Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
METHOD STATEMENT :
SEWERAGE WORKS
JOB TITLE:
DESIGN AND BUILD FOR THE PROPOSED
OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH
AIRPORT, IPOH, PERAK DARUL RIDZUAN
Prepared by Signature
Effective Date
11/03/2024
1
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
INDEX
1.0 OBJECTIVE
11.0 APPENDIX
2
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
1.0 OBJECTIVE:
This work method statement covers outline procedure for Sewerage Works for DESIGN AND
BUILD FOR THE PROPOSED OPTIMIZATION OF TERMINAL FACILITIES AND ITS
ASSOCIATED WORKS AT SULTAN AZLAN SHAH AIRPORT, IPOH, PERAK DARUL
RIDZUAN.
1. Site Agent
2. Site Supervisor
3. Workers
4.
5.
6.
7.
3
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
4.0 MATERIAL LIST (SDS required for any chemical need to be used)
Below is the list of materials that will be used in this scope of work:
2. Portland Cement
3. Sand
5. Tie Rod
6. Exmet
Production
Machineries / Tools Working Hours / Day
No Rate / Unit / Day
1. Concrete Mixer
2. Excavator / Backhoe
5. Tipper Lorry
6.
7.
4
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
6.1 INTRODUCTION
6.1.1 This method statement applies to all personnel involved in the construction and
supervision of the works including the consultant’s site staff required for inspection and approval
of works.
6.1.2 Materials for permanent construction such as 150mm dia. verified clay pipe (vcp) and
Concrete ring shall be submitted by the Site Engineer in the form of samples or technical
brochures by using Material Approval Forms and all approvals in writing must be obtained from
the Consultant prior to commencement of works.
6.1.3 Request for Inspection and checklist shall be submitted by the site Engineer and all
approvals in writing to be obtained from the consultants prior to commencement of works.
6.3 EXCAVATION
6.3.1 The trench shall be excavated using the excavator / backhoe until to excavation levels set
out in the offset pegs and under the charge of the Site Supervisor.
6.3.2 The excavated materials are either stockpiled nearby to be reused for backfilling or
disposed offsite by haulage tippers to spoils tips.
6.3.3 For excavation of trench deeper than 1.5m, temporary shoring such as timbering shall be
provided if the existing ground not in good condition.
6.3.4 Prior to excavation, the Site Supervisor shall ensure that are no underground services are
in the way as to be damaged in the prior. Relocation of the affected services may be required to
facilitate the construction of the sewer line.
6.4 MANHOLE
) Foundation
5
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
6.4.1 The foundation shall be prepared as shown in the construction drawings and a joint
inspection with Consultant site staff shall carried out.
6.4.2 Dewatering by water pumps maybe required to enable dry surface for working.
6.4.3 When blinding layer is required, it should be placed immediately after the foundation
preparation has been completed to protect it from inclement weather.
6.4.4 Where the foundation specified is sand replacement the sand shall be replaced in layers
and compacted by approved compacting equipment.
b) New Manhole
6.4.1 The concrete ring installed base on the depth of the Manhole and the finish road level to
ensure the concrete ring high is acceptable.
6.4.2 The manhole cover used shall be approved by JPP/IWK.
6.4.3 All around the inside of manhole should be paint with alumina paint to replaced 20rnm
thick rendering in alumina cement and sand.
6.6 BACKFILLING
6.6.1 All this backfilling will use suitable material such as sand or hardcore and existing
excavated earth.
6.6.2 The backfilling will be compacted in layers of sand / hardcore and suitable excavated
earth.
6.6.3 Prior to backfilling, a visual inspection shall be carded out to ensure that the sewer line is
not have movement on the alignment and all unsuitable materials and debris are removed from
the backfill area.
6
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
The airside activities that will be carried out during the operation stage and the potential
environmental impact that may occur is summarized with mitigation measures in the following
table.
7
Document No : TBR-P-PM-MS-01
Revision No : 00
TERAS BUDI RESOURCES SDN BHD
Effective Date : ‘11/03/2024
ii. All site worker is compulsory to attend safety induction from the project authorities to ensure
that all worker is aware of site requirement.
iii. Use the proper tool for the job. Worker needs to avoid the first impulse to use whatever tool
(or object) is around you to get a work task done. Using the wrong tool for the job can result
in an injury or damage to the tool which can lead to an injury in the future.
iv. Always wear the proper PPE for the work task. All worker is obligated to ware complete
Personal Protective Equipment (PPE) such as safety helmet, coverall, safety shoes and etc.
v. Working areas must be secured by preventing unauthorized access by using barrier and
signs.
vi. All worker is to make sure chemicals are properly labelled and stored. Improper labelling and
storage can lead to injuries or property loss due to fires, corrosion, etc.
vii. All workers need to stay alert of any potential hazards such as dangerous substance and
confined spaces, so that measures can be developed to eliminate and minimize the risks.
viii. All the workers must ensure that the working area is cleaned and is in safe condition after the
work is completed.
3)
2)
3)