ID Task Task Name Duration Start Finish PIC

Mode
1 Timeline Rekomendasi PMHC NLS Q4 2020 9 days Fri 05/02/21 Fri 19/02/21
2 Request Snapshot Server Apps 1 day Fri 05/02/21 Fri 05/02/21 Pak Deni
3 Implementasi pemindahan Path Folder dari C ke D (UAT)
2 days Mon 08/02/21 Tue 09/02/21 NDS
4 End To End Test 2 days Wed 10/02/21 Thu 11/02/21 Pak Deni
5 Prepare dokumem SDLC 3 days Mon 15/02/21 Wed 17/02/21 Pak Deni
6 Implementasi pemindahan Path Folder dari C ke D (PRD)
1 day Fri 19/02/21 Fri 19/02/21 NDS;Pak Deni

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PMHC NLS Q4
Summary Manual Summary Rollup Progress
Date: Fri 05/02/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
Predecessors
31 Jan '21 07 Feb '21 14 Feb '21 21 Feb '21
W T F S S M T W T F S S M T W T F S S M

Pak Deni
2 NDS
3 Pak Deni
4 Pak Deni
5 NDS;Pak Deni

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PMHC NLS Q4
Summary Manual Summary Rollup Progress
Date: Fri 05/02/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2

You might also like