Kabupaten : Pandeglang Jenis Prasarana : Perkerasan Jalan Beton

Kecamatan : Cisata Take Of Sheet Lokasi : Kp. Cisereh


Desa : Cisereh Volume : 50 x 3 m

Data Ukuran Prasarana


Panjang Jalan : 50 m
Lebar Jalan : 3m
Tinggi Jalan : 0.2 m

Perhitungan Volume Beton


50 x 3 x 0.2 = 30 m3

Perhitungan Analisa Bahan dan Upah


1 Galian Tanah ( SNI 2016 )
50 x 3 x 0.05 = 7.5 m3

Pekerja = 0.75 x 7.5 = 5.625 HOK


Normalisasi Jalan
Pekerja 0.75 x 150 = 112.5 HOK
Tukang 0.2 x 150 = 30 HOK
2 Pekerjaan Urugan Batu scroop
50 x 3 x 0.3 = 45 m3
Pekerja = 0.3 x 45 = 13.5 HOK

3 Pekerjaan Beton Ready Mix K-250


Beton Ready mix = 30 m3
Pekerja = 0.99 x 30 = 29.7 Hok
Tukang = 0.2 x 30 = 6 Hok

4 Bekisting
50 x 2x 0.2 = 20 m2
Papan Ukuran 2/20 0.6 m2
20 : 0.6 = 33.33 lb
= 34.00 lb
Paku : 0.3 x 20 = 6 kg
Pekerja = 0.52 x 20 = 11 HOK
Tukang = 0.26 x 20 = 6 Hok

5 Plastik Cor
50 x 3= 150 m2

Kebutuhan Bahan dan Upah


Beton Ready Mix K-250 = 30 m3
Batu Scroop = 45 m3
Papan Bekisting = 34.00 Lb
paku = 6 Kg

Pekerja = 172.325 = 173 HOK


Tukang = 42 = 42 HOK

Tanggal Survey : Dibuat oleh :