You are on page 1of 10

ADMINISTRATIVE DIVISION

FIELD OFFICE III


DSWD-GF-007 | REV 01 / 12 OCT 2021

"ANNEX-H" - MINIMUM QUANTITIES WITH SPECIFICATIONS


CONSTRUCTION OF TWO-STOREY DSWD FO III
DSWD - Field Office III Main Building, DMGC,
Name of Project: BUILDING AND FACILITIES UNDER DESIGN AND BUILD Location:
SCHEME
Maimpis, City of San Fernando (P)

Total Project Cost: PHP 18,645,000 Project Duration: 180 CALENDAR DAYS

Source of Fund: CAPITAL OUTLAY Mode of Procurement: COMPETITIVE PUBLIC BIDDING

Date: Friday, 21 January 2022 Source of Manpower: OUTSOURCE

Note:
1. Additional line items may be added in Annex H given that the purpose and use of the added items is clearly discussed in the construction
methodology subject for evaluation and assessment.

2. Items indicated in herein may be replaced with other items given that the purpose or intention for the replaced items shall be served and is
clearly discussed in the construction methodology subject for evaluation and assessment. All modifications in a way of deletion and reduction
in sub-item and quantities shall be equivalent in cost of the replaced items.

3. Several items indicated in “Annex H” are the required minimum quantities in Detailed Cost Estimate. Quoting above the respective minimum
quantities per item is allowed. However, quoting below the respective required minimum quantities per item shall be grounds for
disqualification.

4. All other items in “Annex H” under sections that are not enumerated above shall have the required minimum quantities. Quoting above the
respective minimum quantities per item is allowed. However, quoting below the minimum quantities shall be grounds for disqualification.

Item
Item Description Quantity Unit Material Cost Labor Cost Unit Cost Amount
No.
A. DESIGN PHASE
I. DETAILED ARCHITECTURAL AND ENGINEERING DESIGN SERVICES

Services for Detaield Architectural and


Engineering Design, Complete dicipline
withSigned & Sealed Detailed Engineering
Design Plans for Securing Permits, 1.00 l.s. -- -- -
Structural Analysis Signed & Sealed by
Structural Engineer and other analysis
needed for this project

SUB-TOTAL (Detailed Architectural and Engineering Design Services) -


B. CONSTRUCTION PHASE
I. General Requirements

Labor
Quantity Unit Material Cost Unit Cost Amount
Cost
Mobilization 1.00 lot -
Temporary Safety and Health 1.00 lot -
Sub-total -
Occupational Safety and Health
Safety Hard Hat 15.00 unit - -
Safety Shoes 15.00 pair - -
Safety Gloves 15.00 pair - -
Safety Harnest 15.00 unit - -
Safety Goggles 15.00 unit - -
Safety Boots 15.00 pair - -
Medicine Cabinet w/ first aid kit (10pcs-
1.00 l.s. - -
1Gal Alcohol,5pcs- 20ml Povidone
COA Billboard 1.00 lot - -
Project Billboard 1.00 lot - -
Demobilization 1.00 l.s. -
Sub-total -
SUB-TOTAL (General Requirements) -

PAGE 1 of 10
DSWD Field Office III, Government Center, Maimpis, City of San Fernando, Pampanga, 2000 Philippines
Website: www.fo3.dswd.gov.ph Tel Nos.: (045) 961-2143
DSWD-GF-007 | REV 01 / 12 OCT 2021

II. Site Development Works

Demolition of Existing Covered Court,


Cutting & Breaking of Pavement, Removal
1.00 LS - -
and Disposal of Concrete Debris,
Relocation of Container Vans

Structure Demolition (Sub-total) -

Structure Excavation (Footing, Tie Beam,


247.00 cu.m - -
Retaining Wall and Septic tank)

Structure Excavation (Sub-total) -

Embankment from Structure Excavation


130.00 cu.m - -
(Backfilling)

Embankment from Sturcture Excavation (Sub-total) -

Gravel Beddings 1.00 LS. -- -- -- --

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Gravel 3/4" 19.00 cu.m - - -

Gravel Beddings (Sub-total) -

Drainage System Tapping to Existing


1.00 LS. -- -- -- --
Outflow

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Drainage System 1.00 lot - - -

Drainage System (Sub-total) -

Soil Testing 1.00 LS.

