QUIZ: ASME AND NBIC CODE KNOWLEDGE

Chutchai Phromngam
ISSUE 364 : AUG 3, 2022
Authorized Inspector & Supervisor
Line ID: cphromngam RELATED CODE : ASME SECTION VIII.2, E2021
cphromngam@eagle.org
FIG-1
Cont’d
2/6

QUIZ: ASME AND NBIC CODE KNOWLEDGE ISSUE 364


QUIZ: ASME AND NBIC CODE KNOWLEDGE ISSUE 364
Temporary attachments for
Maintaining Alignment During Welding
FIG-2
Cont’d
3/6
QUIZ: ASME AND NBIC CODE KNOWLEDGE ISSUE 364
FIG-3 Temporary attachments for
field site assembly
Cont’d
4/6
Vessel Design Data:

Construction Code : ASME Section VIII Div.2, Class 2, Edition 2021


MAWP : 20 Bar @ 70˚C

QUIZ: ASME AND NBIC CODE KNOWLEDGE ISSUE 364


MDMT : -48˚C
Impact Test : Yes[required by construction Code for base metal, welding procedure and test
plate at MDMT or colder ]
Shell thickness ; 25mm, 35mm, and 50mm.

PWHT : Yes [Required by construction iaw paragraph 6.4.2 and Table 6.8 of ASME VIII.2

Cont’d
5/6
While reviewing Magnetic Particle Examination Or Liquid Penetrant Examination Records of “Removal
of Temporary Attachment” .

The QC Engineer notice to AI, map of location to performed examination(MT/PT) is not required by
Code of construction.

Would you as the AI accept the above situation ?

QUIZ: ASME AND NBIC CODE KNOWLEDGE ISSUE 364


A. Yes.

B. Yes, provided allow by QA/QC Manager.

C. Yes, provided allow by client or user.

D. No.

Reference Code para:______________________________