Professional Documents
Culture Documents
INTRODUCTION:
The purpose of this document is to provide a detailed guide for the Short circuit Calculation and Protection
Relay setting coordination study to achieve safe operation of the SUPER CEMENT 11/0.400kV substation in
coordination with the upstream ADDC substation’s protection relay settings.
O/C and E/F relay setting of incomers are calculated considering that incoming feeder fault current.
O/C and E/F relay setting of Transformers Feeders are calculated considering that transformer full load and
fault current.
OBJECTIVE:
The objective of this study is to provide a protective relay coordination study report for SUPER CEMENT
11/0.400kV substation- fed from ADDC substation
> The Protective relay settings are calculated based on the short circuit currents. The relays are set to operate
such as to isolate the fault circuit from the electrical distribution system.
> The Fault current, CT ratio and relay settings at the feeding end substation are received from M/s.ADDC - T&P
Department
> Protective relays details of the respective feeders are taken from the single line diagram (approved by
ADDC) / vendor drawing documents
> Single phase and three phase fault currents are calculated through the entire network up to the transformers
end. The respective fault current in each feeder are taken for the calculation.
> Over curent and earth fault protection tripping timing of all 11kV I/C and O/G feeders are coordinated with
the Upstream Primary substation.
Following assumptions are made while calculating the relay setting study.
> Upstream substation feeders feeds to SUPER CEMENT 11/0.400kV substation incomer feeder 1 & incomer-2
in loop with the other S/S and all the incoming & outgoing feeders are co-ordinated with the upstream feeders.
> The parameters mentioned in the relay setting schedule are based on the relay manufacturer's manual.
> Ensured from the operating time that any fault in down stream, first down stream feeders will trip. If down
stream breakerfails to trip then immediate nearest upstream breaker will trip, if that also fails to trip, then only
the upstream feeder will trip.
SUPER CEMENT (ICA0101)
SUPER CEMENT 11/0.4kV S/S PROTECTION
CO-ORDINATION STUDY
Electromechanical Co LLC Agents
for SIEMENS
> IEC curves have been considered for relay setting and cordination. The operating time of the relays using IEC
curves calculated by using the following formulas.
Where,
t = Tripping time
I = Fault current
Is = Inverse time over current pickup
TMS = Time multiplier setting
I/Is = Plug setting multiplier-PMS
> The selection of the type of curve ( SI, VI or EI ) is based on the best available option for propper coordination.
So Standard Inverse method is selected for the Protection Relay setting Coordination
PHILOSOPHY:
Over current and earth fault protections at distribution substation are coordinated with the upstream ADDC
substation feeder relays.
Fault in any one of the down stream substation, in case 11kV Transformer feeder breaker fails to operate then
the respective Substation's 11kV incomers will operate with the time grading.
In case 11kV incomers circuit breaker fail to operate, then next immediate nearest upstream breaker will
operate with time grading. In worst case all the downstream breakes fails to operate then only the Upstream
ADDC 11kV Substation feeder breakers will operate with the time grading
REFERENCE DOCUMENTS
> Siemens Publication: Protection and substation control system and individual protection relay manuals
Softwares Used:
INPUT DATA:
PROTECTION DATA
CT Ratio = 400/1 A
Plug setting - Ip = 0
Operating Time -t = 0
Plug setting - Ip = 0
Operating Time - te = 0
Note: Above fault levels & settings are received from ADDC T&P section - Previous Relay Setting
Co-Ordination Study
SUPER CEMENT (ICA0101)
SUPER CEMENT 11/0.4kV S/S PROTECTION
CO-ORDINATION STUDY
Electromechanical Co LLC Agents
for SIEMENS
11kV RING INCOMER - 1 & 2 (=K01 & =K06) (Super Cement S/S-ICA0101)
Over current operating time 350msec is selected by coordinating with the up stream outgoing breakers O/C
operating time 500msec
= 0.154
Time multiplier setting (TMS) ≈ 0.15 Sec
Earth Fault operating time 350msec is selected by coordinating with the up stream outgoing breakers E/F
operating time 500msec
= 0.154
Time multiplier setting (TMS) ≈ 0.15 Sec
Over current operating time 225msec is selected by coordinating with the incomer breakers O/C operating
time 350msec and to cordinate with the LV-SBEF - 300msec
= 0.097
Time multiplier setting (TMS) ≈ 0.10 Sec
Earth Fault operating time 225msec is selected by coordinating with the incomer breakers E/F operating time
350msec
= 0.099
Time multiplier setting (TMS) ≈ 0.10 Sec
Opperating
Over Current Earth Fault
(IDMT) setting (IDMT) setting Max.Fault Time (t) at High Set (OC) High Set (E/F)
Primary Current (KA) Max.Fault (50) (50N) ALARM /
S.No Description CT Ratio (A) Relay Curve (51) (51N) Current TRIP
Type Type Current(Sec)
(A) Status
PMS PMS
TMS (t) TMS (te) O/C E/F O/C E/F I>> (A) t>> (S) Ie>> (A) te>> (S)
(Ip) (A) (Iep) (A)
11kV RING :
1 Up stream ADDC - Feeder-1 400/1 7SJ62 NI 1.1 0.22 0.2 0.22 400 16 19.18 0.500 0.500 16 0 12 0 TRIP
2 Up stream ADDC - Feeder-2 400/1 7SJ62 NI 1.1 0.22 0.2 0.22 400 16 19.18 0.500 0.500 16 0 12 0 TRIP
SUPER CEMENT-S/S :
Incomer-1 & 2
3 600-300/1 7SJ602 NI 0.5 0.15 0.1 0.15 600 10.50 7.64 0.350 0.350 8 0 5 0 TRIP
1500kVA TRANSFORMER-1&2
4 (Typical) 150/1 7SJ602 NI 0.53 0.1 0.2 0.1 150 10.12 7.15 0.225 0.225 8 0 3 0 TRIP
Relay
Description CT Ratio (A) Type Parameters Setting Range Setting
Breaker Recommended
SI No. Feeder/ Breaker Trip Unit Protection Remarks
Rating Settings
4P, 2500A Over Load Current IR: 1 x In
1 LV Incomer (Typical) ABB-SACE P121
ACB (L-Tripping) Time TR: 12Sec
PROJECT
SUPER CEMENT
11/0.4kV SUBSTATION UPGRADATION
(ICA0101)
PREPARED BY
ELECTRO MECHANICAL CO.LLC
Agents for SIEMENS
P.O.Box 732
Abu Dhabi, UAE.
Tel: 02-6262800 / 02-6272164
Fax: 02-6269871
Email:elmec1@elmec.ae
Visit us at:www.elmech.co.ae
Fax: 02-6269871
Email:elmec1@elmec.ae
Visit us at:www.elmech.co.ae
INTRODUCTION 1
SHORT CIRCUIT CALCULATION
&
RELAY SETTING CO-ORDINATION STUDY
INPUT DATA 2
RELAY SETTING
CALCULATION 4
ELECTRO MECHANICAL
CO.LLC
Agents for SIEMENS
P.O.Box 732
REFERENCE
Abu Dhabi, UAE.
7
Tel: 02-6262800 / 02-6272164 DOCUMENTS
Fax: 02-6269871
Email:elmec1@elmec.ae
Visit us at:www.elmech.co.ae
ELECTRO MECHANICAL
CO.LLC
Agents for SIEMENS
P.O.Box 732
Abu Dhabi, UAE. REFERENCE 7
Tel: 02-6262800 / 02-6272164 DOCUMENTS
Fax: 02-6269871
Email:elmec1@elmec.ae
Visit us at:www.elmech.co.ae