Professional Documents
Culture Documents
Client: OQ
Contractor: Arabian Industries Projects L.L.C
Ref. Point in
Comment from OQ Amran response OQ Reply Status
document
TR unit rating shall be 48V/50A as We confirm and document revised
Page 21 of 44
confirmed in TBE accordingly
TR unit rating shall be 48V/50A as We confirm and document revised
Page 21 of 44
confirmed in TBE accordingly
Header cables size from TR unit to AJB
Page 26 of 44 and NDB (positive and negative) shall be Noted and incorporated
70 mm2 because the rating of TR is
48V/50A
7 number of anodes shall be provided
Page 28 of 44 each with 8A rating as per TBE Noted and incorporated
confirmation
Page 30 of 44 Cable size shall be 10 mm2 Noted and incorporated
Consultant Name -
PO Number: WO #: 14-220000733-01
A CONSENT TO PROCEED
PERMANENT CATHODIC
PROTECTION DESIGN
OQ EXPLORATION & PRODUCTION
REPORT- 24" CS PIPELINE
LLC FROM PW MANIFOLD TO
INTERMEDIATE STATION
Location : BISAT
PRODUCED WATER DISPOSAL
Structure :
PIPELINE
Amran Cathodic Protection Systems & Services LLC | PO Box: 919 | PC: 100 | Muscat | Sultanate of Oman
AMRAN CPSS L.L.C OQ EXPLORATION & PRODUCTION
PERMANENT CATHODIC PROTECTION DESIGN ARABIAN INDUSTRIES PROJECTS LLC
REPORT- PRODUCED WATER DISPOSAL PIPELINE CATHODIC PROTECTION SYSTEM - BISAT AREA
AMRAN JOB NO. 2988 DEVELOPMENT PHASE II PROJECT
REVISION RECORD
TABLE OF CONTENTS
1. PROJECT DETAILS
2. SCOPE OF WORK
3. SCOPE OF DOCUMENT
Corrosion protection of the external surface of the pipeline shall be provided with high integrity coating systems,
supplemented by cathodic protection.
The intent of this document is to provide the design basis and engineering calculation of permanent cathodic
protection system for buried pipelines which shall include but not limited to the Design philosophy, assumptions
and calculations for pipelines, and bill of materials.
The following definitions and abbreviations have been used in this document:
TECHNICAL:
TERMINOLOGY DESCRIPTION
Alternating voltages and currents induced to on a structure because of the AC power
AC Exposure
system
Alternating Current Alternating Current is an electrical quantity whose direction changes with time
Anode An electrode, placed in the electrolyte, to apply cathodic protection to the structure
Material placed in a cotton bag to fill the space around the permanent reference
Backfill
electrode of a cathodic protection system.
Cable One conductor or multiple conductors insulated from one another.
Cathodic The destruction of adhesion between a coating and the coated surface caused by
Disbondment products of a cathodic reaction.
The prevention or reduction of corrosion of metal by making the metal the cathode in
Cathodic Protection
a galvanic or electrolytic cell
A liquid, liquefiable or mastic composition that after application to a surface is
Coating
converted into a solid protective, decorative or functional adherent film.
TERMINOLOGY DESCRIPTION
A connection, usually metallic, that provides electrical continuity between structures
Continuity Bond
that can conduct electricity.
The deterioration of metal caused by its electrochemical reaction with its
Corrosion
environment
The potential of a corroding surface in an electrolyte relative to a reference electrode
Corrosion Potential under open-circuit conditions (also known as rest potential, open-circuit potential, or
freely corroding potential)
The associate of two or more circuits or systems in such a way that energy may be
Coupling
transferred from one to another
Current Density Current flowing into the cathode divided by cathode surface area
Direct Current Current whose direction does not change with time.
Location of the negative cable connection to the protected structure through which
Drain Point
the protective current return to its source
The condition of being electrically separated from other metallic structures or the
Electrical Isolation
environment.
A liquid, or the liquid component in a composite material such as soil, in which
Electrolyte
electric current may flow by ionic charge transfer
Any metallic structure that is not intended as a part of a system under cathodic
Foreign Structure
protection.
A metal that provides sacrificial protection to another metal that is more noble when
Galvanic Anode
electrically coupled in an electrolyte.
One or more anodes installed below the earth’s surface for the purpose of supplying
Ground Bed
cathodic protection.
Metallic Short Direct or indirect metallic contact between two metallic structures
“ON” Potential Electrical potential measured while cathodic protection system is operating.
TERMINOLOGY DESCRIPTION
The change from the open-circuit potential as a result of current across the
Polarization
electrode/electrolyte interface.
The potential across the structure/electrolyte interface that is the sum of the
Polarized Potential
corrosion potential and the cathodic polarization
The surface to electrolyte potential of a structure measured in Volts, with respect to a
Potential
reference cell, unless specifically stated otherwise.
The structure-to-electrolyte potential measured after application of cathodic
Protected Potential
protection
A device for converting alternating current to direct current. Usually includes a step-
Rectifier down AC transformer, a silicon or selenium stack (rectifying elements), meters, and
other accessories when used for cathodic protection purposes.
An electrode that has a stable potential in one or more electrolytes at a given
Reference
temperature, thus enabling it to be used for the measurement of other electrode
Electrode
potentials
✓ The resistances per unit length of a substance with uniform cross section.
Resistivity ✓ A measure of the ability of an electrolyte (e.g., soil/water) to resist the flow of
electric charge (e.g., CP current)
A condition considered to exist at an accessible part in a circuit between the part and
Shock Hazard ground or other accessible part if the steady-state open-circuit AC voltage is 15V or
more (root mean square - rms)
A conductor of a known electrical resistance through which current flow may be
Shunt determined by measurement of the voltage across the conductor and calculation
using Ohm’s Law.
Structure A metal which has a surface in contact with an electrolyte
Structure to The potential difference between the surface of a buried or submerged metallic
Electrolyte structure and electrolyte that is measured with reference to an electrode in contact
Potential with the electrolyte.
An electrically conductive wire or cable attached to a structure and terminated in a
Test Lead test station. It is used for the measurement of structure-to-electrolyte potentials and
other measurements.
Test Point / Station A small enclosure or housing that is the termination point of one or more test leads
Maximum value of electric current through a body of a person which that person can
Threshold Current
release himself or herself
Transformer
An electrical unit which converts input alternating current to direct current output.
Rectifier
An electromotive force, or a difference in electrode potentials expressed in volts.
Voltage
Also known as a potential.
ABBREVIATIONS:
TERM DEFINITION
A Ampere
AC Alternating Current
TERM DEFINITION
BS British Standard
CD Current Density
CP Cathodic Protection
CS Carbon Steel
°C Degree Centigrade
DC Direct Current
DP Drain Point
HV High Voltage
IF Insulating Flange
IJ Isolation Joint
IS Isolation Spool
kg Kilogram
km Kilometer
LV Low Voltage
mm Milli Meter
mV Milli-volts
TERM DEFINITION
OD Outer Diameter
PE Polyethylene
P/L Pipeline
RP Recommended Practice
SP Engineering Specification
TR Transformer Rectifier
TS Test facility
V Voltage
DOCUMENT DESCRIPTION
SCOPE OF WORK
BST-12-PPL-MAP-WPO-614-00002- Key Plan - Proposed 24" CS-PERT Lined Water Disposal Main Header
01-U Rev.02 #1 from Bisat PW M/F to Intermediate Station
BST-12-PPL-ALN-WPO-614-00003-
Pipeline Alignment Sheets - Proposed 24" CS-PERT Lined Water
