Rev Date Reason for Issue – Revision Description Prepared Checked Approved
METHOD STATEMENT FOR CABLE TRENCH TCM Identification Code
TABLE OF CONTENTS
1. PURPOSE...................................................................................................................................... 2
2. SCOPE........................................................................................................................................... 3
3. DEFINITION & ABBREVIATION....................................................................................................3
3.1 DEFINITION................................................................................................................................... 3
3.2 ABBREVIATION............................................................................................................................. 3
4. REFERENCES:.............................................................................................................................. 4
5. RESOURCES:................................................................................................................................ 5
5.1 MANPOWER.................................................................................................................................. 5
5.2 EQUIPMENT & TOOLS.................................................................................................................5
6. RESPONSIBILITY AND ATHOURITY............................................................................................6
7. METHODOLOGY AND WORK PROCEDURE:..............................................................................7
7.1 GENERAL:..................................................................................................................................... 7
7.2 EXCAVATION OF CABLE TRENCH (EU2 SUBSTATION TO DOSING SKID):...........................8
7.3 EXCAVATION OF CABLE TRENCH (EU2 SUBSTATION TO NEW QC LAB):............................8
7.4 BACKFILLING AND REINSTATEMENT WORKS:.......................................................................9
8. QA/QC REQUIREMENTS............................................................................................................ 10
9. HEALTH, SAFETY & ENVIRONMENT (HSE) REQUIREMENTS................................................10
9.1 HEALTH:...................................................................................................................................... 10
9.2 SAFETY:...................................................................................................................................... 10
9.3 ENVIRONMENT:.......................................................................................................................... 10
9.4 COMPLIANCE:............................................................................................................................ 10
9.5 PROTECTIVE MEASURES:........................................................................................................ 11
9.6 HSE INDUCTION:........................................................................................................................ 11
10. ATTACHMENTS.......................................................................................................................... 11
10.1 QC LABORATORY EXPANSION UNDERGROUND CABLE ROUTING LAYOUT....................11
10.2 B2 EU2 CABLE ROUTING LAYOUT...........................................................................................11
10.3 JSA.............................................................................................................................................. 11
1. Purpose
METHOD STATEMENT FOR CABLE TRENCH TCM Identification Code
The purpose of this method statement is to define the work procedure for Civil Works and to ensure
required safety & quality aspects during the execution of the works for the civil works at B2 EU2
Substation (Brown field) in full compliance to Borouge 4 Project Specifications & Requirements.
2. Scope
This method statement is covers the Methodology intended to outline how “IMECO” will be executing
activities such as but not limited to Cable Trench Excavation, backfilling & reinstatement works at B2 EU2
Substation to Dosing Skid and New QC Lab Transformer respectfully.
3.1 Definition
3.2 Abbreviation
4. References:
5. Resources:
5.1 Manpower
at site as required.
All the Tools &Equipment deployed for the Project shall be duly inspected by competent
authorities as required and approved by Borouge appointed competent authorities prior to
mobilization to Site.
Project Manager shall be responsible to ensure that all Construction / Site activities shall be within the
agreed timeframe of the project schedule. He shall also be responsible to arrange and ensure the all-
procurement agreements and other administrational/official documents are approved by the Company
prior to any relevant activity.
Construction Manager will plan and resource the manpower, materials & equipment to be used in this
project. He will coordinate with the EE regarding execution of all the works for the entire duration of the
project.
METHOD STATEMENT FOR CABLE TRENCH TCM Identification Code
Planning Engineer shall report to project manager and shall be responsible for the overall evaluation and
control of the project schedules and performs schedule development, maintenance and monitoring of
the planning/scheduling activities with minimal or no supervisory oversight.
QA/QC Engineer - shall reports to the Construction manager, with all quality related aspects with regards
to this project. He is responsible for developing the project Quality Control Plan for the project in
Compliance with Company specifications and requirements. He shall be responsible for ensuring that the
approved Project Quality Plan is effectively implemented in the contract and the inspection and test
results are properly documented. He shall verify and ensure that quality records are being documented
accordingly.
Site Engineer shall report to the Construction manager, The Site Engineer will be responsible for
monitoring and controlling of all the construction activities, he shall report to the Construction manager.
Supervisor will direct all manpower on site receiving instructions from the Civil Engineer for all the
activities.
HSE Engineer shall reports to the Project manager and coordinates with HSE Manager. He shall ensure
that the HSE system and procedures are strictly respected and followed on-site. He shall be responsible
for the necessary training of all personnel and communication of matters affecting Health, Safety and
Environment. He shall develop and institute control and remedial measures for hazardous and potentially
hazardous conditions or equipment or activity, as per Hazard Analysis and Risk Assessment procedures.
