project quality plan

DOCUMENT / MATERIAL /SAMPLE FOR APPROVAL


project AVANUE 3 trade
to (organization) SENIE ASSOCIATES AND BHD ☐ C&S
attention to Ir. Mohammad Faizul Bin Zainudin ☑ M&E
reference number ARSB-AVE3-WMS-0007 REV01 ☐ ARCH.
date 19/4/2023 ☐
copy to ☐ Client ☐ QS Consultant
☐ Architect ☐ Landscape Consultant
☐ C&S Consultant ☐ Site Office
☐ M&E Consultant ☐
description of Method Statement
material/sample
CABLE TRUNKING & CONDUIT INSTALLATION REV01

location to be used Housing

references
(spec. clause. etc.)

supplier
installer
attachment ☐ Manufacturer’s Drawings ☐ Method Statement
☐ Manufacturer’s Literature ☐ Product Certificate
☐ Sample / Brochure ☐ Performance / Technical Data
☐ Design Calculation ☐
signature name designation
submitted by
Muhammad Idham Bin Aziz M&E Engineer

APPROVAL RESPOND
recommendation by consulting engineers/architect approval by superintending officer
document/material/sample status : document/material/sample status :
☐ approved ☐ approved
☐ approved with comment ☐ approved with comment
☐ rejected ☐ rejected

comments comments

signature signature

name name
date date

Ref. No. : UH-MO-GTSD-QA-PQP-F5 Revision : 2 Effective Date : 1 September 2020 Page 1 of 1


CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2
TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2
ZON 13) LAKE VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM
CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK
TETUAN UDA LAND SDN BHD.

METHOD STATEMENT
FOR

CABLE TRUNKING & CONDUIT INSTALLATION


Reference ARSB-AVE3-WMS-0007
No. Revision 01
Date Issued 19/4/2023

Prepared by Reviewed by Approved by


Contractor, Consultant, Client/SO,

---------------------------------- --------------------------------- ---------------------------------


Name: Muhammad Idham Name: Name:
Bin Aziz Designation: Designation:
Designation: M&E Engineer Date: Date:
Date: 03/3/2023
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

Table of Contents
1.0 Scope of work.............................................................................................................................. 3
1.1 General Description ................................................................................................................ 3
1.2 References .............................................................................................................................. 3
1.3 Materials ................................................................................................................................. 3
1.4 Plant and Equipment............................................................................................................... 3
1.5 Manpower............................................................................................................................... 4
1.6 Standard .................................................................................................................................. 4
1.6.1 Cable Trunking ................................................................................................................ 4
1.6.2 20, 25 & Dia. uPVC Conduit............................................................................................. 4
1.7 Prepatory Work....................................................................................................................... 5
1.8 Construction Procedure .......................................................................................................... 5
1.8.1 Material Handling & Storage at Site ............................................................................... 5
1.8.2 Cable Trunking Installation Procedure ............................................................................ 5
1.8.3 Conduit Installation ......................................................................................................... 7
2.0 SAFETY AND HEALTH................................................................................................................... 7
2.1 Job Safety & Health Analysis ................................................................................................... 7
2.2 Information to personal .......................................................................................................... 7
2.3 Emergency Arrangements....................................................................................................... 8
2.4 Air Quality and Noise level ...................................................................................................... 8
2.5 Waste Management ............................................................................................................... 8
2.6 Housekeeping ......................................................................................................................... 8
3.0 Appendices .................................................................................................................................. 9
3.1 Construction Sequence ........................................................................................................... 9
3.2 Job Safety Analysis (JSA) ......................................................................................................... 9

Page | 2
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

1.0 Scope of work


1.1 General Description
The purpose of this procedure is to set out the cable trunking and electrical &
telephone services to facilitate installation on surface conduit construction in
accordance with the construction drawings, approved shop drawings, approved
materials, project specifications, codes, and standard design.

