Document No : TBR-P-PM-MS-01

Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

METHOD STATEMENT :
DRAINAGE WORKS

JOB TITLE:

DESIGN AND BUILD FOR THE PROPOSED


OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH
AIRPORT, IPOH, PERAK DARUL RIDZUAN

Prepared by Signature

TERAS BUDI RESOURCES SDN BHD

Reviewed by Process Owner Signature

Effective Date
11/03/2024

1
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

INDEX

1.0 OBJECTIVE

2.0 PROJECT ORGANISATION

3.0 MANPOWER LIST

4.0 MATERIAL LIST

5.0 MACHINERY AND TOOLS

6.0 METHOD OF STATEMENT (METHODOLOGY)

7.0 ENVIROMENTAL ISSUES

8.0 QUALITY ASSURANCE & QUALITY CONTROL

9.0 SAFETY MEASUREMENT

10.0 FINAL REPORT

11.0 APPENDIX

2
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

1.0 OBJECTIVE:
This work method statement covers outline procedure for Drainage Works for DESIGN AND
BUILD FOR THE PROPOSED OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH AIRPORT, IPOH, PERAK DARUL
RIDZUAN.

2.0 PROJECT ORGANISATION:


Company Name MALAYSIA AIRPORT SDN BHD
MALAYSIA AIRPORTS CORPORATE OFFICE,
Address PERSIARAN KORPORAT KLIA,
64000 KLIA, SEPANG,
SELANGOR DARUL EHSAN
Contact Person
Position
Contact Number

3.0 MANPOWER LIST


Below is the list of manpower involved in this scope of work:
No. Name Designation Initial

1. Site Agent

2. Site Supervisor

3. Workers

4.

5.

6.

7.

3
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

4.0 MATERIAL LIST (SDS required for any chemical need to be used)
Below is the list of materials that will be used in this scope of work:

No. Material / Chemical


Model / Brand

1. Portland Cement

2. Sand

3. Drain

4.

5.

6.

5.0 MACHINERIES AND TOOLS


Below is the list of machinery and tools that will be used in this scope of work:

Production
Machineries / Tools Working Hours / Day
No Rate / Unit / Day

Backhoe
1.
Tipper Lorry
2.
Concrete Mixer
3.
Portable Water Pump
4.

Compactor (Plate/Vibrator)
5.

6.

7.

4
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

6.0 METHOD OF STATEMENT (METHODOLOGY)

6.1 INTRODUCTION

6.1.1 This method statement applies to all personnel involved in the construction and supervision of the
works including the consultant site staff required for inspection and approval works.
6.1.1 Material for permanent construction such as precast block drain U-shape & pipe culvert
shall be submitted by the project engineer in the form of sample or technical brochures by
using material approval form and all approval in writing to be obtained from the consultant
prior to commencement of works.

6.1.2 For the proposed of this method statement, surface drainage includes all permanent drains in open
ground such as roadside drains (e.g. side table drain, block drain, back lane drain, rc pipe culvert
and sump).
6.1.3 Request for inspection and all checklist shall be submitted by the project engineer and all approval
in writing to be obtained from the consultant prior to commencements of works.

6.2 SETTING OUT


6.2.1 The exact location & alignment of each type of drain is set out on site by the survey team
after checking with the project engineer or supervisor according to construction drawing.
The project engineer shall then carry out and alignment inspection with the consultant site
staff to obtain his approval prior commencement of excavation.

6.2.2 Site working drawing approved by the consultant for each typed of drain prepared by the project
engineer shall be used to assist in the correct setting out of the drain.
6.2.3 The alignment of the drain is set out by a series of pegs with the corresponding offset pegs set at
equal distance away & indicate with the required excavation depth to foundation level.

6.3 EXCAVATION

6.3.1 Depending on the size & depth of the drain, the trench of channel shall be excavated using the
appropriate levels set out in the offset pegs and under the charge of site supervisor.
6.3.2 The excavated materials are either stockpile nearby to be reused for backfilling or disposed off site
by haulage tipper to spoils tips.
6.3.3 Where soft sport are encountered at the foundation level, either the unsuitable material are removed
and replace with suitable and compacted imported materials or the localized excavation made good
with mass concrete or as directed by consultant.
6.3.4 For excavation or trench deeper than 1.5m, temporary shoring such as timbering shall be provided if
the existing ground not in good condition.
6.3.5 For excavation of trench in firm ground, a side slope 1V:0.5H batter shall be provided.

