DMRC DC-06 PROJECT

ACCESS DATES - KRISHNA PARK EXTN. STATION

S.No. Area / Rooms Access Dates Remarks

1 Completion of 1st ECS Room in the Station 10-Jun-22

2 Completion of track way basic structure for access to track way 12-Sep-22

3 Completion of 2nd ECS 14-Oct-22

4 Completion of 1st TVF 14-Jul-22

5 Completion of 1st ASS 16-Jun-22

6 Completion of 2nd TVF 14-Oct-22

7 Completion of TER, SCR, SER, UPS, GSM, CDMA 15-Sep-22

8 Completion of undercroft, cable duct, cable and other service gallery 14-Oct-22

9 Completion of First EFO, TOM, AFC 28-Sep-22

10 Completion of Civil structure fit for installation of Lift, escalator from Platform to Concourse 14-Oct-22

11 Completion of Second EFO, TOM, AFC 29-Oct-22

12 Completion of Entire works including plumbing, Finishing as per contract 24-Mar-23

13 Completion of all Outstanding works that does'nt affect testing and commissioning 14-Jun-23