01-U Rev.02 to BST-12-PPL-ALN-
Disposal Main Header #1 from Bisat PW M/F to Intermediate Station
WPO-614-00003-04-U Rev.02
BST-12-PPL-LAY-WPO-614-00001- Pipeline Station Approach Drawing – Proposed 24" CS-PERT Lined
01-U Rev.02 MH #1 and 10” CS-PERT Lined PW Pipeline at Bisat Station
BST-12-PPL-LAY-WPO-614-00002- Pipeline Station Approach Drawing – Proposed 24" CS-PERT Lined
01-U Rev.02 MH #1 and Sub Header #1/ #2 at Intermediate Manifold Station
DOCUMENT DESCRIPTION
BST-GEN-CRR-RPT-AIP-10003- Pre-Design Site Survey Report 24" CS pipeline PW manifold to
10001-00 Intermediate station
BST-GEN-CRR-RPT-AIP-10003- Temporary Cathodic Protection Design Report- 24" CS pipeline PW
10002-00 manifold to Intermediate station
BST-GEN-CRR-RPT-AIP-10003- Permanent Cathodic Protection Design Report- 24" CS pipeline PW
10003-00 manifold to Intermediate station
BST-GEN-CRR-RPT-AIP-10003- Commissioning Report for CP system of 24" CS pipeline PW manifold
10004-00 to Intermediate station
BST-GEN-CNS-MOS-AIP-10003- Method Statement for Installation, Testing & Commissioning of CP
10001-00 System
BST-GEN-CRR-DAS-AIP-10003-
Material Data Sheets - Cathodic Protection Equipment
10001-00
BST-GEN-QAC-PLN-AIP-10003-
Inspection & Test Plan for Cathodic Protection System
10004-00
BST-GEN-QAC-PCD-AIP-10003-
Factory Acceptance Test (FAT) Procedure - CP TR unit
10002-00
BST-GEN-CRR-DTL-AIP-10003-
Detail Drawing -Welded Pad Cable Connection & Encapsulation
10001-00
BST-GEN-CRR-DTL-AIP-10003-
Detail Drawing - Pin Brazing Cable Connection & Encapsulation
10002-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Details - Cable Trench
10003-00
BST-GEN-CRR-DTL-AIP-10003-
Detail Drawing - Standard CP Test Post
10004-00
BST-GEN-CRR-DTL-AIP-10003-
Detail Drawing - CP Marker Plate
10005-00
BST-GEN-CRR-DTL-AIP-10003-
Detail Drawing - General Purpose Bond Box
10006-00
BST-GEN-CRR-DTL-AIP-10003- Installation Drawing - Potential Monitoring Test Facility with Mg Anode
10007-00 (TP1A)
BST-GEN-CRR-DTL-AIP-10003-
Installation Drawing - Isolation Spool Test Facility (Type-3)
10008-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Drawing - Drain Point with & CU (Type-2)
10009-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Drawing - Foreign Service Test Facility (Type-5)
10010-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Drawing - OHL Crossing Test Facility (Type-7) -
10011-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Drawing - Road Crossing Test Facility (Type-6) -
10012-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Details-Negative Distribution Box
10013-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Details- Anode Junction Box
10014-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Details- Anode Ground Bed Installation
10015-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Details- Anode Ground Bed Head Works
10016-00
BST-GEN-CRR-DTL-AIP-10003-
Installation Details - Transformer Rectifier (TR) Unit
10017-00
BST-GEN-CRR-DTL-AIP-10003-
Circuit Diagram for Transformer Rectifier Unit
10018-00
DOCUMENT DESCRIPTION
BST-GEN-CRR-DTL-AIP-10003- CP Appurtenance Drawing - 24" CS pipeline PW manifold to
10019-00 Intermediate station
BST-GEN-CRR-GAR-AIP-10003-
General Arrangement Drawing for CP Equipment at RMS-1
10001-00
BST-GEN-CRR-LAY-AIP-10003-
Schematic Layout - Cathodic Protection System
10001-00
ASTM Standards
ASTM B843 Standard Specification for Magnesium Alloy Anodes for Cathodic Protection
NACE SP0169 Control of External Corrosion of U/G or Submerged Metallic Piping System
NACE SP0177 Mitigation of Alternating Current and Lightning Effects on Metallic Piping System
British Standard
BS 7361 Part 1 Cathodic protection Part 1, Code of Practice for Land and Marine Application
Shell Standards
6. STRUCTURE DETAILS
TECHNICAL DETAILS
The technical detail of proposed new buried water disposal pipeline can be listed as:
The design strategy followed for permanent ICCP system for subject pipeline is enumerated below:
• All buried sections of pipeline shall be protected using permanent impressed current CP system.
