You are on page 1of 1

NOTES

TOILET DETAIL SHADING ELEMENT DETAIL 1


Top Screw Fix

A
GENERAL NOTES
This drawing is protected under the
11,455 copyright Act and cannot be reproduced
in part or in whole whole without
200 150 150 200 200 1,000 authors consent.
4,875 1,500 3,415 765 Channel Section
All dimensions are to be checked on
site, written dimensions rules over
scaled dimensions. Any discrepancy in
the dimensions is to be reported to the

120
Architect before work commences.
150

150

150
175
0
00 All dimensions are in MM unless
1, specified.
Timber Louvre
All construction Work is to comply with
1,600

1,600

1,600
1,771
the latest K.B.S standard codes of
practice, local authority by-laws and fire
regulations.
1
this darwing is to be read in conjuction
150

150

150
with specifications and all other relevant
drawings.
Floor Plan Louvre Layout 1:20
P.V denotes permanent ventilation and
150mm thick reinforced concrete floor slab with
1,527

85
must be provided above all windows
5,780

5,780
and doors where indicated or shown.
400X200X30mmnon slip granito tiles

150
3,175

3,175
Water meter to be 300mm above
ground level.

All walls under 200mm thick to


reinforced with hoop iron after every
alternating course.
2,153

2,153
Damper proof course to be provided
under all external walls at grade. D.P.C
to be a minimum of 150mm obove
200

200
ground level.
505

505
Depth of foundation is to be determined
on site to S.E approval.
425 11,027
All vegetable soil to be removed from
200 150 150 150 150 150 150 150 150 200 under slab and all paved surfaces.
1,000 1,000 1,000 1,425 1,500 1,000 925 960 1,045
wall mounted water closets to M's All soils under slab and around external

specifications foundation to be treated for termite


control.

Provide 1 row of 600*600*50mm


550mm X 800mm high steel 750mm X 800mm high steel
A

precast conc. paving slabs around the


building unless otherwise shown.
casement single hung window casement single hung window
All reinforcement work to Structural
Engineers details.

. Drain pipes passing under tarmac,


driveways and buildings to be encased
in 150mm thick concrete surround.
TOILET PLAN 1:50
All sanitary works to the satisfaction of
the mechanical engineer.

All roads, storm water drainage and foul


sewerage to civil engineers drawings.

All electrical works to the entire


satisfaction of the Electrical engineer.
50mm thick Suspended gypsum ceiling
painted white
REVISIONS

DATE DESCRIPTION
150

400X 500mm R.C concrete beam


0.600

550mm X 800mm high steel


casement single hung window BRACKET OPTION CONNECTION TO THE WALL

BRACKET OPTION CONNECTION TO THE WALL


Wash hand basin to schedule
2.800

Urinal bowl to specs Perspective View of the Louvres 1:1.25

sink with a cabinet


1500mm high wall tiling finish to
specs

150mm thick reinforced concrete floor slab with


400X200X30mmnon slip granito tiles Timber
CLIENT NAME
MOWASCO
Lourve
75 used as
Toilet Section A-A 1:50 shading PROJECT DESCRIPTION
element in
the MIXED USE
TILE building DEVELOPMENT AT CBD
GROUT JOINT
MOMBASA
BOND COAT

STUDENT NAME
8mm thick WATERPROOF MEMBRANE IF
REQUIRED
granite top laid KENNETH KIPKOSGEY
MORTER BED
to approval SEALANT
KIPKEU
mm thick masonry BACKING

1,000
walling finish to 130 360 110
OPTIONAL REINFORCED
MORTAR BED IF REQUIRED

schedule PROJECT STAGE


MOVEMENT JOINT
WORKING DRAWINGS
12mm lime SHOWER PAN LINER

plaster Finish to 32mm CONCRETE SLAB


140

SLOPE TO
schedule mortar DRAIN
SCALE:
AS SHOWN

REG NO:
BARC/074J/2017

DATE:
30TH JULY 2021

Section Through WB 1:10 DRAWING NUMBER :

DETAIL DRAWINGS
Toilet Floor Section 1:10 Shading Lourve Detail 1:10 Louvre Render Detail 1:3.52

You might also like