Geotechnical Exploration, as Confirmatory of


Soil Bearig Capacity in the site (Provision of 1.00 l.s -- -
Signed and Sealed Geothechnical Report)

Soil Testing (Sub-total) -

Soil Poisoning

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Chemical Soil Poisoning 262.50 sq.m - - -

Soil Poisoning (Sub-total) -

SUB - TOTAL (Site Development Works) -

III. Structural Works


Structural Concrete 1.00 LS.

Materials Quantity Unit Material Cost Labor Unit Cost Amount

Ready Mix Concrete , 4000 psi, (3/4" Gravel) 330.00 cu.m - - -


Reinforcing Steel Bars, Grade 60 36,913.22 kg - - -
#16 GI Tie Wire 620.00 kg - - -
Form Works (3 Uses) 1,186.51 sq.m - - -
Form Works (Metal Deck) 230.00 sq.m - - -

SUB - TOTAL (Structural Works) -

PAGE 2 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

IV. Roofing Works


Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Prepainted Rib Type Roofing Sheet (Long


Span) w/ flashing ,gutter, spamdrel and other
401.50 sq.m - - -
accessories on a steel trusses and purlins
Gauge 24

SUB-TOTAL (ROOFING WORKS) -

V. Architectural Works
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Masonry
CHB Laying (783.64 sq m.)
150 mm Concrete Hollow Blocks 9,501.00 pcs - - -
Sand 68.00 cu.m - - -
Cement 814.00 bags - - -
10mm dia x 6m Steel Bar (Grade 40) 1,778.00 kg - - -
# 16 G.I. Tie Wire 191.00 kg - - -
Plastering
Sand 26.00 cu.m - - -
Cement 313.00 bags - - -

Masonry (Sub-total) -

Wall and Doors and Jambs with Complete


Accessories
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Solid Wooden Panel Door with Peep Glass
10.00 units - - -
Jamb and Accessories
Solid Wooden Panel Door with Jamb and
8.00 units - - -
Accessories
Electronic Door Lock System 2.00 units - - -

Doors and Jambs with Complete Accessories (Sub-total) -

Windows
Materials Quantity Unit Material Cost Labor Unit Cost Amount
Fixed glass window on aluminum analok
72.00 sq.ft - - -
framing
Sliding glass window on aluminum analok
416.00 sq.ft - - -
framing
Awning window on aluminum analok framing 48.00 sq.ft - - -

Windows with Complete Accessories (Sub-total) -

Floor Finishes
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
Non Skid Floor Tiles 530.00 sq.m - - -
Wall Tiles (1.2m ht.) 50.00 sq.m - - -

Floor Finishes (Sub-total) -

Water Proofing
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
Cement Base Waterproofing 29.50 sq.m - - -

Water Proofing (Sub-total) -

PAGE 3 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

Railings

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Stainless steel stairs railings 1.00 lot - - -

Railings (Sub-total) -

Ceiling

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Gypsum Board on metal furring and carrying


275.00 sq.m - - -
channel ceiling

Ceiling (Sub-total) -

SUB - TOTAL (Architectural Works) -

VI Sanitary/Plumbing Works
Water Lines
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
PPR Pipe 2" dia x 4m 28.00 pcs - - -
PPR Pipe 1" dia x 4m 10.00 pcs - - -
PPR Pipe 1/2" dia x 4m 8.00 pcs - - -
Gate Valve, 2" dia 3.00 unit - - -
Gate Valve, 1" dia 4.00 unit - - -
Check Valve, 2" dia 1.00 unit - - -
Fitting and Accessories 1.00 lot - - -