5
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

6.4 FOUNDATION PREPARATION

6.4.1 The foundation shall be prepared as shown in the construction drawings and joint inspection with
C.O.W shall carry out if necessary.
6.4.2 dewatering by water pump maybe required to enable a dry surface working.
6.4.3 When blinding layer is required it should be placed immediately after the foundation preparation
has been completed to protected it from inclement weather.
6.4.4 Where the foundation specified is sand replacement, the sand shall be replaced in layer and
compacted by approved compacting equipment.

6.5 DRAIN CONSTRUCTION


6.5.1 The different type of drains is laid on to the foundation either by hand such as small precast units of
roadside & suitable machineries for RC pipe culvert.
6.5.2 For precast concrete drain, the gaps between precast unit are filled up with cement sand mortar 1:3
mixes and thoroughly rammed into place.
6.5.3 For roadside drains, the weep hole is provided with graded filters wrapped found inside a geotextile
membrane behind the wall and held in place by initial backfilling of compacted material. Brickwork
of concrete courses and cement rendering for the wall shall be carried out as shown in the drawing.

6.6 BACKFILLING
6.6.1 All backfilling shall be carried out using approved materials such as sand or suitable earth fill
depending on the type of drains.
6.6.2 Prior to backfilling a joint site inspection shall be carried out to ensure that the drains are not
defective on the external side and all unsuitable material and debris are removed from the backfill
area.

6.7 AS-BUILT DRAWING


6.7.1 A-built drawing will be taken after the drawing work completed, show the drain alignment, drain
size, drain type, drain invert level, size of sump & sump invert level.

7.0 ENVIRONMENTAL ISSUES

7.1 Environmental Aspect, Impact & Control Measures.

The airside activities that will be carried out during the operation stage and the potential
environmental impact that may occur is summarized with mitigation measures in the following
table.

6
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

Activities Aspects Potential Impact Proposed Mitigation


Inspection/Operation Routine inspection Oil/lubricant Perform oil/lubricant
and maintenance spillage replacement with funnel
and spillage container.
Fuel filling Perform fuel filling by using
funnel and spillage
container.

Mobilisation Moving in and out Smoke emission Ensure vehicle


maintenance is done as
per schedule
8.0 QUALITY ASSURANCE & QUALITY CONTROL

8.1 Contractual Requirements


As per Tender Document requirement.

8.2 Inspection & Reporting :


i) Site Diary
ii) Test Form

8.3 Follow up & Evaluation


Shall refer to our Standard Operation Procedure.

9.0 SAFETY MEASUREMENT


i. All work is prohibited to start before receiving Permit to Work (PTW) by the Building Owner/
Project Owner.
ii. All site worker is compulsory to attend safety induction from the project authorities to ensure
that all worker is aware of site requirement.
iii. Use the proper tool for the job. Worker needs to avoid the first impulse to use whatever tool
(or object) is around you to get a work task done. Using the wrong tool for the job can result
in an injury or damage to the tool which can lead to an injury in the future.
iv. Always wear the proper PPE for the work task. All worker is obligated to ware complete
Personal Protective Equipment (PPE) such as safety helmet, coverall, safety shoes and etc.
v. Working areas must be secured by preventing unauthorized access by using barrier and
signs.
vi. All worker is to make sure chemicals are properly labelled and stored. Improper labelling and
storage can lead to injuries or property loss due to fires, corrosion, etc.

7
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

vii. All workers need to stay alert of any potential hazards such as dangerous substance and
confined spaces, so that measures can be developed to eliminate and minimize the risks.
viii. All the workers must ensure that the working area is cleaned and is in safe condition after the
work is completed.

10.0 FINAL REPORT (types of report)

1) Photo Progress Report

2) Request for Inspection

3)

11.0 APPENDIX (if available i.e. drawing, plan, catalog etc.)


List down the necessary document and attached together with method statement.
1)

2)

3)