OBJECTIVE
Strain Insulator
❑ Increase Strength
❑ Balance Tension
2
DUTY OF GUYS
1. Terminal guys
Dead-End Tap-Line
Terminal guys is used for receive tension from Dead-End,
Tap-Line or pole that line deflection Angle over 60º
3
2. Side guys
2-3 km
Anchor guys
8
Guy Type
Stub guys
9
Guy Type
Pole guys
8 m long
10
Guy for overhead
ground wire
11
Installation instructions for guying
12
Installation instructions for guying
13
Installation instructions for guying
14
For Distribution System
Strain Insulator
GY: Guys
2 : Distribution System
1 :Type 1
Strain Insulator
16
For Distribution and Low voltage Distribution System on Same pole
Strain Insulator
Low voltage
across Guys
17
For Distribution and Low voltage Distribution System on Same pole
Strain Insulator
18
Tie Method
19
20
Line guys
1 Feeder 2 Feeder
22
Guys Sizing (LV)
23
Guys Sizing (HV)
24