Professional Documents
Culture Documents
MOS Column
MOS Column
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
METHOD STATEMENT :
CONCRETE WORK (COLUMN)
JOB TITLE:
DESIGN AND BUILD FOR THE PROPOSED
OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH
AIRPORT, IPOH, PERAK DARUL RIDZUAN
Prepared by Signature
Effective Date
11/03/2024
1
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
INDEX
1.0 OBJECTIVE
11.0 APPENDIX
2
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
1.0 OBJECTIVE:
This work method statement covers outline procedure for Column Works for DESIGN AND
BUILD FOR THE PROPOSED OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH AIRPORT, IPOH, PERAK DARUL
RIDZUAN.
1. Construction Manager
2. Site Engineer
3. Site Supervisor
5. Surveyor
6. Operator
7. Workers
3
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
4.0 MATERIAL LIST (SDS required for any chemical need to be used)
Below is the list of materials that will be used in this scope of work:
4.
5.
6.
1. Batching plant.
4
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
6.1 GENERAL
6.1.1 The level of the concrete slab shall be checked as per drawing and the height of first floor
level be checked to determine the height of column as per drawing.
6.1.2 Starter bar of every column shall be checked to ensure that there has enough lapping
length as per drawing requirement. (normally is 45 time of bar size)
6.2.1 The surveyor will provide and transfer a gridline references mark to surface of concrete
floor.
6.2.2 Base on the gridline references, the carpenter has to set out the column position with right
angle marker at every column. This reference is to guide the barbender to install and fix up
the steel bar of column.
6.3.1 Re-bar shall then be fixed accordingly. The bar bender must be making sure that the
position of reinforcement shall not be out from the right angel marker provided by
carpenter.
6.3.2 Before formwork of column to be erected and fixed, main contractor’s Engineer shall
inspect the reinforcement for approval.
6.3.3 After four side of formwork are fixed, carpenter shall make sure that the formwork of
column are vertical by using split level and plumb bob. This checking shall be checked all
corner of every column and tighten up using 1”x2” timber nailed on surface on concrete
slab.
6.3.4 An opening must be provided at middle height of every column, these are to guide the
concreter to check the concrete
6.3.5 Reference level shall then be marked on formwork of every column. These are to check
the differences of uneven surface of concrete slab an to determine finish top level of
formwork which will receive soffit formwork of first floor beam for the purposed to make
sure that the soffit of the first floor beam are straight and in level when connected from one
column to another column.
6.4 CASTING
6.4.1 Preparation
6.4.1.1 Lighting facilities to be provided at area where night pouring is expected and
tested
5
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
6.4.1.2 Access for mixer truck and mobile crane have to be prepared.
6.4.1.3 Chute, poker, engine, fuel, bucket and worker should be in place ready for the
work.
6.4.2.1 Clear instruction must be given to all supervisors, crane operator & workers on the
casting sequence to avoid cold joint & confusion prior to placing of concrete.
6.4.2.2 Pouring shall be carried with two parts for each column, these mean that first part
pouring shall be half height of column and after continually to two or three column
and before the concrete of the first column become set, the second part must be
continuing.
6.4.2.3 Step of 4.4.2.2 is to make sure all column is constantly vibrated and to avoid
honeycomb occur.
6.4.2.4 If heavy rain falls during concreting, protective tarpaulin sheet shall be used to
cover the freshly laid concrete. If continues longer than expected then a
construction joint shall be formed.
6
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
The airside activities that will be carried out during the operation stage and the potential
environmental impact that may occur is summarized with mitigation measures in the following
table.
v. Working areas must be secured by preventing unauthorized access by using barrier and
signs.
vi. All worker is to make sure chemicals are properly labelled and stored. Improper labelling and
storage can lead to injuries or property loss due to fires, corrosion, etc.
vii. All workers need to stay alert of any potential hazards such as dangerous substance and
confined spaces, so that measures can be developed to eliminate and minimize the risks.
viii. All the workers must ensure that the working area is cleaned and is in safe condition after the
work is completed.
3)
2)
3)