TECHNICAL PROPOSAL

REHABILITATION OF WATERPROOFING OF NAGA STUDIO &


OFFICES

 SCOPE OF WORKS
 BILL OF QUANTITY
 METHODOLOGY
 HEALTH AND SAFETY PROCEDURE
 SPECIFICATION/EQUIPMENT
 WARRANTY
 CONSTRUCTION LEAD TIME

PROJECT : Rehabilitation of Waterproofing of Naga Studio & Offices


LOCATION : Concepcion Pequena, Naga City
DATE : February 22, 2021

GMA NAGA WATERPROOFING REHABILITATION


Concepcion Pequena, Naga City
SCOPE OF WORKS:

 Mobilization/Demobilization
 Temporary Facilities
 Waterproofing Works
o Surface Preparation
o Grinding of Rough Surfaces
o Chipping of Reglet Terminations
o Supply and Application of Bitumen Membrane
o Application of Bitumen sealant at terminations
 Cleaning and Restoration of affected areas

BILL OF QUANTITY

ITE      
M DESCRIPTION UNIT QTY
NO      
I   General Requirements        
Mobilization /
    1   lot   1
Demobilization
    2 Temporary Facilities   lot   1
Temporary Power (tapping
    3   lot   1
at existing source)
    4 Delivey of Materials, tools   lot   1
GMA NAGA WATERPROOFING REHABILITATION
Concepcion Pequena, Naga City
and equipment to site
        Sub Total        
                   
II   WATERPROOFING WORKS        
    1 Surface Preparation   sq.m.   368.2
    2 Grinding of rough surfaces   sq.m.   368.2
Chipping of reglet
    3   sq.m.   185
terminations
Supply and application of
    4   sq.m.   368.2
Bitumen Membrane
Application of Bitumen
    5   sq.m.   185
sealant at terminations
      Sub Total        
                   
III   Cleaning and restoration of affected areas   lot   1

METHODOLOGY FOR EXECUTION OF WORKS

 Personnel working on site will be complete of Personal Protective Equipment prior to


start of construction

 All approach will be as per plan. Designs will duly follow by the construction team.
 Surface up for waterproofing will be properly prepare and cleared.
 Rough surfaces will be well grinded
 Reglet Terminations will be up for chipping
 Bitumen Membrane Will be well applied
 Surface applied will be flood tested to ensure no leak will arise

HEALTH AND SAFETY PROCEDURE

PURPOSE
This procedure is designed to provide instructions and to assign responsibilities for
safety control.

GMA NAGA WATERPROOFING REHABILITATION


Concepcion Pequena, Naga City
SAFETY POLICY
a.) Safety precedes all activities.
b.) It shall be a duty for each person to create the safety environment.

 All personnel are required to wear face mask at all times


 Site supervisor will be strict for health monitoring of all workers
 Foot bath and alcohol will be on site for disfection
 Daily health monitoring sheet/log will be provided
 Personnels are limited only to stay on site to prevent interactions on other person
outside.

RESPONSIBILITIES AND AUTHORITY

Project Engineer shall take responsibilities for the safety of all activities and promote
the safety consciousness among all workers at every stage of the work. Specifically he shall
adjust and coordinate construction work in the safest manner based on the detailed work
schedule.

SAFE WORKING PRACTICES


All workers shall wear the following equipment whenever they are on the site
a.) Hard hat

b.) Hand gloves for jobs which have potential for hand injuries, burns, chemical
infections,etc.

c.) Safety belts at heights of over 2.0m above the ground level where properly
constructed working platforms are neither available nor practical.

d.) Welding shield while doing welding works, anti glare eye protection (safety
goggles while doing gas cutting or any similar activities.
e.) All workers are required to wear face mask and face shield

TOOLS AND EQUIPMENT

a.)The following three basic principles shall be applied to and govern the safe use of hand and
powertools, and which principles are :

1. To use the correct tool for the job in the correct way.
2. To use only tools in good conditions
3. To maintain and store tools properly after use.

LIST OF TOOLS AND EQUIPMENT:

 Personal Protective  Waterproofing


Equipments Compounds
 Grinder

GMA NAGA WATERPROOFING REHABILITATION


Concepcion Pequena, Naga City
 Drill  Safety Gloves
 Chipping Gun  Application Tools
 Bitumen Membrane
Waterproofing

WARRANTY
- 1 year after work completion

CONSTRUCTION LEAD TIME

- 30 Calendar days upon receipt of Purchase Order


Prepared By:

CIVIL ENGINEER

GMA NAGA WATERPROOFING REHABILITATION


Concepcion Pequena, Naga City