He shall be directly responsible for monitoring the project for compliance of HSE requirements as per
approved HSE plan and HSE implementation program.
HSE Officer reports to the HSE Engineer on all HSE aspects with regards to this project and shall ensure
that the HSE system and procedures are followed on-site. He shall be responsible for the necessary
training of all personnel on matters affecting Health, Safety and Environment as per HSE Engineer.
Document Controller shall report to the Project Manager is mainly responsible for maintaining and
managing project related documentation such as technical documents, drawings, correspondence etc. He
shall ensure project documentation is appropriately logged, stored and easily traceable & accessible. He
shall ensure controlled copies of latest approved documents and drawings are distributed to the required
staff, Company, consultant & subcontractors.
Storekeeper shall be responsible for overseeing the proper storage and control of all material from the
suppliers. He shall coordinate all storekeeping related activities and keep track of all assets, tools and
inventory through effective documentation as per procedure.
METHOD STATEMENT FOR CABLE TRENCH TCM Identification Code
7.1 General:
The necessary work permit shall be obtained from concerned authorities prior to start of any work at site.
Proper access shall be maintained to all the working area through-out the execution of job.
All the latest revisions of all IFC Drawings to be made available at site.
The line and location of existing cable trench shall be marked by Surveyor.
Risk assessment shall be done to ensure that all the hazards involved are identified, risk assessed and
control measures are put in place.
Working Personnel should have work related PPE.
Conduct and record Tool box talk (TBT) prior to commencement of the activity.
Excavation area shall be surveyed and marked to the excavation lines as per the Approved IFC drawing.
Existing facilities, if any shall be protected / or covered properly prior to start work.
Temporary barricading will be provided all around the cable trench and warning lights shall be fixed all
around trench.
METHOD STATEMENT FOR CABLE TRENCH TCM Identification Code
Warning Tape Written “Caution Electrical Cable” will be placed on top of cable tiles all along the cable
route in line with COMPANY standard drawing.
Cable Route Markers Post will be installed in the cable route at intervals of 25mtrs & diversions as per
standard procedure.
Damaged precast cover slab will be repaired or replaced with new one as per Company approval.
Joints between existing precast cover slab will be filled with approved sealant.
Color coding for Covers to be followed.
Reinstatement of demolished Concrete slab shall be done per approved Site Inspection and Test Plan
for Civil Works-PU-CC-474-00103
Reinstatement of interlocking shall be done as per approved Site Inspection and Test Plan for Civil
Works-PU-CC-474-00103
On completion of the works, all tools, equipment and surplus materials shall be removed from site
and all work areas reinstated to the satisfaction of COMPANY.
8. QA/QC Requirements
Site management, Site Engineer, QA/QC Engineer and Safety Officer will closely supervise and monitor
all phases of the work to ensure full compliance with the procedures and safe methods of working.
Inspection and test shall be carried out in accordance with the approved procedures and in accordance
with the project specification.
To perform all activities related to the project in such a way to avoid any harm to the health of
employees and subcontractors.
To promote general hygiene practices in the normal life.
To provide a well-defined medical care attention to each employee working in the project
9.2 Safety:
To provide a safe work environment by well-defined procedures and its strict Implementation.
Zero Lost Time Accidents.
To conduct adequate trainings to have a better safety awareness on work related activities.
Encourage Near Miss reporting and incident evaluations.
Comply with all applicable U.A.E. laws and regulations.
Identify hazards and reduce risks to an acceptable level as per project standards.
A minimum of one safety inspection of the working areas must be performed per week.
9.3 Environment:
To implement Reduce, Reuse and Replace policy in overall waste management.
Proper segregation and storing of wastes materials generated by the project activity.
METHOD STATEMENT FOR CABLE TRENCH TCM Identification Code
9.4 Compliance:
All the works should comply with this method statement and follow the rules and guidelines as set
out in the approved HSE plan.
Contractor to keep COMPANY fully informed at all times of any issues regarding HSE.
Ensure that personnel are trained in:
Health, Safety & Environmental Requirements and Regulations
Potential Risks and Impacts
Protection Measures
PPE Usage
Contractor shall provide as a minimum HSE induction training for all its employees involved in the
Project in addition to mandatory COMPANY HSE induction. Contractor induction will cover the
following as minimum-
HSE Policy.
Plant/location hazards.
H2S.
Work related hazards controls.
Emergency evacuation procedure.
Duties and responsibility.
DO’s and DON’TS in the plant and work site.
Usage of PPEs.
10. ATTACHMENTS
10.3 JSA