Professional Documents
Culture Documents
Observation Report
Rev 00
22/03/2022
Incident Description
- Customer informed SEE that a crack occurred on the Potential Transformer of
What happened Phase L2 for Cell 1/Main Incomer 1.
PT failure Ph-L2
Corrective Actions
All collected data along with the defected potential transformer (ALCE type) will need to be sent
for TEX analysis.
The defected P.Ts (ALCE type) will be sent back to BADR for full assessment.
Observations
1- Failure occurred at cell 01 – Main Incomer affecting Potential Transformer of Phase L2.
(Pic 6,7,8 &9)
2- After dismantling the affected P.Ts, the subjected potential transformer (ALCE type)
appeared severely cracked. (Pic 6,7,8 &9)
3- Voltage protection functions were deactivated by customer.
4- Too much dust inside shelter and inside panels as well. (Pic 3,4 & 5)
5- The copper connection for phase L2 is decoloured most probably because of the humidity
and the dust. (Pic 10)
Important Observation:
1- Customer claims that the voltage protection functions were deactivated since the
commissioning of the substation.
2- According to the above point, we couldn’t find any valuable data that could help analyse this
failure within the extracted log from the protection relay.
3- We asked the customer to obtain the protection relay’s extractions (events log &
disturbance record) for the upstream SS.
4- The new P.Ts weren't stored properly. (Pic 11&12)
5- The shelters aren't sealed properly and the dust affects the mechanical operation of the
shutters and the circuit breakers. (Pic 3,4 & 5 &15)
6- The roof of the shelter needs to be repaired and installed correctly. (Pic 16)
Pic.15 Existing dust on the roof of the switchgear Pic.16 Shelter Roof.
1- Setting overview
i. General characteristics VT connection type to be
checked, should be V1, V2, V3
50/51 activated
Elements 1 & 2
1
-On 19/03/2022 2:33:21 AM, there’s an OC happened.
-short circuit duration is about 190 ms, less than OC and EF settings, that’s why
CB not tripped.
-fault current was about 5KA then decayed to normal value 190 A
2
-A disturbance at voltage measurement was occurred before current fault for a
period 400 ms (incident of PT failure)
-After current back to normal value, voltage measurements were
U21= 1.2KV
U32= 1.2KV Failure at Ph-L2
U13= 2.1KV
1- Setting overview
i. General characteristics
1- Setting overview
i. Current protection
Conclusion
Additional Recommendations
Risk:
Arc Flash Occurrence
Risk:
High Temp. rise may cause the
following
The insulators will break down.
Short lifetime for the panels.
Explosion may occur.
leakage current, tracking and flashover on
insulators.
Corrective action proposed: