Document No : TBR-P-PM-MS-01

Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

METHOD STATEMENT :
SEWERAGE WORKS

JOB TITLE:
DESIGN AND BUILD FOR THE PROPOSED
OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH
AIRPORT, IPOH, PERAK DARUL RIDZUAN

Prepared by Signature

TERAS BUDI RESOURCES SDN BHD

Reviewed by Process Owner Signature

Effective Date
11/03/2024

1
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

INDEX

1.0 OBJECTIVE

2.0 PROJECT ORGANISATION

3.0 MANPOWER LIST

4.0 MATERIAL LIST

5.0 MACHINERY AND TOOLS

6.0 METHOD OF STATEMENT (METHODOLOGY)

7.0 ENVIROMENTAL ISSUES

8.0 QUALITY ASSURANCE & QUALITY CONTROL

9.0 SAFETY MEASUREMENT

10.0 FINAL REPORT

11.0 APPENDIX

2
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

1.0 OBJECTIVE:
This work method statement covers outline procedure for Sewerage Works for DESIGN AND
BUILD FOR THE PROPOSED OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH AIRPORT, IPOH, PERAK DARUL
RIDZUAN.

2.0 PROJECT ORGANISATION:


Company Name MALAYSIA AIRPORT SDN BHD
MALAYSIA AIRPORTS CORPORATE OFFICE,
Address PERSIARAN KORPORAT KLIA,
64000 KLIA, SEPANG,
SELANGOR DARUL EHSAN
Contact Person
Position
Contact Number

3.0 MANPOWER LIST


Below is the list of manpower involved in this scope of work:
No. Name Designation Initial

1. Site Agent

2. Site Supervisor

3. Workers

4.

5.

6.

7.

3
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

4.0 MATERIAL LIST (SDS required for any chemical need to be used)
Below is the list of materials that will be used in this scope of work:

No. Material / Chemical


Model / Brand

1. Common Clay Brick / Cement Brick

2. Portland Cement

3. Sand

4. Bituminous damp proof membrane

5. Tie Rod

6. Exmet

5.0 MACHINERIES AND TOOLS


Below is the list of machinery and tools that will be used in this scope of work:

Production
Machineries / Tools Working Hours / Day
No Rate / Unit / Day

1. Concrete Mixer

2. Excavator / Backhoe

3. Portable water pump

4. Compactor (Plate / Vibrator)

5. Tipper Lorry

6.

7.

4
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

6.0 METHOD OF STATEMENT (METHODOLOGY)

6.1 INTRODUCTION
6.1.1 This method statement applies to all personnel involved in the construction and
supervision of the works including the consultant’s site staff required for inspection and approval
of works.
6.1.2 Materials for permanent construction such as 150mm dia. verified clay pipe (vcp) and
Concrete ring shall be submitted by the Site Engineer in the form of samples or technical
brochures by using Material Approval Forms and all approvals in writing must be obtained from
the Consultant prior to commencement of works.
6.1.3 Request for Inspection and checklist shall be submitted by the site Engineer and all
approvals in writing to be obtained from the consultants prior to commencement of works.

6.2 SETTING OUT


The exact location and alignment of sewer line will be set by the surveyor after checking with the
Site Engineer or supervisor follow the drawing above. The site Engineer shall then carry out an
alignment inspection with the consultant site staff to obtain his approval prior to commencement
of excavation'
6.2.2 Site working drawings approved by the consultant for sewer work prepared by the site
Engineer shall be used to assist in the correct setting out of the sewer line.
6.2.3 The alignment of the sewer line will be set out only fur the manhole location and the
manhole invert level

6.3 EXCAVATION
6.3.1 The trench shall be excavated using the excavator / backhoe until to excavation levels set
out in the offset pegs and under the charge of the Site Supervisor.
6.3.2 The excavated materials are either stockpiled nearby to be reused for backfilling or
disposed offsite by haulage tippers to spoils tips.
6.3.3 For excavation of trench deeper than 1.5m, temporary shoring such as timbering shall be
provided if the existing ground not in good condition.
6.3.4 Prior to excavation, the Site Supervisor shall ensure that are no underground services are
in the way as to be damaged in the prior. Relocation of the affected services may be required to
facilitate the construction of the sewer line.

