Daily Report

DATE: 10-28-2022
PROJECT AREA: LUGAIT SPORTS COMPLEX

TEAM MEMBERS:

SAIMON LOZADA MARJUN MOLAN


JOHN EVE EXAMINADA KIM JD MORATA
GARIEL MORATA JOSEPH BANAAG
TAGARDA ALEXIS RONRON SABANAL
JEUVANIE BANAAG CARLO SABANAL
RONELO JAMISOLAMIN ALVIN LUCERO
CRES SANCHEZ JOSE BABASOL

DAYS DUTY
Day 21

SITE LOG IN / LOG OUT


8:00 am - 12:00 pm
1:05 pm - 5:00 am

I. ACCOMPLISHMENT
ACTUAL ACTIVITY:
 Nahuman ug cover sa grupo nila Gabriel ang duha (2) ka steel post extension
ug hardiflex. Pagka 5:40 PM, nahuman nila ang fascia frame.
 Ang grupo ni Marjun, nahuman nilag finishing ang ilalom sa beam ug jam sa
teller area.
 1:00PM nagbuhos ang grupo sa mezzanine column ug anchor bolt.
 Na receive na ang ubang materials nga gi deliver.

II. CONCERNS/REQUESTS/ISSUES: N/A


III. RECOMMENDATION:
1. During working hours, employees must concentrate on their assigned tasks.
2. To achieve the project's estimated deadline, double the time spent on the
work.
3. Ensure that the necessary materials are available so that the task does not sit
idle.
4. Ensure collaboration and communication on the construction site.

STATUS: Still On-going

IV. DOCUMENTATION

(Figure 1. Concrete pouring being done on mezzanine columns)


(Figure 2. Concrete finishing is being done in the Teller area)

(Figure 3. Installation of hardiflex in the extension steel post.)