• Design life for the impressed current cathodic protection system shall be 25 years as per SOW.
• Mixed Metal Oxide (MMO) tubular anodes in coke breeze column shall be used as impressed current anode
for permanent ICCP system.
• Considering the high surface resistivity prevalent in the region, deep well ground beds (borehole type - until
the existing water table) is proposed for the pipeline CP system which shall be remote from the structure to
be protected.
• Remote deep well anode ground beds shall be provided at Produced Water Manifold station to provide
permanent impressed current cathodic protection to the 24” CS pipelines subjected to Produced Water
Manifold station. The requirement of the CP systems has been discussed in the site survey report BST-
GEN-CRR-RPT-AIP-10003-10001-00. The same shall be verified with detailed calculation in the preceding
sections.
• Impressed current anode bed shall be sized as a minimum to discharge the rated current output of the DC
power source.
• Cathodic protection current shall be injected to the anodes through following arrangements: DC power
source→ Anode junction box →Anodes→ Pipeline → Negative Distribution Box →DC power source.
• NDB shall be installed in between the transformer rectifier unit and pipeline. The current drain cable from
the pipeline to transformer rectifier unit shall be routed through negative distribution box.
• Material of construction of AJB, NJB & NDB enclosures shall be SS 316L with a minimum ingress protection
of IP55 and shall be suitable for safe area application.
• Material of construction of bond boxes shall be SS 316L with an ingress protection of IP55 and shall be
suitable for installation in non-classified areas.
• Anode junction box is designed to terminate the anode lead cables with suitable rated shunt for current
measurement.
• The designed active column length is 40 meters considering a spacing 5 meters between anode-to-anode
centres below the water table.
• Potential monitoring test facility shall be provided at every 2 km for proposed pipeline .
• Cable to proposed pipeline connection (monitoring and negative drain connection) shall be achieved by
welded pad / cleats connection. Encapsulation at cable connection location shall be done using two-part
epoxy.
• Cable to existing buried metallic pipeline connection (at P/L crossing locations) shall be achieved by pin
brazing. Encapsulation at cable connection location shall be done using two-part epoxy.
• Test facility shall be provided at metallic foreign pipeline crossing locations identified during site survey.
However, interference and mitigation requirement shall be evaluated and employed during the
commissioning of the system, if required.
• At road crossing locations, CP test station shall be provided on one side of the crossing as minimum.
• Test stations with coupon test facility shall be installed at drain points of the pipeline.
• Test post with bond box for isolation flange & drain point test facility shall be provided at produced water
manifold station of the pipeline to analyse the integrity of the isolation flange and measure the drain point
potential of the pipeline.
• Surge diverter/ spark gap shall be provided across isolation flange as available produced water manifold
Station and intermediate manifold station to protect the isolation flange from the surge AC and lightning
strike on the pipeline.
• DC power sources (TR units) shall be installed at Produced Water Manifold Station. The TR units shall be
oil cooled type suitable for outdoor installation. The cabinet shall have ingress protection of a minimum of
IP66. The TR unit shall be suitable for installation in non-hazardous location and shall be placed
accordingly.
The criteria for determining the adequacy of the protection of structure shall be as per clause 3.3. of CP SOW
doc# BST-GEN-ELE-SOW-OQ-000-00001-00-U-01. Adequate cathodic protection for the 24” CS Pert Lined
produced water disposal pipeline as below:
• Impressed current cathodic protection (ICCP) system shall be designed such that instantaneous “OFF”
potentials can be measured. The system shall be designed to achieve minimum structure-to-electrolyte
“Instant OFF” potential of (-) 850 mV with respect to copper-copper sulphate (Cu/CuSO4) reference
electrode.
