You are on page 1of 3

Product Documentation GIS (PGHV DEPARTMENT)

abb On Site Test / SAT JAKARTA, INDONESIA

VOLTAGE
TRANSFORMER
PROCEDURE TEST

Doc. Kind Doc Title Doc No. Lang. Rev.


VOLTAGE
abb PT. ABB SAKTI INDUSTRI Procedure TRANSFORMER
PROCEDURE TEST
07 Eng A

Page 1 of 3
Product Documentation GIS (PGHV DEPARTMENT)
abb On Site Test / SAT JAKARTA, INDONESIA

A. PURPOSE
This procedure covers all inspections and tests to be performed on a current transformer
after installation at site and prior energization.
B. EQUIPMENT REQUIRED
- Digital CPC/VT Analyzer.
- Mega Ohm Meter 500/5000 V.
C. GENERAL INSPECTION
- Visual inspection, compliance with drawings.
- Visual check rated pressure.
- Nameplate ratings.
- Connections tightening, cables marking.
- Grounding system (continuity and connections).
- Fuses/ MCB rating.
D. ISOLATIONS RESISTANT TEST
- Apply a DC voltage for 1 minute (500 V DC for the LV side winding)
- Performance the following Test:
> Insulation resistance between Primary winding and ground.
> Insulation resistance between Secondary windings and ground.

> Insulation resistance between Secondary windings.


> Insulation resistance between Primary and Secondary windings.
E. SECONDARY CHARACTERISTICS
In order to control that the PT is meeting the requirements, and for some type of protection relays
such as differential or high impedance relays, the following secondary measurements must be done.
E.1 PT SECONDARY RESISTANCE
- Disconnect the secondary loop from the PT’s terminals.
-
E.2 SECONDARY BURDEN
- Disconnect the secondary loop from the PT’s terminals.
- Inject with the secondary injection set, a voltage equal to the nominal secondary of the
PT by using CPC or CT/VT Analyzer.
- Check that the consumption does not exceed the nominal rated power of the PT.

Doc. Kind Doc Title Doc No. Lang. Rev.


VOLTAGE
abb PT. ABB SAKTI INDUSTRI Procedure TRANSFORMER
PROCEDURE TEST
07 Eng A

Page 2 of 3
Product Documentation GIS (PGHV DEPARTMENT)
abb On Site Test / SAT JAKARTA, INDONESIA

F. RATIO TEST
Apply an AC source on the primary side of the potential transformer. The primary and secondary
voltages are measured to determine the ratio Vs / Vp.
Vp = injected primary voltage
Vs = measured secondary voltage
NOTE: Check that the unused windings are NOT BE shorted.
G. RECORDING OF INSPECTION AND TEST DATA
The results of the checks and measurements made during the field test shall be recorded.

Doc. Kind Doc Title Doc No. Lang. Rev.


VOLTAGE
abb PT. ABB SAKTI INDUSTRI Procedure TRANSFORMER
PROCEDURE TEST
07 Eng A

Page 3 of 3

You might also like