Professional Documents
Culture Documents
Weekly Report
Weekly Report
PROJECT INTRODUCTION
WEEKLY REPORT NO
Report No. 0 Report from date, to date 14-May-22 to 19-May-22
Cut Off Date 19-May-22 Report date 30-Dec-99
PROJECT LOCATION
WEEKLY REPORT NO
Report No. 0 Report from date, to date 14-May-22 to 19-May-22
Cut Off Date 19-May-22 Report date 30-Dec-99
Performance Bond
Advance Payment Guarantee
CAR Insurances
WEEKLY REPORT NO
Report No. 0 Report from date, to date 14-May-22 to 19-May-22
Cut Off Date 19-May-22 Report date 30-Dec-99
Client
Consultant
Contractor
Award Date
Contractual Start Date
Contractual Completion Date
Revised Completion Date
Contract Value (QR)
Net Contract Value (QR)
Revised Contract Value (QR)
WEEKLY REPORT NO
Report No. 0 Report from date, to date 14-May-22 to 19-May-22
Cut Off Date 19-May-22 Report date 30-Dec-99
PROGRESS SUMMARY
Retaining wall steel works - Basement Retaining wall steel works - Basement
PROGRESS S-CURVE
AREAS OF CONCERN
1- Office staff 18 18 18 18 18 18
2- Steel fixer 8 8 8 8 8 8
3- Scaffolder 6 6 6 6 6 6
4- Plumber 1 1 1 1 1 1
5- Electrician 1 1 1 1 1 1
6- Rigger 0 0 0 0 0 0
7- mason 2 2 2 2 2 2
8- Labour/helper 5 5 5 5 5 5
9- Charge Hand 0 0 0 0 0 0
10- Carpenter 8 8 8 8 8 8
11- technician/Welder 0 0 0 0 0 0
12- Operator/Driver 6 6 6 6 6 6
13- welder 0 0 0 0 0 0
14- Surveyor Helper 2 2 2 2 2 2
15- Security/watchman/Office Boy 3 3 3 3 3 3
-
TOTAL 60 60 60 60 60 60
WEEKLY REPORT NO
Report No. 0 Report from date, to date 14-May-22 to 19-May-22
Cut Off Date 19-May-22 Report date 30-Dec-99
1- BOB CAT 0 0 0 0 0 0
2- FORKLIFT 0 0 0 0 0 0
3- PICKUP 2 2 2 2 2 2
4- GENERATOR 4 4 4 4 4 4
5- LOADER/SHOWEL 0 0 0 0 0 0
6- ROAD ROLLER 0 0 0 0 0 0
7- SMALL ROLLER 0 0 0 0 0 0
8- SMALL GENERATOR 1 1 1 1 1 1
9- VIBRATOR 2 2 2 2 2 2
10- COMPRESSOR 1 1 1 1 1 1
11- TOWER LIGHT 1 1 1 1 1 1
12- WATER PUMP 2 2 2 2 2 2
13- COMPACTOR 0 0 0 0 0 0
14- BACK FILLING SIEVER 0 0 0 0 0 0
15- TOWER CRANE 1 1 1 1 1 1
16- STEEL BENDING MACHINE 1 1 1 1 1 1
17- STEEL CUTTING MACHINE 1 1 1 1 1 1
18- CONCRETE PUMP 3 3 3 3 3 3
19- CONCRETE TRUCK 1 1 1 1 1 1
20- EXCAVATOR 0 0 0 0 0 0
21- WELDING MACHINE 1 1 1 1 1 1
22- MOBILE CRANE 1 1 1 1 1 1
WEEKLY REPORT NO
Report No. 0 Report from date, to date 14-May-22 to 19-May-22
Cut Off Date 19-May-22 Report date 30-Dec-99
PROGRAMME UPDATE
Dash Board
Column B Column C
Retaining wall steel works - Basement Retaining wall steel works - Basement Curing of columns casted - Basement Retaining wall concreting works - Basement
Curing of concreted columns - Basement Curing of columns casted - Basement Shuttering works for Columns- Basement Curing of columns casted - Basement
CONTRACT COMMENCEMENT DATE 10-Oct-21 CLIENT TRIPPLE A Activity ID Activity Name Start Finish Schedule % Complete Performance % Complete Total Float
CONTRACT COMPLETION DATE 10-Sep-22 CLIENT REPRESENTATIVE TRIPPLE A Outpatient Updated 19-05-2022 10-Oct-2021 A 7-Mar-23 67.87% 36.12% -133
CUUMALTIVE AWARDED EOT (DAYS) 0 SUPERVISION CONSULTANT (ENGINEER) Al Baraaha Engineering Consultant Key Dates & Milestones 10-Oct-2021 A 7-Mar-23 0% 0% -133