1.2 References
The relevant references are as follows:
No. Description Document Ref no.
Doc No: (1) JKR 20800-0226-20
1 Technical Specification
(2)MS IEC 364-5-52
SASB-1249 / AVENUE 3 / SP / 01
SASB-1249 / AVENUE 3 / E / LGD / 01
SASB-1249 / AVENUE 3 / E / LGD / 02
SASB-1249 / AVENUE 3 / E / ES / 01
SASB-1249 / AVENUE 3 / E / ES / 02
2 References Drawing
SASB-1249 / AVENUE 3 / E / ES / 03
SASB-1249 / AVENUE 3 / E / ES / 04
SASB-1249 / AVENUE 3 / E / ES / 05
SASB-1249 / AVENUE 3 / E / ES / 06
SASB-1249 / AVENUE 3 / E / ES / 07
3 HSE ARSB-AVE3-PSHP-0001

1.3 Materials
All relevant material shall be submitted and approved through the Material
submission approval.

1.4 Plant and Equipment


No. Plant and Machinery Quantity Purpose
1 Spanner For tightening or loosening
2 Hand Tools nuts, bolts
3 Hand Drill Make a hole
Cut the UPVC conduit to the
4 Cutter
required length and angle
5 Ladder

Page | 3
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

To reach high places and


6 Scaffolding
points safely

1.5 Manpower
All workers including local and non-local employed in the project site must attend the
CIDB Green card training and obtained the green card before commencing the work.
Foreign workers must also be ensured to have a valid work permit. The Safety and
Health Officer will inspect and ensure all the workers have valid CIDB green card and
valid work permit before commencing work.

No. Description Type of Brief Roles and Responsibilities


1 Construction Work M&E Engineer/ Planning, coordinating and
M&E Supervisor supervising construction activities
Land surveyor/ Setting out of works and checking
Chainman of completed works
Machinery and Operating the plants and
plant operator machineries
General Worker Carrying out general works at site
2 QAQC QAQC Engineer To inspect the item of works as
provided in the Inspection & Test
Plan
Lab Technician / To carry out sampling and testing
Workers of materials
3 Safety, Health and Safety Officer To implement and audit safety
Environment requirements at site, to enforce
safety rules and regulations at
work place
Security Guard To guard the materials, plant and
machinery at site

1.6 Standard
The following Standard and Codes of Practice is referred to in prepared of this
method statement.

1.6.1 Cable Trunking

BS EN 1461 : 1999(E)

1.6.2 20, 25 & Dia. uPVC Conduit

BS EN 50086-2-1 : 1996 Conduit Classification Code

Page | 4
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

1.7 Prepatory Work


i. Prior to work started, supervisor shall check the approved electrical shop
drawing, C&S drawing & Architect drawing, setting out, level andset up
alignment.

ii. Check cable trunking sizes and brand as per approved material.

iii. Coordinate with builder for the other utilities services and determine
thetrunking route.

iv. Check conduit sizes and brand as per approved material.

v. Coordinate with builder for the other utilities services and determine the
conduit route.

vi. Should there be any crossing of others utilities services, confirmation of


level shall be obtained before proceeding with actual works at site.

1.8 Construction Procedure


1.8.1 Material Handling & Storage at Site
i. Handling: All materials required are easily handle and loaded.The material
shall be handling with care to avoid any damage before and during
installation.

ii. Storage: The cable trunking and pipe materials will be stored and placed
properly.

1.8.2 Cable Trunking Installation Procedure


i. The size of cable trunking shall be according to required space of the sub-
main cables being laid in the cable trunking.

ii. The trunking is either mounted directly onto the slab/wall or supported on
mild steel angle brackets suspended from soffits or mounted directly onto
the slab or wall.

iii. The finishing of the soffit of slab shall be painting, plastering, etc. prior to
installation.

iv. The edge of the metal trunking shall be made smooth by sandpaper etc. to
ensure that cables are not damage during installation.

