Professional Documents
Culture Documents
INSPECTION SCHEDULE For Repair Works at Existing MPDP-1 CIVIL Updated 16th Nov 2022
INSPECTION SCHEDULE For Repair Works at Existing MPDP-1 CIVIL Updated 16th Nov 2022
Inspection Schedule
(Port Gate (1+300~ Connection Road to Near Substation T) 10:30 ~ 11:00 Am KPA CIVIL
16-Nov-22
(SGR - Trunk Road - MPDP1- Trunk Road 2+025 to Exp Joint - 2 +256.977) 11:00 ~ 11:30 KPA CIVIL
Suplimentary Area & Small Berth 2:30 ~ 4:00Pm KPA CIVIL / KPA OPERATIONS
Bulding Areas ( MEW , WEL, GRB, ADMIN, CGB,) 9:00 ~ 10:00 Am KPA CIVIL / KPA OPERATIONS
17-Nov-22 YARD AREA - Reefer Areas to Lane 1 to lane 12 10:00 ~ 11:30 Am KPA CIVIL / KPA OPERATIONS
Berth No. 20 - Berth No. 21 2:30 ~ 4:00 Pm KPA CIVIL / KPA OPERATIONS