Risk ID Risk Likelihood Impact Plan

Office space is more Evaluate possible


1 Likely Medium
expensive than expected. budget increase.

Include penalty clause


Poor workmanship and in contract for delay.
4 Likely Large
rework delays project. Use contingency time
in schedule.

Building permits or Use contingency time


5 Unlikely Medium
certificates are delayed. in schedule.

Layout doesn't work and Add interim review


6 Unlikely Large
requires redesign. to schedule.

Technology doesn't work Add prototype task


7 Likely Large
as planned. with demonstration.

Technology setup takes Use contingency time


8 Likely Large
longer than planned in schedule.