To : China Construction (S.E.A) Corporation Attention : Mr. Phan Bui Anh Tai
1.0 Your drawings are rejected and returned herewith for your compliance as per our comments over-marked
therein.
2.0 Your drawings are rejected and returned herewith as they have not been checked and coordinated by you.
Note: Your endorsement stamp is required on every drawing.
3.0 Your drawings are rejected and returned herewith due to non-compliance of our comments with reference
to your previous submission ref.
4.0 Your drawings are rejected and returned herewith as they are incomplete and cannot be commented on.
You are to submit the above together with relevant interfacing details for other trades including
__________________________________________________________________________________
6.0 Your drawings have been examined with the following observations added:
Take up all minor comments annotated on the shop drawings.
Contractor is responsible to verify the dimensions and levels shown in the drawings.
All dimensions and levels are to be checked and verified at site prior to commencement of the relevant
works.
7.0 Remarks
Color of door frame and door leaf subject to Archi’s approval before proceeding to fabrication.
Contractor to ensure comply with PCCC requirement and obtain fire certificate for Define
project.
Technical door must be provided master key, contractor to submit a separate master key
schedule for approval.
There shall be no time & cost impact on this approval and associated scope of works
Final approval subject to final inspection onsite
Our examination of the drawings does not relieve you of your responsibilities. You are still responsible for all
correctness of dimensions and details in the drawings and for the full coordination of all aspects of the work. Work shall
conform to all Drawings & Specifications, and the Contractor is responsible to highlight if the design results in any
variation of cost and time.
Please note that delay caused by late submission of shop drawings, repeated submission of non-coordinated shop
drawings or repeated amendment of same due to inadequate, incomplete or inaccurate details and information shall
not be recognized as a reason for extension of time.
Regards
DESCRIPTION:
Attachment:'34 pages A3 size " Shopdrawing steel door of the apartment – Tower (Floor4-Roof)”.
”.
This review is for conformance with the general design concept and for general expressed in the documents. Review shall not be construed to mean that
the reviewer accepts the detail calculations and dimensions shown in the shop drawings or any deviation from the requirements of the contract
documents. Contractor is responsible for errors and omissions in the shop drawings; for meeting all requirements of the contract documents; for
confirming and correlating job site dimensions; for information that pertains solely to fabrication process or to techniques of construction, and for the
coordination of the work of all trades. It is understood that the notation on the submittal is not to be construed as an authorization for additional work or
additional cost.
1. There are some mistakes need to be captured accordingly.
_______________________________________________________________________________________________________________________________
2. Grouting for door facing to outdoor area must be mixed with waterproof additive
_______________________________________________________________________________________________________________________________
3. Silicone to be weather resistant, non-shrink, non-staining type
4. Refer to comments on the cover page ref "Z2.RFA.ARC.SDW.068.REV02_RSP" and comments on
_______________________________________________________________________________________________________________________________
CL RSP TWA JRP CIDECO That’s ITH La Terra VinaQS Green Viet
Tien Dat
25
25
25
RSP: Lever handle with
round rosette, NO KEY,
install at every 4 floors
916.96.014
this door can
omit handle
outside
916.96.314