Water Lines (Sub-total) -

Sewer Lines
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
PVC Pipe, 100 mm dia x 3m 14.00 pcs - - -
PVC Pipe, 75 mm dia x 3m 22.00 pcs - - -
PVC Solvent 12.00 can - - -
Support and Hangers 1.00 lot - - -
Fitting and Accessories 1.00 lot - - -

Sewer Lines (Sub-total) -

Sanitary/Plumbing Fixture

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Water Closet 8.00 pcs - - -


Stainless Bidet 8.00 pcs - - -
Floor Drain (SS 304) 8.00 can - - -
Lavatory Counter Type with Stainless Faucet
8.00 lot - - -
and Complete Accessories
Automatic Flash Urinal 2.00 lot - - -

Sanitary/Pumbing Fixture (Sub-total) -

Storm Drainage and Down Spout


Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
HDPE Pipe, 200mm dia x 4m 8.00 pcs - - -
HDPE Pipe, 150mm dia x 4m 6.00 pcs - - -
PVC Pipe, 100 mm dia x 3m 3.00 pcs - - -
Roof Deck Drain Plate (SS 304) 3.00 pcs - - -
Catch Basin 5.00 unit - - -
Fitting and Accessories 1.00 lot - - -

Storm drainage and down spout (Sub-total) -

SUB - TOTAL (Sanitary/Plumbing Works) -


PAGE 4 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

VII. Mechanical Works


Automatic Fire Sprinkler
A. Installation of Automatic Fire Sprinkler System
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
Fire Pump 1.00 unit - - -
Jockey Pump 1.00 unit - - -
Booster Pump 1.00 unit - - -
Floor Control Valve, 65mmØ OS&Y Gate
2.00 pc - - -
Valve
65mm Supervisory Switch and Water Flow
2.00 pc - - -
Detector
Auxiliary Drain Valve 2.00 pc - - -
Inspection Test Valve 2.00 set - - -
Flushing connection 2.00 pc - - -
Fire Dept. Connection w/ Cap & Chain,
1.00 pc - - -
100mmØ x 65mmØ x 100mmØ
Sub-total -
Sprinkler Heads, Sheilds and Tools
Pendent 28.00 pc - - -
Sidewall 4.00 pc - - -
Upright 2.00 pc - - -
Sprinkler Head Cabinet w/ 8 spare heads 2.00 set - - -
Sub-total -
Pipes and Fittings
BI Pipe, 100mmØ, s-40 3.00 length - - -
BI Pipe, 65mmØ, s-40 12.00 length - - -
BI Pipe, 50mmØ, s-40 9.00 length - - -
BI Pipe, 40mmØ, s-40 5.00 length - - -
BI Pipe, 32mmØ, s-40 7.00 length - - -
BI Pipe, 25mmØ, s-40 15.00 length - - -
BI TEE, 100mmØ 3.00 pc - - -
Reducer TEE, 100mmØx 65Ø x 100Ø 3.00 pc - - -
BI TEE, 65mmØ 5.00 pc - - -
BI TEE, 50mmØ 5.00 pc - - -
BI TEE, 40mmØ 5.00 pc - - -
BI TEE, 32mmØ 5.00 pc - - -
BI TEE, 25mmØ 5.00 pc - - -

