Ref: DWE-COS-HSE-TMP-00120

Rev: A.1
ENERGISATION NOTICE
Date: 14-JUL-2022
DWMC Project Page: 1/2

Kiosk Temporary
Location: Power Supply Date: 27.07.2022 No.: H-EN0001

1. Description of System/Sub-System or Component to be Energised:


00 BBB 11kV Switchgear for temporary power supply will be energize from DEWA Point
Area is highlighted in attached document

2. Test Cert Attached? Associated TOP No.


Yes
TOP-17AA-00-L0
No ✘
3. The unenergised system/sub-system or component listed above has passed through the
TOP on:
Date: 27.07.2022 Time: 13.30

Note: Testing or energisation of systems which have not yet been subject to the TOP pro-
cess can only be authorised by the Commissioning Manager or Site Manager
4. Additional information including supporting document numbers:
Only authorised personnel will be allowed within these areas. A Safety Document will be re-
quired from the SAP for any work inside. Anyone found interfering with electrical/mechan-
ical equipment who does not hold the relevant Safety Document will be removed from site.

EPC has placed many safety signs where they are required for information and safety. Any
person found removing or modifying any signage or sticker within this area will be removed
from site

Only qualified technicians will work on this equipment under the control of a Competent Per-
son holding the relevant Safety Document

All isolation keys will be under strict control by the SAP within the LOTO Office.

A Toolbox Talk must be carried out with all workers detailing the dangers of the above. A
signed copy of the Toolbox Talk record will be available on site.

EPC will monitor this task very closely and constantly re-assess the safety measures in
place. If there are any doubts to whether something is unexpectedly live the work must be
stopped immediately and the area made safe. The incident must be reported straight away to
the EPC HSE.

EPC is re-emphasising that if anyone has doubt over safety they should “STOP THE JOB”

Emergency contacts for the above are: SAP-E Bruno Hasenbichler +971 50 485 6323
COLEN Ugur Yucel +971 54 996 3601
COLEN Hamza Fadil +971 54 996 3903
Ref: DWE-COS-HSE-TMP-00120

Rev: A.1
ENERGISATION NOTICE
Date: 14-JUL-2022
DWMC Project Page: 2/2

5. Power Source (voltage, AC/DC, gas/liquid type, pressure, temperature):


     

6. Isolations:
     

7. Authorisations:
Senior Authorised Person
      Signature:       Date:      
Mechanical (SAP - M):

Senior Authorised Person


      Signature:       Date:      
Electrical (SAP - E):

Commissioning/Site Manager:       Signature:       Date:      

You might also like