Complex Basement Construction in Very Congested Urban Environtment


DEEP BASEMENT
IN DENSE URBAN CONDITION

Design Consideration:

- Depth of Excavation
- Type of Soil
- Water Table
- Adjacent Structure / Site Constraints
- Sequence of Works
- Excavation Methodology
Complex Basement Construction in Very Congested Urban Environtment - Construction Details
DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Use of RC Slab as Struts

Use of RC slab as strut gives the required


SUPPORT
rigid support for the diaphragm wall
Work progressed simultaneously for the
Top-Down Semi Top-Down basement and the super-structure, saving
Construction Construction
construction time
TDC enables the superstructure Semi TDC makes use of the
and the underground structure stiff RC slab as struts, starting Design MUST reflect the actual sequence of
to be built simultaneously the construction from the
GROUND ANCHOR
ground to the bottom
work. DETAILING is tedious and complex
STRUT : Steel or RC slab (top down)

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

1
11/12/2014

Top-Down Construction The Key Component

Construction Method
Where to install the 1st slab
Sequence of
Work
Choice of
LL for Working Platform Depends on
King-Post
Equipment And Method of Work
Strutting
System
Installing the Kingpost
Load Path
Casting Concrete under the Slab
Connect RC Slab to Kingpost
Steel Rebar Passing Through Kingpost
Soil Removal: Skip Floor or Not? Construction Holes?

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Soil Removal

Soil Removal

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

WTC-2
Mosque

Basement is located very close to adjacent WTC-2,


5-level basement Wisma Metropolitan 1, Mosque and future WTC-4.
Dense urban location Excavation reached 15.8 meters
Wisma Metropolitan 1 +
Deformation of the retaining structure must be
WTC-2 + Mosque are
close to the basement minimized to avoid damaging adjacent structures
Depth of excavation 16 M
Not possible to install ground anchors
Semi Top-Down
Construction WM-1 Limited access and space for work

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

2
11/12/2014

WM-1

115 piles φ1500mm


with kingpost

Bored-piles φ1200 mm
without kingpost

WTC-2

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Stress S22 Diagram: Effect of soil pressure and openings on RC slab


Strutting
the Hole Temporary Ramp for Construction

Check the Stress in the Slab


Due to Soil Pressure and
Construction Opening

COMPRESSION TENSION

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

3
11/12/2014

Connection Detail:
The Details Kingpost to Slab

Use of CAD/CAM
to help the Design Process

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Work on Progress:
Preparation Work for B-1 Slab
(Working Platform)

Welding Quality Inspection

Shear Stud Quality Assurance

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Case Study No.2: Plaza Indonesia Extension


48-story + 5-level basement, 220,000 sq.m, completed in 2009

Basement is located very close to adjacent Grand


Hyatt hotel, e-X center and Japanese Embassy, and
excavation reached 17 meters

Project High water table, 1.5 – 2.0 meters below the surface
Location

Deformation of the retaining structure must be


minimized to avoid damaging adjacent structures

Limited Construction time and space for work

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

4
11/12/2014

Use of RC slab as strut gives the required


-Use RC slab as strut
-Work simultaneously Top-Down Construction rigid support for the diaphragm wall
upwards and downwards
Work progressed simultaneously for the
basement and the super-structure, saving
11 month’s construction time
The Ground floor was designed
for LL = 2000kg/sq.m (20kPa)
On completion of B-5 level, work on
to take construction load superstructure had reached level-11

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Use of metal formwork for precision and speed of construction

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Use of weldable coupler


Dye Penetrant Test
to Check Weld Quality
Holes for steel rebar

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

5
11/12/2014

Foundation of Tower Crane

Pipes for concrete casting

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Analysis and design of D-wall, king-posts


and supporting bored-piles
must follow construction sequence

High capacity king-post and bored pile


is required to take the construction load
before the RC mat is poured and
steel king-post encased in concrete

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Horizontal Deflection Bending Moment Shear Force "A"-side : Adjacent to Existing Plaza Indonesia (Without Temporary Strut)
Horizontal Deflection Bending Moment Shear Force
0 0 0
0 0 0 0
Excav. To 3.7m (EL. -0.35m)
-5 -5 -5
-5 -5 -5
-5 Bending Moment
-10 -10 -10 B1 and Excav. To 6.7m (-3.35m)
-10 -10 -10 Min ≅ -63.5 ton.m/m
-10
Max ≅ 64.0 ton.m/m
-15 -15 -15
Depth (m)

