MS-ASU-059 Tubbing Leak Test
MS-ASU-059 Tubbing Leak Test
Osman Türkkan
Approved by Sign.
Construction Manager
Burak Ozyazan
Verifiyed by Sign.
QA / QC Chief
FARAH BADREDINE
Verifiyed by Sign.
HSE
Verifiyed by Sign.
REVISION HISTORY
Rev. Date Status and Description
00 21.02.2022 Issued for review
ARZEW ASU PROJECT
Date: Page
Rev.
Document No.: MS-ASU-059 :
21.FEBUARY.
00 2022 2/5
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. IMPROVEMENT
4. REFERENCES
5. RESPONSIBILITIES
6. DEFINITIONS AND ABBREVIATIONS
7. GENERAL DESCRIPTION:
7.TEST PROCEDURE DETAIL:
This document is Ronesans Heavy Industries property, and this document may not, in part or in whole, be reproduced, published or distributed in any
manner without the prior written approval of RHI..
ARZEW ASU PROJECT
Date: Page
Rev.
Document No.: MS-ASU-059 :
21.FEBUARY.
00 2022 3/5
PURPOSE
The purpose of this procedure is to describe the steps for leak test tubbing work in accordance with
the specified requirements for ASU ARZEW.
SCOPE
This is applicable for leak test tubbing work for all installed systems in ASU ARZEW. This method
statement defines minimum requirements but not limited, involved with instrument part , ensure that
full compliance with ASU requirements, safety, perfection and durability as per approved drawings
and specifications in the “Realization of An Industrıal Complex for Asu Project located in Arzew .
IMPROVEMENT
Users of the document who identify inaccuracy or ambiguity can notify the custodian or his/her
delegate and request changes be initiated.
REFERENCES
. REFERENCE DOCUMENTS:
> ASME B31.3 Pneumatic Testing (para345.5).
>4WPI-EW44001 TESTING AREA PREPARATION CONTRO par. 10, 11, 12, 13
>4WPI-EW44001 PRESSURE TEST EXECUTION par. 14
>4WPI-EW44001 LINE REINSTATEMENT - WORK ACCEPTANCE par. 15.2
RESPONSIBILITIES
The safety manager will be responsible for ensuring of the all activities related to preparation and
roof waterproofing works as per site safety procedures.
This document is Ronesans Heavy Industries property, and this document may not, in part or in whole, be reproduced, published or distributed in any
manner without the prior written approval of RHI..
ARZEW ASU PROJECT
Date: Page
Rev.
Document No.: MS-ASU-059 :
21.FEBUARY.
00 2022 4/5
This document is Ronesans Heavy Industries property, and this document may not, in part or in whole, be reproduced, published or distributed in any
manner without the prior written approval of RHI..
ARZEW ASU PROJECT
Date: Page
Rev.
Document No.: MS-ASU-059 :
21.FEBUARY.
00 2022 5/5
7. GENERAL DESCRIPTION:
Pressure Step and Inspection timing:
Step-1: Pressure should be gradually increased to 5 PSI for initial inspection and hold 10 minutes.
Step-2: at 5 psi maintain, then soapy check for all joints including flanges. using soap solution,
spray all flanges and related tubbing work and observe for bubbles. Bubbles are indicative of
leaking points
Step-3: De-pressurize up to 0.0 bar (end of Test).
If there is any leak from Flange joints, depressurize up to 0 bar (re-test back to 5 psi).
8. TEST PROCEDURE DETAIL:
Nitrogen cylinder to be used and testing team shall be placed outside evacuation zone
8-1. Circuit Monitoring and Checking:
- For tubbing leak testing of circuits, access to the area of the test shall be limited to only the
personnel directly involved in the test or personnel involved in the inspection and monitoring.
- Soft Barricade (Red and White) shall be installed and a watchmen should ensure that no
personnel enter the area.
8-2. Exclusions
- The followings are excluded from the testing requirements of this specification:
a. Any package unit previously tested by the vendor in accordance with the applicable codes.
b. Lines and systems which are open to the atmosphere such as drain, vents, open discharge of
relief valve, and atmospheric sewers.
no leakage is found and no unaccounted pressure drop noticed during the agreed time interval .