• ICCP system will be designed in such a way that maximum “Instant OFF” potential shall be restricted to (-)
1200 mV to avoid over protection of DSS structure. The potentials shall be recorded w.r.t. a saturated
copper-copper sulphate (Cu/CuSO4) reference electrode.
• Alternatively, (Ref: NACE RP 0169 clause no 6.2.2.1.3), a minimum of 100 mV of cathodic polarization
measured between the pipeline surface and a stable reference electrode contacting the electrolyte shall be
considered as an adequate protection. The formation or decay of polarization shall be measured to satisfy
this criterion.
The following section outlines the design calculations for permanent impressed current cathodic protection for
the Produced Water Manifold Station pipeline 24” CS from Produced Water Manifold Station Intermediate
Manifold Station. The detailed ICCP calculation is attached in Appendix-C.
= 8139.24 m2
60 − 30
=0.01 × 1 . 25 10
= 0.02 mA/m2
CURRENT DEMAND
𝑺𝒂,𝒄 × 𝒊𝒄𝒑 , 𝑻
ICP = ⁄
𝟏𝟎𝟎𝟎 ------------------------------- (3)
= 8139.24 x 0.02 /1000
= 0.16 A
= 0.16 x 1.3
= 0.21 A
Polarization
where
0 - Pipeline potential at drain point (V)
min
0 - Minimum protected potential (V)
R’
s …………………….(4)
= (Ω/m)
2 r t
Where
= 1 (S/m2) …………………….(5)
g RC
Where
G’ = ( g 2 r ) (S/m) …………………….(6)
Where
Attenuation Constant
=
R' G' (1/m)
…………………….(7)
Z = …………………….(8)
R' / G' (Ω)
The polarization of pipeline at location ‘x’ from the source, when connected to an anode through a DC power
source, is given by the following expression
E
= Em cosh[L] (V) …………………………….(13)
0
I0 = E0
(A) ……… …………………...(16)
Z coth[L]
Where
- Attenuation constant
References
1. Von Baeckmann, V., Schwenk, W., and Prince, W., Handbook of Cathodic Corrosion protection Third
Edition [All Equations]
has the primary assumption of looking into an infinite resistance on one end which is essential an electrical
isolation.
As per NACE CP4 manual, a net potential shift of 350 mV at any point on the pipeline shall be sufficient to
polarize the pipeline cathodically meeting the criterion above and thus effectively mitigate corrosion.
The maximum and minimum anticipated shifts in potentials are given by the CP criteria under Section 7.2 of
this document. The maximum protection potential criterion for CS pipeline (i.e., a 1200 mV in the electro
negative direction when measured w.r.t. to a portable Cu/CuSO4 reference cell) is impressed on the pipeline
at the drain point, attenuated along the length of the pipeline.
= -0.50 – (- 1.2)
= 0.7 V
= -0.50 – (-0.850)
= 0.350 V
CP station shall be installed at Produced Water Manifold Station. The attenuation model shall be developed
along these CS pipeline as detailed in Appendix–D
Below section shows the typical attenuation model for 24” diameter pipeline from Produced Water Manifold
Station to Intermediate Manifold Station
= 1/30000
Attenuation Constant,
= R' G' from (7)
=
√(6.389 E -05) × (8.432 E -06)
= 2.32104 x 10-5 /m
Polarization at end of pipeline due to drain point at one end at which a potential of 1050 mv (500 mV natural
potential + 550 mV of polarization) is applied.
Em = 1050 mV
The attenuation model for the 24” produced water pipeline 4250 meters is calculated with 1 number of CP
station (ICCP ground bed and power source) at produced water manifold station.
The attenuation constant above has been used for the water disposal pipeline since this is represents the
worst condition.
