POWER CORPORATION Date: August 03, 2022 Technical Operations I. Meter Readers (7:00am -5:00pm) Work Description Location Remarks Meter Reading Manalupang, Sinala 201 completed Statement of Account Sinala 202, Magalang-galang, San Pedro, Sampaguita completed (SOA Deliveries)
II. Line Crew (8:00am - 5:00pm) Crew A & C (5 manpower and 2 Work Description Work Order No. Location Remarks casual) Work Order: Interconnection of Substation 1 and Substation 2 (section 1 - Balayong-Manghinao on-going from Balayong to Manghinao Bridge) for Proper Feeder 2 1. Installation of overhead guying for two
(2) 55 ft. steel poles. 2. Cable pulling of new span 3 wire #4/0
PACSR primary lines. Crew B Work Description Work Order No. Location Remarks (3 manpower) Clearing branches if trees close and Bagong Silang and completed overlap on primary and secondary line. Magalang-galang Crew D (2 manpower) Dispatch Customers Name Location Remarks 1. Temporary Connection Baylon, Abel M. San Andres Proper completed 2. New Connection Robles, Mila Rose San Andres Proper completed Ferdinand Joseph C. Blk 3 Lot 19 Boomtown, 3. Permanent Connection Dimaapi Manghinao Proper completed 4. Transfer Meter Marcelino M. Gonzalvo Manalupang completed Blk 21 Lot 1 Boomtown, 5. Permanent Connection Sherly Mandigma Manghinao Proper completed Blk 21 Lot 1 Boomtown, 6. Disconnection Sherly Mandigma Manghinao Proper completed Delos Reyes, Antonina - 7. Others Alba, Jeffrey Delos Reyes San Roque - Route 5 completed Trouble Customers Name Location Remarks 1. No power due to loose connection of service drop wire / Respliced and retapped Leonila Montalbo San Andres 1 completed of service drop wire. Routinary Activity: Inspection of substation and recording of Substation (Taño Rd,
operational data . Manghinao Proper)
Regular OT - 3 manpower Routinary Activity: (5pm - 10pm) Inspection of substation and recording of Substation (Taño Rd,
operational data . Manghinao Proper) Crew D (2 manpower) Routinary Activity: 10:00pm - 8:00am Inspection of substation and recording of Substation (Taño Rd,
operational data . Manghinao Proper)
TOTAL NO. OF REPLACED KWH METER:
Today To Date 0 17,725 TOTAL CUSTOMER TO DATE: New Connection A. Residential B. Commercial Total Today To Date Today To Date 2 8,885 0 1,289 9,872 Total Consumer 23,907 Total Consumer 2,263 25,872