OPERATING PROCEDURE ASL FORM


NO.ISM065

VLGC GAS ALYSSA

LOCAL PROTECTION WATER MIST SYSTEM

TESTING FOR MAINTENANCE


Testing procedure must be done once a month
NOTES : The test is to be recorded in log book. The test must be coordinated with duty officer on
bridge in order to avoid any mistakes.

1. Close all outlet Valves. (1a,1b,1c,1d,1e,1f,1g)


2. Open the test valves. (2a,2b,2c,2d,2e,2f,2g)
3. Bring the test connection hose out from steering gear room.
4. Release one section manually by activating the “F1” button on the Fire Control Panel , select
a zone for release and press “ok”.
5. Check that the pump start, the correct section valve opens, the water is being discharged
through drain valve, and display on the fire control panel indicates:
“Water mist system released”.
6. Reset the alarm on the FCP.
7. Check that the section valve is closed and the pump is stopped
8. Close the test valve.
9. Repeat the test for other sections.
10. Open all outlet valves.
11. Refill F.W. tank with fresh water.
12. Check strainer if fitted in suction line.

CONTROLLED Revision: 01 Dec 2020


Approved by DPA
Page 1 of 1