BI TEE, 65mmØ x 50Ø x 65mmØ, buttweld 9.00 pc - - -

BI TEE, 65mmØ x 25Ø x 65mmØ, buttweld 9.00 pc - - -

BI TEE, 50mmØ x 38Ø x 50mmØ, buttweld 9.00 pc - - -

BI TEE, 38mmØ x 32Ø x 38mmØ, buttweld 9.00 pc - - -

BI TEE, 32mmØ x 25Ø x 32mmØ, buttweld 10.00 pc - - -

Bell Reducer, 100mmØ x 63mmØ 4.00 pc - - -


Bell Reducer, 65mmØ x 50mmØ 16.00 pc - - -
Bell Reducer, 50mmØ x 40mmØ 25.00 pc - - -
Bell Reducer, 40mmØ x 32mmØ 25.00 pc - - -
Bell Reducer, 32mmØ x 25mmØ 25.00 pc - - -
Bell Reducer, 25mmØ x 12mmØ 35.00 pc - - -
BI Elbow, 25mmØ 35.00 pc - - -
Bind Flange, 65mmØ 10.00 pc - - -
Slip-On Flange, 100mmØ 5.00 pc - - -
Slip-On Flange, 65mmØ 5.00 pc - - -
Slip-On Flange, 50mmØ 5.00 pc - - -
Threadolet, 50mmØ 4.00 pc - - -
Victaulic Coupling, 50mmØ 4.00 pc - - -
Victaulic Coupling, 100mmØ 2.00 pc - - -
Check Valve, 100mmØ, (Fire Pump) 1.00 pc - - -
PAGE 5 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

Check Valve, 50mmØ, (Jockey Pump) 1.00 pc - -

Check Valve, 50mmØ, (Booster Pump) 1.00 pc - -

OS&Y Gate Valve, 100mmØ, (Main Line-Fire 1.00 pc - -

OS&Y Gate Valve, 100mmØ, (Return Test Lin 1.00 pc - -

Gate Valve, 50mmØ, (Jockey Pump) 1.00 pc - -


Gate Valve, 50mmØ, (Booster Pump) 1.00 pc - -
Complete Vertical Alarm Check Valve,
1.00 set - -
Assembly 100mmØ
Sub-total -

Automatic Fire Sprinkler (Sub-total) -

Fire Detection and Alarm Sytem


A. Installation of Fire Alarm System
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
20mmØ PVC Pipe 60.00 length - - -
25mmØ PVC Pipe 6.00 length - - -
20mmØ PVC Adaptor 42.00 pc - - -
25mmØ PVC Adaptor 5.00 pc - - -
20mmØ Locknut and Bushing 45.00 pc - - -
25mmØ Locknut and Bushing 6.00 pc - - -
Utility Box 7.00 pc - - -
Junction Box/Octagonal Box 12.00 pc - - -
Flexible Metal Conduit 15mm 16.00 pc - - -
Pullbox 6" x 6" 4.00 pc - - -
2.0mm squared THHN 550.00 l.m. - - -

Smoke Detector Sensor w/ Modular Base 12.00 pc - - -


Vibrating Round Bell 6" dia. 24vDC 2.00 pc - - -
Manual Call Point Station 2.00 pc - - -
Anunciator 2.00 pc - - -

8 Zones Fire Alarm Control Panel w/ Backup 1.00 assy - - -


Testing and Commissioning 1.00 lot - - -

Fire Detection and Alarm Sytem (Sub-total) -

Cooling System / Centralize Airconditioning and Ventilating System


A. Installation of Cooling System
Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Package/ Split Type, Inverter Air-con Unit,
2.00 lot - - -
Wall Mounted, 1.0 HP, 1Ø, 230V
Package/ Split Type, Inverter Air-con Unit,
2.00 lot - - -
Wall Mounted, 2.0 HP, 1Ø, 230V
Package/ Split Type, Inverter Air-con Unit,
2.00 lot - - -
Floor Mounted, 5Ton, 1Ø, 230V

Cooling System / Centralize Airconditioning and Ventilating System (Sub-total) -

SUB - TOTAL (Mechanical Works) -

VIII ELECTRICAL WORKS

Electrical Conduits Works


Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

PVC Pipe, 50mm x 3m, Orange 4 pcs. - - -


PVC Pipe, 40mm x 3m, Orange 8 pcs. - - -
PVC Pipe, 20mm x 3m, Orange 312 pcs. - - -
PVC Male Adapter w/ Lock Nut, 50mm 3 pcs. - - -

