Method Statement
Rev. Date 06/02/2023 Document No. QAD-MS-SSS4 Version No. 1.0 Page 1 of 7
METHOD STATEMENT
PO 112799
This document is the property of BopCons. It is strictly confidential and may on no account be reproduced, copied, or divulged without prior
authorisation.
DOCUMENT MANAGEMENT SYSTEM (Site Specific)
Method Statement
Rev. Date 06/02/2023 Document No. QAD-MS-SSS4 Version No. 1.0 Page 2 of 7
Table of Contents
This document is the property of BopCons. It is strictly confidential and may on no account be reproduced, copied, or divulged without prior
authorisation.
DOCUMENT MANAGEMENT SYSTEM (Site Specific)
Method Statement
Rev. Date 06/02/2023 Document No. QAD-MS-SSS4 Version No. 1.0 Page 3 of 7
The purpose of this document is to describe the working procedure of laying asphalt in the
road reserve in Sasol Midlands site, at safe and acceptable standard. The area for
asphalting is near the Midlands Chlorine Plant, along Acetylene Road.
3. Resources
This document is the property of BopCons. It is strictly confidential and may on no account be reproduced, copied, or divulged without prior
authorisation.
DOCUMENT MANAGEMENT SYSTEM (Site Specific)
Method Statement
Rev. Date 06/02/2023 Document No. QAD-MS-SSS4 Version No. 1.0 Page 4 of 7
This document is the property of BopCons. It is strictly confidential and may on no account be reproduced, copied, or divulged without prior
authorisation.
DOCUMENT MANAGEMENT SYSTEM (Site Specific)
Method Statement
Rev. Date 06/02/2023 Document No. QAD-MS-SSS4 Version No. 1.0 Page 5 of 7
6. Sequence of Construction
Critical Responsible
Sequence of Activities
Step? Person
All members to be on-boarded, according to Sasol safety induction procedures, with
fingerprint vetting from the South Clock Permit Office.
All drivers and operators to be in possession of valid driver’s licenses and competency
certificates.
All members to be briefed about the scope of works, and to be well versed with the
Method Statement, SWP and PTRA. Site Agent
1 Y SHE Officer
Task Executer is responsible for completing and communicating the PTRA with the team.
Team Members
No work is to begin unless the PTRA is complete.
Ensure that the Base layer has been approved, and is free from any defects. Dips are to
QA Officer
2 be taken on the prepared layerworks to ensure that the top of base level is 40mm below Y
Team Members
the final road level. Base dip sheet is to be signed by the Client before starting work.
QA Officer
3 Perform surface preparation by removing any debris / dust accumulated, with brooms. Y
Team Members
This document is the property of BopCons. It is strictly confidential and may on no account be reproduced, copied, or divulged without prior
authorisation.
DOCUMENT MANAGEMENT SYSTEM (Site Specific)
Method Statement
Rev. Date 06/02/2023 Document No. QAD-MS-SSS4 Version No. 1.0 Page 6 of 7
Apply a light sprinkling of water to break the surface tension. Make use of water QA Officer
4 Y
sprayers, bottles, or a water bowser with nozzles. Take care not to over water the layer. Team Members
Apply the SS60 coating as per the required application rate dictated by the specification
5 Y Team Members
– Ensure that the entire area is covered sufficiently.
Perform a weather check before asphalting – check ambient temperature and weather
QA Officer
6 conditions. The asphalt temperature should be 120 degrees Celsius or above when Y
Team Members
placed on site.
Begin to place the asphalt at a typical spread rate of 1ton per 10m2. Ensure that enough
7 Y Team Members
material has been placed before compaction begins
Begin to compact the asphalt to its final shape, using a vibratory roller. Make use of
light water sprays to aid the cooling process to allow the asphalt to stiffen in place once QA Officer
8 Y
it is fully compacted. Compaction ceases when there is a flat uniform surface with no Team Members
loose stones or blemishes.
7. Safety Notes
This document is the property of BopCons. It is strictly confidential and may on no account be reproduced, copied, or divulged without prior
authorisation.
DOCUMENT MANAGEMENT SYSTEM (Site Specific)
Method Statement
Rev. Date 06/02/2023 Document No. QAD-MS-SSS4 Version No. 1.0 Page 7 of 7
8. Required Documentation
PTRA document
Method Statement
Quality Assurance Documents
Safety checklists
Excavation Permit
Tool/Equipment certificates
Training Competency Certificates
Toolbox Talks
9. Drawings
This document is the property of BopCons. It is strictly confidential and may on no account be reproduced, copied, or divulged without prior
authorisation.