Professional Documents
Culture Documents
Total Project Cost: PHP 18,645,000 Project Duration: 180 CALENDAR DAYS
Note:
1. Additional line items may be added in Annex H given that the purpose and use of the added items is clearly discussed in the construction
methodology subject for evaluation and assessment.
2. Items indicated in herein may be replaced with other items given that the purpose or intention for the replaced items shall be served and is
clearly discussed in the construction methodology subject for evaluation and assessment. All modifications in a way of deletion and reduction
in sub-item and quantities shall be equivalent in cost of the replaced items.
3. Several items indicated in “Annex H” are the required minimum quantities in Detailed Cost Estimate. Quoting above the respective minimum
quantities per item is allowed. However, quoting below the respective required minimum quantities per item shall be grounds for
disqualification.
4. All other items in “Annex H” under sections that are not enumerated above shall have the required minimum quantities. Quoting above the
respective minimum quantities per item is allowed. However, quoting below the minimum quantities shall be grounds for disqualification.
Item
Item Description Quantity Unit Material Cost Labor Cost Unit Cost Amount
No.
A. DESIGN PHASE
I. DETAILED ARCHITECTURAL AND ENGINEERING DESIGN SERVICES
Labor
Quantity Unit Material Cost Unit Cost Amount
Cost
Mobilization 1.00 lot -
Temporary Safety and Health 1.00 lot -
Sub-total -
Occupational Safety and Health
Safety Hard Hat 15.00 unit - -
Safety Shoes 15.00 pair - -
Safety Gloves 15.00 pair - -
Safety Harnest 15.00 unit - -
Safety Goggles 15.00 unit - -
Safety Boots 15.00 pair - -
Medicine Cabinet w/ first aid kit (10pcs-
1.00 l.s. - -
1Gal Alcohol,5pcs- 20ml Povidone
COA Billboard 1.00 lot - -
Project Billboard 1.00 lot - -
Demobilization 1.00 l.s. -
Sub-total -
SUB-TOTAL (General Requirements) -
PAGE 1 of 10
DSWD Field Office III, Government Center, Maimpis, City of San Fernando, Pampanga, 2000 Philippines
Website: www.fo3.dswd.gov.ph Tel Nos.: (045) 961-2143
DSWD-GF-007 | REV 01 / 12 OCT 2021
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Soil Poisoning
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
PAGE 2 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021
V. Architectural Works
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Masonry
CHB Laying (783.64 sq m.)
150 mm Concrete Hollow Blocks 9,501.00 pcs - - -
Sand 68.00 cu.m - - -
Cement 814.00 bags - - -
10mm dia x 6m Steel Bar (Grade 40) 1,778.00 kg - - -
# 16 G.I. Tie Wire 191.00 kg - - -
Plastering
Sand 26.00 cu.m - - -
Cement 313.00 bags - - -
Masonry (Sub-total) -
Windows
Materials Quantity Unit Material Cost Labor Unit Cost Amount
Fixed glass window on aluminum analok
72.00 sq.ft - - -
framing
Sliding glass window on aluminum analok
416.00 sq.ft - - -
framing
Awning window on aluminum analok framing 48.00 sq.ft - - -
Floor Finishes
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
Non Skid Floor Tiles 530.00 sq.m - - -
Wall Tiles (1.2m ht.) 50.00 sq.m - - -
Water Proofing
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
Cement Base Waterproofing 29.50 sq.m - - -
PAGE 3 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021
Railings
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Railings (Sub-total) -
Ceiling
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Ceiling (Sub-total) -
VI Sanitary/Plumbing Works
Water Lines
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
PPR Pipe 2" dia x 4m 28.00 pcs - - -
PPR Pipe 1" dia x 4m 10.00 pcs - - -
PPR Pipe 1/2" dia x 4m 8.00 pcs - - -
Gate Valve, 2" dia 3.00 unit - - -
Gate Valve, 1" dia 4.00 unit - - -
Check Valve, 2" dia 1.00 unit - - -
Fitting and Accessories 1.00 lot - - -
Sewer Lines
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
PVC Pipe, 100 mm dia x 3m 14.00 pcs - - -
PVC Pipe, 75 mm dia x 3m 22.00 pcs - - -
PVC Solvent 12.00 can - - -
Support and Hangers 1.00 lot - - -
Fitting and Accessories 1.00 lot - - -
Sanitary/Plumbing Fixture
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
PAGE 6 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021
Panelboard
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
(SMDP1) Main: 200AT, 350AF, 3P, 230V,
Bolt-on
Branches: 4 - 100AT, 150AF, 3P, 230V, Bolt- 1 set - - -
on
2 - 70AT, 100AF, 3P, 230V, Bolt-on
PAGE 7 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021
Panelboard (Sub-total) -
Lighting Fixtures
Electrical Transformer
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
IX Painting Works
Masonry Painting
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Metal Painting
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Wood Painting
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Supply and Installation of 12 unit CCTV
1 lot -
camera
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
PAGE 9 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021
(F) (Post Construction Phase) Processing of Occupancy Permits and fees, Securing
Permanent Electrical Connections and Fees, Securing Permanent Water District
Connections and Securing/Processing, Application & Accreditation of DSWD
Pollution Control Officers and other Necessary requirements (1.0%-2.0% of DC)
PAGE 10 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)