Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
METHOD STATEMENT :
DRAINAGE WORKS
JOB TITLE:
Prepared by Signature
Effective Date
11/03/2024
1
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
INDEX
1.0 OBJECTIVE
11.0 APPENDIX
2
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
1.0 OBJECTIVE:
This work method statement covers outline procedure for Drainage Works for DESIGN AND
BUILD FOR THE PROPOSED OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH AIRPORT, IPOH, PERAK DARUL
RIDZUAN.
1. Site Agent
2. Site Supervisor
3. Workers
4.
5.
6.
7.
3
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
4.0 MATERIAL LIST (SDS required for any chemical need to be used)
Below is the list of materials that will be used in this scope of work:
1. Portland Cement
2. Sand
3. Drain
4.
5.
6.
Production
Machineries / Tools Working Hours / Day
No Rate / Unit / Day
Backhoe
1.
Tipper Lorry
2.
Concrete Mixer
3.
Portable Water Pump
4.
Compactor (Plate/Vibrator)
5.
6.
7.
4
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
6.1 INTRODUCTION
6.1.1 This method statement applies to all personnel involved in the construction and supervision of the
works including the consultant site staff required for inspection and approval works.
6.1.1 Material for permanent construction such as precast block drain U-shape & pipe culvert
shall be submitted by the project engineer in the form of sample or technical brochures by
using material approval form and all approval in writing to be obtained from the consultant
prior to commencement of works.
6.1.2 For the proposed of this method statement, surface drainage includes all permanent drains in open
ground such as roadside drains (e.g. side table drain, block drain, back lane drain, rc pipe culvert
and sump).
6.1.3 Request for inspection and all checklist shall be submitted by the project engineer and all approval
in writing to be obtained from the consultant prior to commencements of works.
6.2.2 Site working drawing approved by the consultant for each typed of drain prepared by the project
engineer shall be used to assist in the correct setting out of the drain.
6.2.3 The alignment of the drain is set out by a series of pegs with the corresponding offset pegs set at
equal distance away & indicate with the required excavation depth to foundation level.
6.3 EXCAVATION
6.3.1 Depending on the size & depth of the drain, the trench of channel shall be excavated using the
appropriate levels set out in the offset pegs and under the charge of site supervisor.
6.3.2 The excavated materials are either stockpile nearby to be reused for backfilling or disposed off site
by haulage tipper to spoils tips.
6.3.3 Where soft sport are encountered at the foundation level, either the unsuitable material are removed
and replace with suitable and compacted imported materials or the localized excavation made good
with mass concrete or as directed by consultant.
6.3.4 For excavation or trench deeper than 1.5m, temporary shoring such as timbering shall be provided if
the existing ground not in good condition.
6.3.5 For excavation of trench in firm ground, a side slope 1V:0.5H batter shall be provided.
5
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
6.4.1 The foundation shall be prepared as shown in the construction drawings and joint inspection with
C.O.W shall carry out if necessary.
6.4.2 dewatering by water pump maybe required to enable a dry surface working.
6.4.3 When blinding layer is required it should be placed immediately after the foundation preparation
has been completed to protected it from inclement weather.
6.4.4 Where the foundation specified is sand replacement, the sand shall be replaced in layer and
compacted by approved compacting equipment.
6.6 BACKFILLING
6.6.1 All backfilling shall be carried out using approved materials such as sand or suitable earth fill
depending on the type of drains.
6.6.2 Prior to backfilling a joint site inspection shall be carried out to ensure that the drains are not
defective on the external side and all unsuitable material and debris are removed from the backfill
area.
The airside activities that will be carried out during the operation stage and the potential
environmental impact that may occur is summarized with mitigation measures in the following
table.
6
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
7
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
vii. All workers need to stay alert of any potential hazards such as dangerous substance and
confined spaces, so that measures can be developed to eliminate and minimize the risks.
viii. All the workers must ensure that the working area is cleaned and is in safe condition after the
work is completed.
3)
2)
3)