Page | 5
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

v. Upon confirmation the layout of the trunking routes, use a line marker to
mark out the intended routes.

vi. If the trunking is mounted directly onto the slab, the base of the trunking is
secured by post drilled wedge anchors into the concrete soffits of slabs and
beams or wall.

vii. The metal trunking shall be supported at an interval about 2 meter


maximum. The installation of trunking shall be straight and level.

viii. Avoid soffit areas where the tendons of the slab are pre-cast concrete slab.
This is to prevent damage to the slab when the drop-ins are inserted.

ix. Using an electric drill, drill the soffit where the intended points for the drop-
in are located. These drop in are to be used to support the threaded rods.

x. The supporting bracket for the trunking, threaded rod and drop-in anchor
shall be installed and fastened firming on to the slab as described in the
installation of the cable ladders and trays.

xi. Prepare the angle bar/flat bar brackets to size and insert the bracket with
the holes pre-drilled into the treaded rods. Tighten the brackets at desired
height as per co-ordination with nuts.

xii. Install the correct size of trunking and lay the trunking on the supporting
brackets. “Earth continuity link” by using cooper link is installed between
two connections of trunking.

xiii. All the bends of the cable trunking are cut and fabricated not exceeding an
angle of 90 degrees. In the case of a trunking need to be bended at an angle
of 90 degrees, two numbers of 45 degrees bend are to be cut and
fabricated.

xiv. Pieces of woods or etc. are put across the internal wall of the trunking after
cables have been installed. If the trunking cover were opened for
inspection, troubleshooting and etc., the cable in the trunking will not fall
out.

xv. Finally touch up with paint to match the existing colour wherever necessary.

Page | 6
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

1.8.3 Conduit Installation Procedure

i. The conduit sizes used for the above installation work are either
20mm, 25mm or in diameter to meet the sectional area of wiring
laid.

ii. The conduit shall be laid either parallel or perpendicular to the


building line according to the shop drawing approved by consulting
engineer.

iii. The edge and internal surface of the conduit is to be reasonable


smooth to ensure that the cables are not damaged while pulling
during the installation.

iv. The conduit installed concealed in slab, column and shear wall or
brick wall area.

v. The surface boxes shall be firmly fixed to the construction material.

2.0 SAFETY AND HEALTH


2.1 Job Safety & Health Analysis
Job Safety & Health Analysis shall be carried out on the project site. Barriers and safety
awareness signs shall be established at location of works. The potential hazards in a
particular activity and the control measures implemented shall be briefed to the
workers during safety induction, tool box talk and JSA Briefing. Road works shall be
commenced in accordance to the requirements spelt in Project Safety Health Plan
(PSHP).

2.2 Information to personal


All workers employed in the project site must have valid document. The safety
personnel will inspect and ensure all the workers have valid document before
commencing work.

All the control measures detailed in the job safety & health analysis will be
disseminated to site personnel through:

Page | 7
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

- Safety Induction Briefing


- Tool Box Briefing
- Notice Board
- Safety & Health Meeting
- Permit to Work etc.

All the attendance records and briefing materials will be maintained and properly
recorded.

The supervisors will be trained based on the approved work method statement which
is including the safety and health, as well as the environmental and quality
requirements. Subsequently, the supervisors will brief the information to the site
workers prior the commencement of work at site.

2.3 Emergency Arrangements


The emergency situations which may occur are shown in the appendix 3.2 for jobs
safety analysis.

2.4 Air Quality and Noise level


All construction machineries shall be in well maintain and in good working condition
to reduce emission of soot, smoke and noise.

The following measures shall be implemented if the above mentioned (soot, smoke
and noise) is deteriorating:

- Increase maintenance frequency


- Replace to better equipment if necessary.
- Switched-off equipment if not in used.
- Supply workers on-site with proper PPE (i.e. ear plugs and mask).

Water jet shall constantly spray the water to minimize the dust especially during hot
weather if any transport operation going on.

2.5 Waste Management


Scheduled waste from maintenance works of machineries, vehicles and tools shall be
placed in designated areas at the site. Proper oil trays shall be placed for oil petroleum
product to prevent oil spillage at ground. Scheduled waste shall be collected and
transferred to scheduled waste storage area. The scheduled waste shall be disposed
by license contractor registered with DOE to approved dump site. Scheduled waste
storage and disposal shall follow EQ (Scheduled Waste) Regulation 2005 accordingly.