Considering the attenuation calculation and over all current demand, it is understood that, the proposed ground
bed at Produced Water manifold station is sufficient to supply adequate current to the proposed pipeline to
meet the design criteria as mentioned in section 7.2.
The attenuation model shall be developed along proposed water disposal pipeline as detailed in Appendix-C
of this document.
Therefore, the proposed ground bed locations are effectively protecting the entire length of pipeline and
satisfies the ICCP design requirements as per section 7.2 of this document.
The Overall pipe to soil potential profile graph is provided under Appendix-C
Considering the total current requirement for the proposed pipeline is 0.21 A. The proposed CP station shall
be installed at produced water manifold station.
Considering the current requirement for the anticipated future pipeline, the transformer rectifier unit rating shall
be proposed as 48V/50A.
TR Unit Rating
Pipeline ID Proposed Location Chainage (KP)
(Proposed)
General
The design of anode ground bed shall ensure sufficient quantity of anode material and carbonaceous backfill
to meet or exceed the design life time. A utilization factor of 75% is applied over the design to ensure time for
replacement or refurbishment of the system, towards the end of design life, if required. The quantities shall be
calculated on the basis that the maximum CP unit rated current output is impressed for the entire duration of
the design life.
The anode active column and the constituents like dimensionally stable anodes, calcined petroleum coke are
chosen and designed such that the current densities on the anode and that on the active column are within
the limits set forth by manufacturer:
Description Specification
Anode Length, La 1m
Utilization Factor, Uf
(The maximum quantity of backfill that 75 %
will be used up, in the design life
period)
I
N = d a L a A ----------------------------- (18)
Where
N = Number of anodes required
I = Rated current output (A)
da= Diameter of anode (m)
La=Anode length (m)
ϒ= Maximum Anode Current Density (A/m2)
= 6.3
≈ 7 No. of Anodes
Hence the active column of the deep well bed shall be constructed with a minimum of 7 no’s anodes spaced
5m equidistant from each other along the 40 m depth, backfilled with calcined petroleum coke.
It is necessary to ensure that the designed coke breeze quantity shall also be sufficient for the minimum rated
current output based on consumption rate and also based on the dimensions of the active column chosen. It
shall be estimated using the following equations.
Based on ground bed dimensions, the minimum quantity of coke breeze required, is given by
d 2 L B
WCB = (kg) …………………..(19)
4
Where
= 2326.742 kg
= 2500 kg
However, 2500 kg of calcined petroleum coke shall be considered to account for spillage, diffusion into the
water table and ensure good compaction in the active column. This quantity shall be verified against the
consumption rate.
I t Cr
WCB = (Kg) ………………………..(20)
Uf
Where
= 1666.667 kg
Hence, the 1666.667 kg of calcined petroleum coke shall be required based upon the consumption rate.
Therefore,2500 kg of calcined petroleum coke shall be considered to be supplied to account for spillage,
diffusion into the water table and ensure good compaction in the active column.
+
RC,
- RC,
N
Ground
PL
bed
RP
RAE
Remote Earth
Generally, the surface of pipeline in contact with Remote Earth is very large yielding a very negligible
resistance. Therefore, the above equation reduces to
Where
Vertical remote deep ground bed is proposed to cathodically protect the subject pipeline. The depth of the
borehole shall be fixed at site as per the water table depth during drilling. The active column length and
diameter of the ground bed shall be 40 m and 0.25 m respectively.
The active column length (40 m) shall be drilled from the first water strike observed during drilling, so as to
ensure the active column being completely immersed into the water table at all time. The length of the active
column, in addition to the factors discussed earlier (current density on active column and the backfill quantity
required) is also dependent on the anode to earth resistance. It is advisable to maintain the resistance of active
column, around 1 ohm, during the design stage to ensure effective utilization of power and reduce electrolytic
stress on the anode-electrolyte interface.
The water resistivity for ground bed resistance calculations shall be assumed, contingently, as 10 Ωm, as the
anodes are installed in the water table depth.