PVC Male Adapter w/ Lock Nut, 40mm 5 pcs. - - -

PVC Male Adapter w/ Lock Nut, 20mm 400 pcs. - - -

PAGE 6 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

PVC Long Elbow, 50mm 4 pcs. - - -


PVC Long Elbow, 40mm 8 pcs. - - -
PVC Long Elbow, 20mm 140 pcs. - - -
Wire gutter 1 lot - - -
15mm Flexible Metallic Conduit (1.5m per
160 pcs. - - -
piece)
PVC Junction Box with Cover, 4" x 4" 155 pcs. - - -
PVC Utility Box, 4" x 2" 105 pcs. - - -
Square Box, 4" x 4" 26 pcs. - - -

Pull Box, 8" x 8" x 6" 4 pcs. - - -

Fittings, C-clamp, PVC Solvent and Pull Wire


1 lot - - -
and other accessories

Electrical Conduits Works (Sub-total) -

Wires and Wiring Devices


Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
38mm² THHN wire 45 meters - - -
30mm² THHN wire 90 meters - - -

14mm² THHN wire (color white or gray only) 15 meters - - -

8.0mm² THHN wire (color white or gray only) 25 meters - - -


5.5mm² THHN wire 1000 meters - - -
3.5mm² THHN wire 450 meters - - -

3.5mm² THHN wire (color white or gray only) 2000 meters - - -

Electrical Outlet, Universal Type, 2-Gang, 3-


Prong (with grounding) including Cover Plate, 60 sets - - -
(Screw type terminals)

Electrical Outlet, Universal Type, 1-Gang, 3-


Prong (with grounding) including Cover Plate, 16 sets - - -
(Screw type terminals)

3-gang Electrical Switch, Classic Series, 3-


Gang including Cover Plate, (Screw type 25 sets - - -
terminals)
2-gang Electrical Switch, Classic Series, 2-
Gang including Cover Plate, (Screw type 32 sets - - -
terminals)
1-gang Electrical Switch, Classic Series, 1-
Gang including Cover Plate, (Screw type 20 sets - - -
terminals)
3-way Electrical Switch, Classic Series, 1-
Gang including Cover Plate, (Screw type 12 sets - - -
terminals)
Electrical Tape, big size (16m) 45 pcs. - - -

Electrical Rubber Tape (3/4" x 8 meters) 20 pcs. - - -

Wires and Wiring Devices (Sub-total) -

Panelboard
Labor
Materials Quantity Unit Material Cost Unit Cost Amount
Cost
(SMDP1) Main: 200AT, 350AF, 3P, 230V,
Bolt-on
Branches: 4 - 100AT, 150AF, 3P, 230V, Bolt- 1 set - - -
on
2 - 70AT, 100AF, 3P, 230V, Bolt-on

PAGE 7 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

(SMDP2) Main: 350AT, 500AF, 3P, 230V,


Bolt-on
Branches: 1 - 150AT, 255AF, 3P, 230V, Bolt-
1 set - - -
on
3 - 125AT, 175AF, 3P, 230V, Bolt-on
2 - 100AT, 150AF, 3P, 230V, Bolt-on
(SMDP3) Main: 600AT, 800AF, 3P, 230V,
Bolt-on
Branches: 4 - 350AT, 500AF, 3P, 230V, Bolt-
1 set - - -
on
1 - 200AT, 350AF, 3P, 230V, Bolt-on
1 - 150AT, 255AF, 3P, 230V, Bolt-on
(LP1) Main: 100AT, 150AF, 3P, 230V, Bolt-
on
1 set - - -
Branches: 16 - 20AT, 50AF, 2P, 230V, Bolt-
on
(DP1) Main: 125AT, 175AF, 3P, 230V, Bolt-
on
1 set - - -
Branches: 7 - 30AT, 50AF, 2P, 230V, Bolt-on

11 - 20AT, 50AF, 2P, 230V, Bolt-on


(PP1) Main: 100AT, 150AF, 3P, 230V, Bolt-
on

Branches: 2 - 50AT, 70AF, 3P, 230V, Bolt-on 1 set - - -

2 - 40AT, 60AF, 2P, 230V, Bolt-on


10 - 30AT, 50AF, 2P, 230V, Bolt-on
(ECB) 30AT, 50AF, 2P, 230V, Bolt-on in
6 set - - -
NEMA 1R
(ECB) 30AT, 50AF, 2P, 230V, Bolt-on in
1 set - - -
NEMA 3R