Depth (m)

Depth (m)
B2 and Excav. To 9.7m (-6.35m)
-15 -15 -15
Depth (m)

Depth (m)

Depth (m)

-20 -20 -20


-15

Depth (m)
-20 -20 -20 B3 and Excav. To 12.7m (-9.35m)

-25 -25 -25


-25 -25 -25 -20 B4 and Excav. To 14.2m (-10.85m)

-30 -30 -30


-30 -30 -30
Excav. To 15.85m (-12.5m)
-25
-35 -35 -35
-35 -35 -35 -20 0 20 40 60 -100 -50 0 50 100 -50 -25 0 25 50
-20 0 20 40 60 -100 -50 0 50 100 -50 -25 0 25 50 Mat (t=2.5m)
Horizontal Deflection (m m ) Bending Mom ent (ton.m /m) Shear Force (ton/m ) -30
Horizontal Deflection (m m) Bending M oment (ton.m /m ) Shear For ce (ton/m)
Excav. To 15.85m (-12.5m) Excav. To 15.85m (-12.5m) Excav. To 15.85m (-12.5m)
Excav. To 3.7m (EL. -0.35m) Excav. To 3.7m (EL. -0.35m) Excav. To 3.7m (EL. -0.35m) GWL Recovery
Mat (t=2.5m) Mat (t=2.5m) Mat (t=2.5m)
-35
B1 and Excav. To 6.7m (-3.35m) B1 and Excav. To 6.7m (-3.35m) B1 and Excav. To 6.7m (-3.35m)
-80 -60 -40 -20 0 20 40 60 80
D-Wall Bending Moment (ton.m/m )

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

6
11/12/2014

Site Condition – Oct.2006

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Adjacent to Existing Plaza Indonesia Adjacent to Exist. Plz. Indo.


[Excavation depth = 16m]
0 0

-5 -5

-10 -10

-15 -15

Depth (m)
Depth (m)
-20 -20
1st
Step

-25
-25

-30
-30
Final
Step

-35
-35
0 10 20 30 40 50
-80 -60 -40 -20 0 20 40 60 80
D-Wall Horz. Deflection (mm )
Envelope of D-Wall Be nding Mom ent (ton.m /m )
DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Adjacent to Jln. Thamrin Adjacent to Jln. Thamrin


[Excavation Depth = 14.5m ]
0 0

-5 -5

-10 -10

-15 -15
Depth (m)

Depth (m)

1st
-20 -20 Step

-25 -25

Final
-30 -30
Step

IA-1 IB-3

-35 -35
-80 -60 -40 -20 0 20 40 60 80 0 10 20 30 40 50

Envelope of D-Wall Bending Mom ent (ton.m/m ) D-Wall Horz. Deflection (m m)


DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

7
11/12/2014

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Jan2008

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

8
11/12/2014

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers DAVYSUKAMTA & PARTNERS, Structural Engineers

Case Study No.3


MENARA BANK MEGA
JAKARTA

26-story, 4-level basement


Semi Top-Down Construction
Skip-floor method
Completed in 2006

Construction of Secant Pile,


Bored-Pile and Kingpost

Installation of King-Post
TAHAP 1

9
11/12/2014

Construction of Level B-1/


Working Platform

Use Level B-1 as Working Platform TAHAP 2

Excavation under B-1 Slab

Excavation to B-3 Level:


Skip Floor Method

TAHAP 3

Work on Level B-3

Starter Bars

10
11/12/2014

Steel Ramp for Access

Strutting
the Hole

Completion of B-4 level

TAHAP 4 Excavation Work Under B-


B- 3 Slab

11
11/12/2014

Use of Chemical Anchors as Dowels


Transfer of Force by Shear-Friction

Galian Tanah P3 Galian Tanah P3 dan Opening LG+P2

Casting of mat foundation


+ 3240 m3 in 36 hours

Constructing the B-2 Level:


Inserting the RC Slab

Preparation for mat Foundation

TAHAP 5

12
11/12/2014

Constructing the B-2 Slab

Use of Chemical Anchors as Dowels


Transfer of Force by Shear-Friction

Excavation P2-P3 (B-3 s/d


Soil Excavation Under LG (B-1) Excavation LG-P2 B-4) dan Mat Foundation
= 16,000 m3 Completed in 65 Days
(B-1 to B-3) = 25,200 m3
Completed in 76 Days
Main Issue: Exercise care for Kingpost Completed in 48 Days Final Work by Manual
Excavation

Completed Project, 2006