Anode ground bed to earth resistance (RAE) for vertical ground bed is determined using Modified Dwight
Equation
𝜌 4𝐿𝐴𝐶
(𝑙𝑛 ( ) − 1) (Ω)
RAE = 2𝜋𝐿𝐴𝐶 𝑑𝐴𝐶
----------------------------------------(23)
Where
• The positive and negative header cable (from DC power source to anode junction box and negative
distribution box) shall be single core 70mm2 XLPE/ PVC cable.
• The average length of positive header cable (from CP DC power source to anode junction box) shall be 100
m approximately.
• Anode tail cables shall be single core 16 mm2 PVDF/HMWPE (Kynar) with max. length of 90 m. Total
number of anode tail cables at anode junction box shall be 7 No.
• The length of negative drain cable from pipeline to negative distribution box shall be approximately 15m.
• The negative cable (from NDB to DC power source) shall be average of 50 m.
R = 0.217 + 0.0590
R = 0.276 Ω
V = ( From 24)
50 X 0.276 + 2
= 15.82 V
An allowance of 2.0 V shall be considered to overcome the back EMF of the CP circuit as an electrochemical
cell formed between the anode and the pipeline. Hence, the minimum rated output voltage of DC power source
shall be 48 V.
The proposed maximum rating of cathodic protection DC power source shall be 48 V / 50 A. The proposed TR
unit rating can cater the current requirement for the 24” CS pert water disposal pipeline and the future pipelines
as mentioned in the SOW. Therefore, the designed TR unit rating is sufficient to achieve the design criteria for
the proposed & future pipeline.
Allowable resistance = (Rated Output Voltage – Back EMF) / Rated Output Current
= (48 –2) / 50
= 0.920 Ohm
The combined anode to earth resistance shall be 0.217 ohm and the total circuit resistance shall not exceed
0.920 ohm.
48 × 50⁄
P = 0.75 X 1000…………………………….. From (25)
= 3.20 kW
95/8” CS Casing
: 40 m
(Active Column
APPENDIX – A
BILL OF MATERIALS
ITEM
DESCRIPTION TOTAL QUANTITY UNIT
NO.
Standard Test Post with Bond Box –Isolation Joint & Drain
Point Test Facility, Type-2
Salient features of test post:
1. Material – Galvanized Iron (GI)
2. Length- 2250 mm
3. Dia. – 4 inches
3. Salient features of bond box: 1 No.
1. Enclosure – Stainless Steel
2. IP rating – IP55
3. Size: 300 x 300 x 150 (mm)
4. Reed switch and magnet
5. No. of terminals- 8
ITEM
DESCRIPTION TOTAL QUANTITY UNIT
NO.
Black 230 m
Red 170 m
ITEM
DESCRIPTION TOTAL QUANTITY UNIT
NO.
Surge Diverter
9. 1. Model: EXFSKU 2 No.
2. Design current: 100 KA
Miscellaneous Items
1. Cable lugs-
• 70mm2 /M10 – 2 No.
• 10mm2 /M10 – 15 No.
10. 1 Lot
2. Cable ties- 2 packet (small)
3. Silicone sealant – 3 tubes
4. M10 GI nut bolt & washers- 10 No.
5. M6 GI nut bolt & washers for box fixing- 10 Set
Buried Coupon
1. Enclosure: PVC
2. Exposed metal surface: 75 mm x 75 mm
20. 1 No
3. Material – CS
4. Lead cable: 2 No. of single core 10 mm2 Cu/XLPE/PVC Red cable -
10m long tail cable for each
BILL OF MATERIALS FOR FOREIGN LINE CROSSINGS OF 24”CS PRODUCED WATER PIPELINE
ITEM TOTAL
DESCRIPTION UNIT
NO. QUANTITY
Black 24 m
Red 24 m
BILL OF MATERIALS FOR FOREIGN LINE CROSSINGS OF 24”CS PRODUCED WATER PIPELINE
ITEM TOTAL
DESCRIPTION UNIT
NO. QUANTITY
Miscellaneous Items
1. Cable lugs-
• 16mm2 /M10 – 6 No
• 10mm2 /M10 – 6 No.
