Professional Documents
Culture Documents
3X660 MW NKSTPP,
TANDWA, DIST- CHATRA, JHARKHAND.
NAME SIGNATURE
Mr. A K SINGH
PREPARED BY
Mr. C K DUTTA
Page 1 of 7
BHARAT HEAVY ELECTRICALS LIMITED
POWER SECTOR - EASTERN REGION
METHOD STATEMENT OF AIR COOLED CONDENSER AND AUXILIARIES WITH
HANGER SUPPORT ALONG WITH SUPPORTING STRUCTURES ” AT PROJECT SITE
TABLE OF CONTENTS
Sl.
Description Pg. No.
No.
1. Scope
3. Alignment tools
6. Safety measures
Page 2 of 7
BHARAT HEAVY ELECTRICALS LIMITED
POWER SECTOR - EASTERN REGION
METHOD STATEMENT OF AIR COOLED CONDENSER AND AUXILIARIES WITH
HANGER SUPPORT ALONG WITH SUPPORTING STRUCTURES ” AT PROJECT SITE
1. Scope :
The scope includes Pre assembly, Erection and alignment of following major activities
in ACC at project site:
3. Alignment Tools
i. Hook chuke 3/5 ton – 5 nos.
ii. Ratchet 1.5 Ton – 04 nos.
iii. Turn buckle 3/5T – 08 Nos.
iv. Hydraulic/Screw Jack 10 to 50 T – 4 Nos.
Page 4 of 7
BHARAT HEAVY ELECTRICALS LIMITED
POWER SECTOR - EASTERN REGION
METHOD STATEMENT OF AIR COOLED CONDENSER AND AUXILIARIES WITH
HANGER SUPPORT ALONG WITH SUPPORTING STRUCTURES ” AT PROJECT SITE
i) Shifting through suitable capacity crawler mounted/ pick & carry mobile crane.
Erection:
Lifting is to be done by 250MT/350 MT crawler crane at top of concrete
column (+55 m elevation).
Anchor plate is to be fixed with anchor bolts provided at top of concrete.
Alignment:
Necessary packings to be measured and inserted
Page 5 of 7
BHARAT HEAVY ELECTRICALS LIMITED
POWER SECTOR - EASTERN REGION
METHOD STATEMENT OF AIR COOLED CONDENSER AND AUXILIARIES WITH
HANGER SUPPORT ALONG WITH SUPPORTING STRUCTURES ” AT PROJECT SITE
Ensure that lifting load should be within safe limit of total lifting capacity of
crane arrangement.
Visual inspection of cranes and lifting accessories before putting in use for
ensuring healthiness of the same.
Ensure fitting of all the safety devices in cranes like as hook lifting latch, hoist
limit switch, boom limiting switch, braking system, TPI certificate, rope
condition & application of lubricants etc.
Ensure validity of documents of cranes and lifting accessories.
Ensure proper functioning of all the safety devices fitted in cranes.
Ensure cordoning off erection area by safe distance.
Ensure use of tag line/guide rope with safe access in respect of entry & exit
points.
Co-ordination between foremen/signal man/operators with single point
signalling system.
Ensure that crew members should be experience enough.
Ensure that nobody should be under suspended load and crane’s boom/rope
crossing area.
Minimum persons should be engaged for lifting.
After getting clearance from the signalman for lifting, all persons should
move away from lifting area.
Tag line persons should handle the load by maintaining safe distance from the
lifting area.
All persons should wear required PPEs.
Work-package shall be in ready condition.
Trained and experienced operator shall be engaged for operation of Cranes.
Ensure the levelled ground where cranes shall be used.
Provide warning systems such as cautionary safety signage.
Use of all necessary PPE shall be ensured.
Page 7 of 7