4 3 Takt br 25 (armatura,oplata I beton) 7d 19.11.2021 26.11.2021 29,120.72 KM Beton zidova (821.7-840.5 Beton zidova (821.7-840.5 mnm)MB30[88 m3];Armatura B500B[5,096 kg]
mnm)MB30[88 m3];Armatura
B500B[5,096 kg]
5 4 Takt br 26 (armatura,oplata I beton) 7d 26.11.2021 4.12.2021 39,791.57 KM Beton zidova (821.7-840.5 Beton zidova (821.7-840.5 mnm)MB30[120 m3];Armatura B500B[7,001 kg]
mnm)MB30[120 m3];Armatura
B500B[7,001 kg]
6 5 Takt br 27 (armatura,oplata I beton) 7d 4.12.2021 11.12.2021 27,672.87 KM Beton zidova (821.7-840.5 Beton zidova (821.7-840.5 mnm)MB30[83.57 m3];Armatura B500B[4,851 kg]
mnm)MB30[83.57
m3];Armatura B500B[4,851 kg]
7 12 Takt br 29 (armatura,oplata I beton) 8d 22.12.2021 18.1.2022 37,640.36 KM Beton zidova (821.7-840.5 Beton zidova (821.7-840.5 mnm)MB30[114 m3];Armatura B500B[6,548 kg]
mnm)MB30[114 m3];Armatura
B500B[6,548 kg]
8 7 Takt br 30 (armatura,oplata I beton) 7d 18.1.2022 26.1.2022 35,880.08 KM Beton zidova (821.7-840.5 Beton zidova (821.7-840.5 mnm)MB30[108 m3];Armatura B500B[6,344 kg]
mnm)MB30[108 m3];Armatura
B500B[6,344 kg]
9 8 Takt br 31 (armatura,oplata I beton) 7d 26.1.2022 2.2.2022 33,571.87 KM Beton zidova (821.7-840.5 Beton zidova (821.7-840.5 mnm)MB30[102 m3];Armatura B500B[5,791 kg]
mnm)MB30[102 m3];Armatura
B500B[5,791 kg]
10 4 Takt br 33 I 34 (armatura, oplata, 15 d 26.11.2021 12.12.2021 4,624.57 KM Beton trougaonih zidova Beton trougaonih zidova debljine d=50cm na krilnim zidovima ulazne građevine, MB-30[8.43 m3];Armatura B500B[895 kg]
beton) - Metalna oplata Faresin debljine d=50cm na krilnim
zidovima ulazne građevine,
MB-30[8.43 m3];Armatura
B500B[895 kg]
13 9 Takt br 32 ploča na koti 842 12 d 2.2.2022 15.2.2022 34,172.05 KM Beton ploče na koti 842.00 Beton ploče na koti 842.00 (radni plato)-dio UG[103 m3];Armatura B500B[8,415 kg]
(radni plato)-dio UG[103
m3];Armatura B500B[8,415 kg]
16 15 Takt br 2 (armatura,oplata I beton) 5d 24.1.2022 29.1.2022 51,901.44 KM Armatura B500B[15,872 Armatura B500B[15,872 kg];Beton potpornih zidova MB-30[128 m3]
kg];Beton potpornih zidova
MB-30[128 m3]
17 16 Takt br 3 (armatura,oplata I beton) 5d 29.1.2022 3.2.2022 51,901.44 KM Armatura B500B[15,872 Armatura B500B[15,872 kg];Beton potpornih zidova MB-30[128 m3]
kg];Beton potpornih zidova
MB-30[128 m3]
18 17 Takt br 4 (armatura,oplata I beton) 5d 4.2.2022 9.2.2022 51,901.44 KM Armatura B500B[15,872 Armatura B500B[15,872 kg];Beton potpornih zidova MB-30[128 m3]
kg];Beton potpornih zidova
MB-30[128 m3]
19 18 Takt br 5 (armatura,oplata I beton) 5d 9.2.2022 14.2.2022 51,901.44 KM Armatura B500B[15,872 Armatura B500B[15,872 kg];Beton potpornih zidova MB-30[128 m3]
kg];Beton potpornih zidova
MB-30[128 m3]
20 19 Takt br 6 (armatura,oplata I beton) 5d 14.2.2022 20.2.2022 51,901.44 KM Armatura B500B[15,872 Armatura B500B[15,872 kg];Beton potpornih zidova MB-30[128 m3]
kg];Beton potpornih zidova
MB-30[128 m3]
21 20 Takt br 7(armatura,oplata I 5d 20.2.2022 25.2.2022 39,639.70 KM Armatura B500B[12,090 Armatura B500B[12,090 kg];Beton potpornih zidova MB-30[98 m
beton)-ploča na koti 842 kg];Beton potpornih zidova
MB-30[98 m3]
Page 1
800,000.00
CASH FLOW
701,928.82
FINANSIJSKI PLAN
700,000.00
600,000.00
435,873.65
500,000.00
400,000.00
266,055.16
238,232.83
300,000.00
197,640.82
94,760.22
200,000.00
102,880.61
94,760.22
100,000.00
0.00
November 2021 December 2021 January 2022 February 2022
Cost 94760.21787 102880.6066 238232.8281 266055.1644
Cumulative Cost 94760.21787 197640.8245 435873.6526 701928.817