INSPECTION CHECKLIST FOR REINFORCED CEMENT CONCRETE WORKS Date :

Building / Area :
Location : ( For Location / Grid please refer Location plan attached herewith ) Structure
Member/ ID / No. :

Reference Drawing :
Sr. Date & Time of
No. Inspection Items Checking Checking Status Remarks
1.0 CONCRETE PRE POUR CHECK
Check for Base (PCC) and Survey
1.1 Check for Cleaning of PCC Base
1.2 Check for Centerline marking
1.3 Check for PCC Top Level
CHECK FOR SHUTTERING WORKS
1.4 Check for Shuttering material Suitability
1.5 Check for Shuttering Size as per ref. drawing
1.6 Check for Shuttering Line, Level & Plumb
1.7 Check for Shuttering Supports system
1.8 Check for Provision of Pockets and its sizes
1.9 Check for Formwork Tightness
1.10 Check for Concrete Top Level
1.11 Check for Shuttering Release oil Application
1.12 Check for Concrete Cover as specified in the ref. drawing
1.13 Check for marking of Concrete Top Level
CHECK FOR REINFORCEMENT WORKS
1.14 Check for Cleanliness of Rebar (Free from Rust, Oil,
Grease, Oil & Dirt)
1.15 Check for Bar Dia, Spacing & , Bar Shape & Spacing
1.16 Check for Provision of Chairs / Supports
CHECK FOR INSERTS IF ANY
1.17 Check for Size, Spacing of Inserts / Structural Steel
CHECK FOR RESOURCES (MATERIAL, PLANT & MACHINERY)
1.18 Check for Concrete Qty. availability from RMC
Check for availability of Concrete Pumps, Chutes, Vibrators
CHECK FOR SAFETY
1.19 Check for Working Area / Area Lighting / Platform
availability
2.0 DURING CONCRETE POUR CHECK
2.1 Check for Concrete Grade (M30)
2.2 Check for Concrete Slump @ Site
2.3 Check for Concrete Sampling (Concrete Cube Casting)

RECTIFICATION COMPLIANCE STATUS


Sr.
No. Inspection Items Checking Record Checking Status Signature

Concrete Quantity Cum