2.6 Housekeeping
Housekeeping is an essential part of safety for the daily routine. Housekeeping would
include the following items:

- Maintain the access/egress to all working area.

Page | 8
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

- Store and stack all construction materials in safe and orderly manner
- No littering around the site and provide sufficient waste bin.

3.0 Appendices
3.1 Construction Sequence
3.2 Job Safety Analysis (JSA)

Page | 9
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

Appendix 3.1

Construction Sequence

CABLE TRUNKING & CONDUIT INSTALLATION

Page | 10
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

Figure 1 Flow chart for electrical cabling services

Page | 11
Method Statement for Cable Trunking & Conduit Installation
Document No. ARSB-AVE3-WMS-0007

Revision No. 01 Revision Date 19/4/2023

Appendix 3.2

Job Safety Analysis (JSA)

CABLE TRUNKING INSTALLATION

Page | 12
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

PREPARED BY REVIEWED BY APPROVED BY


DESCRIPTION
(Project Department) (Project HSE Section) (Project Manager / Client Rep)

Signature

Name MUHAMMAD IDHAM BIN AZIZ SHAZWANI BINTI AB WAHID MUHAMAD AZI BIN AB RAHMAN
Designation PROJECT ENGINEER SAFETY HEALTH OFFICER PROJECT MANAGER
Date 2/3/2023 2/3/2023 2/3/2023

LIKELIHOOD (L) EXAMPLE RATING SEVERITY (S) EXAMPLE RATING


Numerous fatalities, irrecoverable property damage (Rm 100,000.00) and
MOST LIKELY The most likely result of the hazard / event being realized 5 CATASTROPHIC 5
productivity
POSSIBLE Has a good chance of occurring and is not unusual 4 FATAL Approximately one single fatality or major property damage if hazard is realized 4

CONCEIVABLE Might be occur at some time in future 3 SERIOUS Non-fatal injury, permanent disability 3

REMOTE Has not been known to occur after many years 2 MINOR Disabling but not permanent injury 2

INCONCEIVABLE Is practically impossible and has never occurred 1 NEGLIGIBLE Minor abrasions, bruises, cuts, first aid type injury 1

RISK EVALUATION (LIKELIOOD X SEVERITY)


LOW
No need action required
1-14
MEDIUM
Action is necessary
5-12
HIGH
Action needed to reduce risk
15-25
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

PIC
NO WORK ACTIVITY HAZARD WHICH CAN CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)

Provide signalman / banksman to control


machinery movement for congested
area.
Safety helmet,
Ensure all machinery has beacon light, Safety vest,
reverse / swing alarm. Safety Shoe, PM/Engineer/
Struck by moving site
Moving machinery 1 3 3 Relevant certificate for operator. Specific PPE to Site supervisor/
machinery perform task Operator
Segregate access between workers / e.g.: Earplug,
machinery. face shield
Machinery side & rear mirror in order.
Wearing orange reflective vest.
All material needs to secure with proper Safety helmet,
1 Mobilization of equipment lashing. Safety vest,
Transportation supervisor / operator Safety Shoe, PM/Engineer/
Improper lashing Load fall during transportation 1 3 3 needs to check & ensure load secure Specific PPE to Site supervisor/
before start transportation. perform task Operator
e.g.: Earplug,
face shield
All access must clear from any
obstruction.
Provide flag / banksman to control Safety helmet,
machinery movement for congested Safety vest,
area. Safety Shoe, PM/Engineer/
Limited access Hit another property 1 3 3 For congested area needs to avoid Specific PPE to Site supervisor/
delivery during peak hour. perform task Operator
e.g.: Earplug,
Reverse exit is not allowed for all
face shield
machinery
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

PIC
NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)

