: Calumpit Bulacan
Project Owner Calumpit Water District
Contractor/Supplier AQUA HAUS, INC.
Approved Contract Amount 2,762,500.00
Date of Completion October 13, 2020

This is to certify that the above-stated project has been jointly inspected and found to be
satisfactory completed, all in accordance with the plans and specifications of the contract
and based on the Final Inspection Report.

Certified by:

Chito D. Cole
President & CEO