BILL OF QUANTITIES

Volume of Concrete in Waist Slab


Height of one flight = 3.6/2 = 1.8 m
Length of flight = 2075mm =2.075 m

Inclined length of flight = √1.82 + 2.0752


= 2.75 m
Concrete in waist slab = Length x Width x Thickness
= 2.75 x 1.0 x 0.125

= 0.34 m³

Total volume concrete = 2 x 0.34 = 0.68 m³

Volume of Concrete in Steps


Height of Riser, R = 0.17m
Length of Tread, G = 0.255m
Length of steps = 1.0m
Volume of steps = ½ x Base x Height x Depth
= ½ x 0.17 x 0.255 x 1.0

= 0.022 m³
No. of steps in two flights = 9 x 2 = 18
Total volume concrete = 0.022 x 18

= 0.40 m³
Volume of Concrete in Landing
Length of landing = 2425mm = 2.425m
Breadth of landing = 1.0m
Depth of landing = 125mm = 0.125m
Total volume concrete = Length x Breadth x Depth
= 2.425 x 1.0 x 0.125

= 0.30 m³

Volume of Concrete in Handrail


Volume = Length x Breadth x Depth
= 2.75 x 0.1 x 0.5

= 0.14 m³
No. of handrails = 2

Total volume concrete = 2 x 0.14 = 0.28 m³

Item
Description Quantity Unit Rate RM
No.
Concrete work
Mass concrete for slab, mix grade 30
1 Concrete in waist slab 0.68 m 285.00 193.80
2 Concrete in steps 0.40 m 285.00 114.00
3 Concrete in landing 0.30 m 285.00 85.50
4 Concrete in handrail 0.28 m 285.00 79.80

Total Bill RM 473.10