Wash trough needs to construct prior


start site clearing. Safety helmet,
Soil brought into Safety vest,
Spray water at dry area.
public road Road dirty / Dust Safety Shoe, PM/Engineer/
Provide water browser to carry out
1 3 3 dewatering. (if required). Specific PPE to Site supervisor/
perform task Operator
Provide power broom to maintain e.g.: Earplug,
cleanliness (if required). face shield
Mobilization of equipment
(cont’)
Logistic supervisor needs to inspect the
route and make sure the clearance of Safety helmet,
overhead cable Safety vest,
All the overhead lines must be identified Safety Shoe, PM/Engineer/
Striking overhead prior start mobilization and briefly explain
Electrocution 1 3 3 Specific PPE to Site supervisor/
cable to the driver. perform task Operator
Install goal post with height limit sign to e.g.: Earplug,
protect overhead cable (if required) face shield

Briefing correct method to carry out Safety helmet,


manual handling. Safety vest,
Buddy system to minimize repetitive Safety Shoe, PM/Engineer/
Loading & unloading of Improper manual Ergonomics injury / Back pain
2 1 2 2 work / heavy manual lifting. Specific PPE to Site supervisor/
equipment & materials handling
Wheel barrow shall be use on suitable perform task Operator
surface condition. e.g.: Earplug,
face shield
PIC
NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

Wear suitable safety shoes with proper


tread.
Conduct housekeeping & material Safety helmet,
arrangement. Safety vest,
Scattered Material / Supervisor must ensure access to work Safety Shoe, PM/Engineer/
Uneven ground / Slip, trip & fall 2 2 4 area clear & no obstruction. Specific PPE to Site supervisor/
limited access Strut installation must be in sequence to perform task Operator
the access / egress point e.g.: Earplug,
Identify, mark or barricade any face shield
obstruction.

Loading & unloading of In any condition out rigger must


equipment & materials fully/properly extend before operate.
(cont) Make good / compact all soft ground
area before park & MP Test
Safety helmet,
Operator / lifting supervisor need to
Safety vest,
inspect ground condition at working area
Improper parking of Safety Shoe, PM/Engineer/
prior start work.
crane / not solid Crane collapse 1 3 3 Specific PPE to Site supervisor/
Crane spirit level for parking must
ground foundation perform task Operator
function.
e.g.: Earplug,
Valid PMA & DOSH certificate and valid
face shield
JPJ driving license for operator.
Lifting Plan shall be made available prior
start work. (Critical lifting/heavy lifting)

PIC
NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)

In any condition out rigger must Safety helmet,


fully/properly extend before operate. Safety vest,
Loading & unloading of Make good / compact all soft ground Safety Shoe, PM/Engineer/
Improper lifting using
equipment & materials Crane topples 1 3 3 area before park & MP Test Specific PPE to Site supervisor/
crane
(cont) Operator / lifting supervisor need to perform task Operator
inspect ground condition at working area e.g.: Earplug,
prior start work. face shield
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

Crane spirit level for parking must


function.
Valid PMA & DOSH certificate and valid
JPJ driving license for operator.
Lifting Plan shall be made available prior
start work. (Critical lifting/heavy lifting)

All lifting gear must be inspected prior


start work.
Make sure lifting gear capable to take Safety helmet,
load & used the right lifting gear. Safety vest,
Improper lifting Lifting supervisor to supervise lifting Safety Shoe, PM/Engineer/
method / not Loss load / lifting fail 1 4 4 activity. Specific PPE to Site supervisor/
approved lifting gear Lifting supervisor to brief lifting activities perform task Operator
to lifting team e.g.: Earplug,
Lifting Plan shall be made available prior face shield
start work. (Critical lifting/heavy lifting)

PIC
NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)

Safety helmet,
Apply buddy system Conduct toolbox & Safety vest,
emphasize regarding this hazard to Safety Shoe, PM/Engineer/
Improper manual
Ergonomics injury / Back pain 1 2 2 workers involved Specific PPE to Site supervisor/
handling
Used trolley if heavy load and surface perform task Operator
condition suitable. e.g.: Earplug,
Loading & unloading of face shield
equipment & materials
(cont) Safety helmet,
Wear proper PPE, safety Helmet, Shoe,
Safety vest,
vest & gloves.
Safety Shoe, PM/Engineer/
Cover all sharp object where applicable.
Sharp object Hand/Bodily injury 1 3 3 Specific PPE to Site supervisor/
Smooth by sandpaper.
perform task Operator
Conduct toolbox & emphasize regarding
e.g.: Earplug,
this hazard to workers involved.
face shield
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

