Calculation for Transformers By taking Overall Diversity factor 50 % => 960 KW By taking Power factor 0.90 => 1070 KVA Total Electrical Load = 1070 KVA
Recommended Transformers @ 80% Loading = 1 nos. 1600 KVA
Elec_Load Calc_Spring Homes Page 1
Electrical load Calculation of Spring Homes-EV Charging
S.No Description No. of unit Load per Unit Total Load
EV Charging load
1 Electrical Car Charging (20 % of Dwelling units) 62 nos @ 3.0 KW = 186 KW
Calculation for Transformers By taking Overall Diversity factor 75 % => 341 KW By taking Power factor 0.90 => 380 KVA Total Electrical Load = 380 KVA
Recommended Transformers @ 80% Loading = 1 nos. 630 KVA (Considering Fire Dead Load)
Elec_Load Calc_Spring Homes Page 3
Essential Electrical Load Calculations - Spring Homes
S.no Description No. of unit Load per Unit Total Load
SUB HEAD - A (APARTMENTS)
Tower - A (S+21) Nos of Tower = 1
1 3BHK + 3T+Servant 39 units @ 3.00 KVA = 117 KVA 2 4BHK + 4T+Servant 39 units @ 4.00 KVA = 156 KVA Tower - B/C(S+18) Nos of Tower = 2 3 3BHK+2T - type1 108 units @ 3.00 KVA = 648 KVA 4 3BHK+2T - type2 108 units @ 3.00 KVA = 648 KVA Tower - D (S+16) Nos of Tower = 1 5 5BHK + 5T+ 2 Servant 16 units @ 5.00 KVA = 80 KVA
Total Load = 1649 KVA
By taking overall Diversity factor 70 % => 1154 KVA