4. 1 Lot
2. Cable ties- 1 packet (small)
3. Silicone sealant – 1 tube
4. M10 GI nut bolt & washers- 10 Set
5. M6 GI nut bolt & washers for box fixing- 10 Set
APPENDIX – B
DESIGN CALCULATIONS-PCP
Appendix - C
Title : PERMANENT CATHODIC PROTECTION DESIGN REPORT - 24" CS PIPELINE PW MANIFOLD TO INTERMEDIATE STATION
PW M/F TO
24" CS-Pert Lined Produced
1 INTERMEDIATE M/F 3LPP 24 0.6096 4250 8139.24 0.01 60 0.02 0.16 0.21
water disposal pipeline
STATION
Total 0.21
P2988-REP-001
BISAT PHASE II DEVELOPMENT PROJECT
RC,N
Company : OQ Exploration & Production LLC Anode Material
RC,P
Mixed Metal Oxide / Titanium
Off plot Contractor : Arabian Industries Projects LLC Anode Length 1 m
CP Vendor : Amran Cathodic Protection Systems and Services LLC, Sultanate of Oman Anode Diameter
0.0254 m
Ground bed
Title Permanent Cathodic Protection System - Design Calculations Sheet Max. Current Density (γ A ) PL
: 2
100 A/m
Location : PW M/F TO Intermediate M/F Station for 25 years life of anode Total Resistance in Circuit,
Rated Anode Current Output (Ia) 8A per anode
1 Total Current Requirement Anode Coating Consumption Rate < 1 mg / A-yr R = RAE + RDC + RP
2
Tail Cable 1x16 mm KYNAR
Nominal Max. Current Output
50.00 A
a.
Permanent Cathodic Protection System of Transformer Rectifier Unit (I dc ) Remote Earth
Station ID Current Req. (A) Dia. of Active Column (D AC ) 0.2500 m The voltage rating of the TR unit can be determined by considering the
Length of Active Column (L AC ) 40.000 m total resistance that may occur in the circuit, which is contributed by
Current density on Active Column Anode to Earth Resistance (RAE), DC cable resistance (RC = RC,P + RC,N)
1.592 A/Sqm
PW M/F TO Intermediate M/F Station 0.21 at peak load (i.e., 50A) and Pipeline to Remote Earth Resistance (RP)
Description
b. Refer Appendix - B for detailed Calculations.
(Ω/m)
Run
iii. Minimum Quantity of Backfill Required
W CB = I dc t C r
Kg
U f
= 1666.667 From the Table,
Hence, a minimum of 2500 kg of coke breeze shall be poured down the Hence, R DC = 0.0590 Ω
deep well to ensure sufficient coke breeze quantity.
P2988-REP-002
BISAT PHASE II DEVELOPMENT PROJECT
>> The combined anode to earth resistance shall be around 0.217 Ω and the total
Appendix - C circuit resistance shall not exceed 0.920 Ω, as calculated earlier
V = I dc . R + Back Emf
P = kW
Schematic Sketch of a Typical Deep Well ICCP System
P = 3.20 kW
Required Input VA
kVA
rating = 4.57
4 Conclusion
>> The ground bed shall be 0.25 m in diameter with a length of 40 m for active
column, installed ensuring the first water strike, on the drilled borehole.
P2988-REP-002
AMRAN CPSS L.L.C OQ EXPLORATION & PRODUCTION
PERMANENT CATHODIC PROTECTION DESIGN ARABIAN INDUSTRIES PROJECTS LLC
REPORT- PRODUCED WATER DISPOSAL PIPELINE CATHODIC PROTECTION SYSTEM - BISAT AREA
AMRAN JOB NO. 2988 DEVELOPMENT PHASE II PROJECT
APPENDIX – C
ATTENUATION PROFILE ALONG PIPELINE