Updated: 16th November 2022

MOMBASA PORT DEVELOPMENT PROJECT - PHASE 1 (REPAIR WORKS)

PROPOSED INSPECTION FOR REPAIR WORKS AT EXISTING MPDP-1 - CIVIL WORKS

Joint KPA / TOYO Team

Inspection Schedule

Date Location Time Remarks / Attendees


Access Road (Port Ritz Junction -BP:: 0-173.44 ~ Port Gate Gate (1+250)) 9:00 ~ 10:30 Am KPA CIVIL

(Port Gate (1+300~ Connection Road to Near Substation T) 10:30 ~ 11:00 Am KPA CIVIL
16-Nov-22
(SGR - Trunk Road - MPDP1- Trunk Road 2+025 to Exp Joint - 2 +256.977) 11:00 ~ 11:30 KPA CIVIL

Suplimentary Area & Small Berth 2:30 ~ 4:00Pm KPA CIVIL / KPA OPERATIONS

Bulding Areas ( MEW , WEL, GRB, ADMIN, CGB,) 9:00 ~ 10:00 Am KPA CIVIL / KPA OPERATIONS

17-Nov-22 YARD AREA - Reefer Areas to Lane 1 to lane 12 10:00 ~ 11:30 Am KPA CIVIL / KPA OPERATIONS

Berth No. 20 - Berth No. 21 2:30 ~ 4:00 Pm KPA CIVIL / KPA OPERATIONS