Panelboard (Sub-total) -

Lighting Fixtures

Materials Quantity Unit Material Cost Labor Unit Cost Amount

2x18 Watts T8 LED Tube Light with


Aluminum Reflector and Complete
60 sets - - -
Accessories:
Dimensions (12" x 48" x 3")
1x11 Watts LED Bulb light in pinlight
housing with aluminum reflector, recessed
10 sets - - -
type including complete accessories:
Dimensions (8"
1x15 Watts LED Bulb light in pinlight
housing with aluminum reflector, recessed
type including complete accessories: 15 sets - - -
Dimensions (8"
diameter)
1x15 Watts LED Bulb light in pinlight
housing with aluminum reflector, surface type
including complete accessories: Dimensions 12 sets - - -
(12"
diameter)

Lighting Fixtures (Sub-total) -

Electrical Transformer

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Electrical Transformer 240/480 KVA 1.00 set - - -

Electrical Transformer (Sub-total) -

SUB-TOTAL (ELECTRICAL WORKS) -


PAGE 8 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

IX Painting Works
Masonry Painting

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Masonry Painting (3 coatings) 1870.00 sq.m - - -

Masonry Painting (Sub-total) -

Metal Painting

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Metal Painting (2 coatings) 40.00 sq.m - - -

Metal Painting (Sub-total) -

Wood Painting

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Wood Painting (3 coats) 280.00 sq.m - - -

Wood Painting (Sub-total) -

SUB - TOTAL (Painting Works) -

X Electronics and Communications Works


Installation of CCTV

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount
Supply and Installation of 12 unit CCTV
1 lot -
camera

Installation of CCTV (Sub-total) -

Data Network and Cabling

Materials Quantity Unit Material Cost Labor Cost Unit Cost Amount

Supply and Installation of Data Network


1 lot -
Cabling System of Entire Building

Data Network Cabling System (Sub-total) -

SUB - TOTAL (Electronics and Communications) -

XI Supply and Installation of Office Sytem

Supply and Installation of Office System 1.0 lot -

SUB - TOTAL (Supply and Installation of Office Sytem) -

XII Supply & Installation of Generator Set, 60kVA - 100kVA (3P)


Supply & Installation of Generator Set, 60kVA-
1.0 sets -
100kVA (3P)

SUB - TOTAL (Supply & Installation of Generator Set, 60kVA (3P)) -

PAGE 9 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)
DSWD-GF-007 | REV 01 / 12 OCT 2021

( A) TOTAL DIRECT COST (Materials, Labor and Equipment Cost)


(B) OCM (10% of A)
(C) Contractor's Profit (8% of A)
(D) VAT (5.0 % of A+B+C)
(Pre & During Construction Phase) Processing of Building Permit including its Fees,
Gov't Clearances and fees, Location Clearance fees and application, Electrical
(E) Temporary Connections Fees , Water District Temporary Connections,(Tax Inclusive
for all permits), Preparation of grounds breaking cermonies & Inauguration
cermonies (1.50%-3.0% of DC)

(F) (Post Construction Phase) Processing of Occupancy Permits and fees, Securing
Permanent Electrical Connections and Fees, Securing Permanent Water District
Connections and Securing/Processing, Application & Accreditation of DSWD
Pollution Control Officers and other Necessary requirements (1.0%-2.0% of DC)

( H ) TOTAL INDIRECT COST (B + C + D+ E + F)


TOTAL PROJECT COST ( A + H )

PAGE 10 of 10
(Construction of Two – Storey DSWD FO III BUILDING AND FACILITIES under Design and Build Scheme)
DSWD FO III| (ARDA CLUSTER / FIELD OFFICE NO. 3) | (ADMIN)

You might also like