Wear full body harness if movement job


at height.
Provide proper access, walking platform
and rigid barrier / edge protection. Safety helmet,
Conduct toolbox & emphasize regarding Safety vest,
this hazard to workers involved. Safety Shoe, PM/Engineer/
Conduit / Trunking / Cable Improper working at
3. Falling from height 1 3 3 Provide hook point / life line for hook the Specific PPE to Site supervisor/
Tray Installation height
safety harness. Ensure harness hook at perform task Operator
rigid hook point e.g.: Earplug,
Ensure mobile scaffold tyre lock all the face shield
times.
No personnel are to be on the mobile
scaffold while being relocate.
PIC
NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)

Safety helmet,
Inspected & tagged by competent Safety vest,
scaffolder Safety Shoe, PM/Engineer/
Conduit / Trunking / Cable Improper scaffold Collapse of the scaffold & fall of
1 3 3 Need to inspect ground condition at Specific PPE to Site supervisor/
Tray Installation (cont) installation person
working area prior start work. perform task Operator
e.g.: Earplug,
face shield
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

Safety helmet,
Conduct toolbox & emphasize regarding
Safety vest,
this hazard to workers involved
Safety Shoe, PM/Engineer/
Work with buddy system if carry material
Awkward posture Backpain 1 3 3 Specific PPE to Site supervisor/
over than 15kg
perform task Operator
Correct posture of lifting
e.g.: Earplug,
Rotation of work
face shield
Wear suitable safety shoes with proper
Safety helmet,
tread.
Safety vest,
Conduct housekeeping & material
Safety Shoe, PM/Engineer/
Scattered Material / arrangement.
Slip, trip & fall 2 2 4 Specific PPE to Site supervisor/
Uneven ground Supervisor must ensure access to work
perform task Operator
area clear & no obstruction.
e.g.: Earplug,
Identify, mark or barricade any
face shield
obstruction.
Safety helmet,
Install netting / toe board at edge to
Safety vest,
avoid object from falling
Safety Shoe, PM/Engineer/
Wear proper safety helmet for head
Falling Object Head / Bodily Injury 1 3 3 Specific PPE to Site supervisor/
protection
perform task Operator
Conduct toolbox & emphasize regarding
e.g.: Earplug,
this hazard to workers involved.
face shield
PIC
NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)

Safety helmet,
Power tools to be inspect prior start work Safety vest,
Wear safety goggles / face shields, and Safety Shoe, PM/Engineer/
Conduit / Trunking / Cable
Unfit power tools Eye injury / Bodily injury 1 3 3 all provided PPE. Specific PPE to Site supervisor/
Tray Installation (cont)
Conduct pre task talk prior start work & perform task Operator
emphasize regarding this hazard. e.g.: Earplug,
face shield
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

All electrical tool needs to send for pre- Safety helmet,


inspection prior bring into workplace Safety vest,
All extension wire needs to properly Safety Shoe, PM/Engineer/
Electrical Electrocuted 1 3 3 hang up, not allowed to lay on the Specific PPE to Site supervisor/
ground perform task Operator
All electrical tools need to be sent for e.g.: Earplug,
inspection as required face shield
Safety helmet,
Brief and show this potential hazard at
Safety vest,
machinery to all involved workers
Safety Shoe, PM/Engineer/
Caught in between or Wear proper PPE during working (glove,
Finger injuries Specific PPE to Site supervisor/
pinch point shoe, helmet)
perform task Operator
Placing sign or stickers at the potential
e.g.: Earplug,
hazard area (if applicable)
face shield
Wear proper PPE, safety Helmet, Shoe, Safety helmet,
vest, gloves, safety glass Safety vest,
Flying particle when Conduct toolbox & emphasize regarding Safety Shoe, PM/Engineer/
using grinder / high Eye injury 1 3 3 this hazard to workers involved Specific PPE to Site supervisor/
speed cutter / driller Power tool pre-entry inspection prior perform task Operator
bring into workplace e.g.: Earplug,
face shield

NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED PIC

Provide rest area / shelter.