6.4 MANHOLE
) Foundation

5
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

6.4.1 The foundation shall be prepared as shown in the construction drawings and a joint
inspection with Consultant site staff shall carried out.
6.4.2 Dewatering by water pumps maybe required to enable dry surface for working.
6.4.3 When blinding layer is required, it should be placed immediately after the foundation
preparation has been completed to protect it from inclement weather.
6.4.4 Where the foundation specified is sand replacement the sand shall be replaced in layers
and compacted by approved compacting equipment.

b) New Manhole
6.4.1 The concrete ring installed base on the depth of the Manhole and the finish road level to
ensure the concrete ring high is acceptable.
6.4.2 The manhole cover used shall be approved by JPP/IWK.
6.4.3 All around the inside of manhole should be paint with alumina paint to replaced 20rnm
thick rendering in alumina cement and sand.

6.5 SEWERLINE CONSTRUCTION


a) VCP Pipe (Manhole to Manhole line – outside building)
6.5.1 Due to the constraint of site working, the vcp pipe will lay after l0 meter excavation and
this activity shall be continued until complete the sewer line.
6.5.2 After the excavation until required level, the hardcore will lay and compacted as a sewer
bedding to replace with 20mm aggregate.
6.5.3 The VCP pipe connected to other VCP pipe follow the manufacture specification, using
the rubber ring and the sewer layer will check the gradient of vcp pipe laid use water level to
ensure the VCP pipe have a gradient.
6.5.4 The supervisor will check the Invert level after complete lay 10 meter VCP pipe before the
backfilling work proceed.
6.5.6 Before the backfilling, the hardcore will lay until the top of VCP pipe.

6.6 BACKFILLING
6.6.1 All this backfilling will use suitable material such as sand or hardcore and existing
excavated earth.
6.6.2 The backfilling will be compacted in layers of sand / hardcore and suitable excavated
earth.
6.6.3 Prior to backfilling, a visual inspection shall be carded out to ensure that the sewer line is
not have movement on the alignment and all unsuitable materials and debris are removed from
the backfill area.

6
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

6.7 AS BUILT DRAWING


6.7.1 As-built drawing will be taken after the sewerage reticulation work completed, show the
sewer pipe size, length, manhole position and manhole invert level.

7.0 ENVIRONMENTAL ISSUES

7.1 Environmental Aspect, Impact & Control Measures.

The airside activities that will be carried out during the operation stage and the potential
environmental impact that may occur is summarized with mitigation measures in the following
table.

Activities Aspects Potential Impact Proposed Mitigation


Inspection/Operation Routine inspection Oil/lubricant Perform oil/lubricant
and maintenance spillage replacement with funnel
and spillage container.
Fuel filling Perform fuel filling by using
funnel and spillage
container.

Mobilisation Moving in and out Smoke emission Ensure vehicle


maintenance is done as
per schedule
8.0 QUALITY ASSURANCE & QUALITY CONTROL

8.1 Contractual Requirements


As per Tender Document requirement.

8.2 Inspection & Reporting :


i) Site Diary
ii) Test Form

8.3 Follow up & Evaluation


Shall refer to our Standard Operation Procedure.

9.0 SAFETY MEASUREMENT


i. All work is prohibited to start before receiving Permit to Work (PTW) by the Building Owner/
Project Owner.

7
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024

ii. All site worker is compulsory to attend safety induction from the project authorities to ensure
that all worker is aware of site requirement.
iii. Use the proper tool for the job. Worker needs to avoid the first impulse to use whatever tool
(or object) is around you to get a work task done. Using the wrong tool for the job can result
in an injury or damage to the tool which can lead to an injury in the future.
iv. Always wear the proper PPE for the work task. All worker is obligated to ware complete
Personal Protective Equipment (PPE) such as safety helmet, coverall, safety shoes and etc.
v. Working areas must be secured by preventing unauthorized access by using barrier and
signs.
vi. All worker is to make sure chemicals are properly labelled and stored. Improper labelling and
storage can lead to injuries or property loss due to fires, corrosion, etc.
vii. All workers need to stay alert of any potential hazards such as dangerous substance and
confined spaces, so that measures can be developed to eliminate and minimize the risks.
viii. All the workers must ensure that the working area is cleaned and is in safe condition after the
work is completed.

10.0 FINAL REPORT (types of report)

1) Photo Progress Report

2) Request for Inspection

3)

11.0 APPENDIX (if available i.e. drawing, plan, catalog etc.)


List down the necessary document and attached together with method statement.
1)

2)

3)