Reinforced Earth Indonesia
Unroll the ReGrid-UXPET , position the ReGrid-UXPET so appropriate wide tail is left over
to make full face wrap to last stage. Place backfill up to half typical layer spacing (250mm),
then compact the backfill.
3
Reinforced Earth Indonesia
Place the ReGrid-UXPET over the soilbag with minimum return length of 1500mm on the
backfill, complete the backfill, compact the backfill until the layer thickness is equal to the
design (500mm)
Place the temporary vertical stakes on lower lift, unroll the ReGrid-UXPET as figure shown,
repeat the sequence until the top height of the REW design
4
Reinforced Earth Indonesia
5
Reinforced Earth Indonesia
Curved and
Diagonal Area
on Geogrid
Installation
6
Reinforced Earth Indonesia
Mostly are
manual works
7
Reinforced Earth Indonesia
Techrevetment® AB300
Techrevetment® AB300 Geotextile
Geotextile
8
Reinforced Earth Indonesia
Techrevetment®
TerraLine® AB300
Geotextile
9
Reinforced Earth Indonesia
Geotextile Non-Woven
(Installation Method)
10
Reinforced Earth Indonesia
TerraLine®
(Installation Method)
11
Reinforced Earth Indonesia
Techrevetment®
(Installation Method)
12
Reinforced Earth Indonesia
Techrevetment®
(Installation Method)
13
Reinforced Earth Indonesia
Geotextile
ArmaWeb®
Geomembrane
Geotextile Geotextile
Geomembrane
Geotextile
14
Reinforced Earth Indonesia
Geomembrane
(Installation Method)
15
Reinforced Earth Indonesia
ArmaWeb® Geocell
(Installation Method)
16
Reinforced Earth Indonesia
Techrevetment Techrevetment
Placement Concrete Injection
300-500 m2 fabric/day 3-5 m3 mortar
concrete/hour
12 labours
12 labours
17
Reinforced Earth Indonesia
ArmaWeb® Concrete
ArmaWeb® Geocell Infilling
Placement
28-42 m3 concrete/day
240-480 m2 geocell/day or
6 labours 350-525 m2 geocell
infill/day
18 labours
18
Reinforced Earth Indonesia
19
Reinforced Earth Indonesia
Geomembrane
Installation
450-1.200 m2 /day
18 labours
20
Reinforced Earth Indonesia
Techrevetment®
(The Challanges)
Slope design is
different with
Actual Slope
contour and
Angle
There is no
small Concrete
Pump rental
available yet in
Indonesia
21
Reinforced Earth Indonesia
ArmaWeb®
(The Challanges)
Concrete
infilling is
harder in steep
slope
Need more
treatment on
slope soil
condition
22
Reinforced Earth Indonesia
23