Safety helmet,
Advise worker to drink sufficient water.
Safety vest,
Brief to workers regarding heat stress /
Safety Shoe, PM/Engineer/
dehydration how to recognize the
5 General Hot weather Heat stress / dehydration 1 3 3 Specific PPE to Site supervisor/
symptom.
perform task Operator
Advise worker to wear light clothing and
e.g.: Earplug,
ensure frequent work rotation.
face shield
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

Safety helmet,
Safety vest,
Conduct toolbox talk & emphasize Safety Shoe,
Specific PPE to PM/Engineer/
Lightning strike can cause regarding this hazard to all worker.
Bad Weather 1 4 4 perform task Site supervisor/
whole body burnt or fatality All outdoor & external work shall be stop
e.g.: Earplug, Operator
during thunderstorms & heavy rain.
face shield

Buddy system to minimize repetitive Safety helmet,


work / heavy manual lifting. Safety vest,
Conduct exercise / stretching prior start Safety Shoe, PM/Engineer/
Improper manual
Ergonomics injury / Back pain 1 2 2 work. Specific PPE to Site supervisor/
handling
Wheel barrow shall be use on suitable perform task Operator
surface condition. e.g.: Earplug,
face shield

PIC
NO WORK ACTIVITY HAZARD ZARD CAUSE/EFFECT LIKELIHOOD SEVERITY RISK RATING RECOMMEND CONTROLS MEASURES PPE REQUIRED (DUE DATE /
STATUS)

Wear suitable safety shoes with proper


Safety helmet,
tread.
Safety vest,
Conduct housekeeping & material
Safety Shoe, PM/Engineer/
Scattered Material / arrangement.
Slip, trip & fall 2 2 4 Specific PPE to Site supervisor/
Uneven ground Supervisor must ensure access to work
perform task Operator
area clear & no obstruction.
e.g.: Earplug,
Identify, mark or barricade any
face shield
General (cont’) obstruction.

All night work activity must get approval


Safety helmet,
permit from local authority & client.
Nightwork Safety vest, PM/Engineer/
Standby backup lighting in case of power
Poor Visibility 2 3 6 Safety Shoe, Site supervisor/
/ existing tower light failure
Specific PPE to Operator
Workers must have enough rest and
perform task
physically fit to conduct night work
AS-SYAFF RESOURCES SDN BHD
Doc No. : HSE-AVE3-F025
Rev : 00
HAZARD IDENTIFICATION RISK ASSESSMENT RISK CONTROL (HIRARC)
CADANGAN MEMBINA DAN MENYIAPKAN 79 UNIT RUMAH TERES 2 TINGKAT DAN 1 UNIT PENCAWANG ELEKTRIK DI AVENUE 3 (FASA 2 ZON 13) LAKE
PROJECT TITLE
VALLEY, BANDAR TUN HUSSEIN ONN, MUKIM CHERAS, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN UNTUK TETUAN UDA LAND SDN BHD.
Task/ Job
Description
INSTALLATION OF CABLE TRUNKING HIRARC No JSA 0007 Date 6/3/2023

e.g.: Earplug,
face shield

All area needs to receive background &


task lighting from 2 directions.
Safety helmet,
Provide lighting for access & work area
Safety vest,
All machinery needs to equip with
Safety Shoe, PM/Engineer/
warning light and all lamps in orders.
Poor Visibility 2 3 6 Specific PPE to Site supervisor/
Provide high visibility vest with reflective.
perform task Operator
Minimum lighting provides 50 lux for
e.g.: Earplug,
access & 100 lux for all working area,
face shield
dangerous opening & lifting or lowering
activity.