REVISED COMPLETION DATE 10-Sep-22 TYPE OF CONTRACT Fixed Lump Sum Preliminaries & Mobilization 10-Oct-2021 A 9-Jan-23 92.88% 85.76% -97
FOR ECAST COMPLETION DATE (Up dated Programme R ev 04) 07-Mar-23 CONTRACT AMOUNT (Excluding Provisional Sums +Variations) - Engineering 27-Oct-2021 A 24-Nov-22 94.61% 30.10% -89
DELAY IN DAYS 179 APPROVED CONTRACT AMENDMENT/VARIAITIONS - Procurment 13-Nov-2021 A 4-Aug-22 100.00% 87.20% -88
EOT Rev. xx UNDER APPR OVAL/PR EPRATIO N 10-Sep-22 REVISED CONTRACT VALUE (Cont ract Value + Contr act Amendmen t+ Appro ved Var iations ) - #DIV/0! Remaining Construciton 05-Jan-2022 A 5-Mar-23 62.47% 27.09% -132
DELAY IN DAY S (Considering the EOT under approv al/prepa ra tion) 178 GROSS VALUE OF WORK DONE 4,085,172.00 #DIV/0! #DIV/0! Pointer Main Building 05-Jan-2022 A 5-Mar-23 65.04% 28.20% -132
FOR ECAST COMPLETION DATE (Up dated Programme R ev 0.0) 07-Mar-23 POTENTIONAL VARIATIONS/ UNDER ENGINEER'S APPROVAL 66% 60 Boundry wall 9-Nov-22 17-Jan-23 0% 0% -99
Data Date 19-May-22 PERCENTAGE OF GROSS VALUE OF WORK DONE #DIV/0! 34% 60 Demobilization 5-Mar-23 7-Mar-23 0% 0% -164
120% 60 Client Handing over 5-Mar-23 7-Mar-23 0% 0% -164
PROGRESS (INVOICE) PROGRESS (PROGRAMME) DURATION 180
PLANNED PROGRESS 51.00% PLANNED PROGRESS 67.87% COMPLETED DURATION 222 66% #DIV/0!
ACTUAL PROGRESS 18.33% 32.67% ACTUAL PROGRESS 36.12% 31.75% REMAINING DURATION 114 34%
VARIANCE VARIANCE -31.75% PROGRESS DATA DATA 19-May-22 336
PLANNED PROGRESS 51.00% TOTAL
ACTUAL PROGRESS 2,073,127.41 11,310,000.00 Completed 66%
VARIANCE Remaining 34%
SUMMARY OF WORK PROGRESS (OVERALL)
DESCRIPTION PHASE 1 PHASE 2 PHASE 3 PHASE 4 PHASE 5 35 130 246.692308 307.8916 432.0996296 612.5030435 539.6851852 341.572 249.8575 87.640384615 30
FINANCIAL STATUS
Column1 CLAIMED BALANCE BOQ AMMOUNT
PRELIMINARIES 750 250 1000
STRUCTURAL WORKS 750 250 1000
BLOCK WORKS 750 250 1000
MEP WORKS 750 250 1000
TOTAL 3000 1000 4000
Craft Plan Act Item Plan Act Plan Actual Variance Cummulative
Planned Current Completion
Office staff 18 BOB CAT 0 MU 14 0.00% 0.00% 0.00% Plan Actual Variance Variance in Days
Steel fixer 8 FORKLIFT 0 MU 15 0.00% 0.00% 0.00% Mobilization & Prelims 10.00% 10.00% 0.00% Start Finish Start Finish
Scaffolder 6 PICKUP 2 MU 16 0.00% 0.00% 0.00% Engineering & Shop draw 10.00% 10.00% 0.00%
Plumber 1 GENERATOR 4 MU 17 0.00% 0.00% 0.00% Procurement 10.00% 10.00% 0.00%
Electrician 1 LOADER/SHOWEL 0 MU 18 0.00% 0.00% 0.00% Construction 10.00% 10.00% 0.00%
Rigger 0 39 ROAD ROLLER 0 MU 19 0.00% 0.00% 0.00% Testing & Commissionin 0.00% 0.00% 0.00% 80.00%
mason 2 SMALL ROLLER 0 MU 20 Snagging & Handover 0.00% 0.00% 0.00% 80.00%
Labour/helper 5 SMALL GENERATOR 1 MU 21 16.66% 10.23% -6.43% 0.00%
Charge Hand 0 VIBRATOR 2 MU 22
Carpenter 8 COMPRESSOR 1 MU 23
technician/Welder 0 TOWER LIGHT 1 MU 24
Operator/Driver 6 WATER PUMP 2 MU 25
welder 0 COMPACTOR 0 MU 26
Surveyor Helper 2 BACK FILLING SIEVER 0 MU 27
Security/watchman/Office Boy 3 TOWER CRANE 1 38.77% 6.28% -13.95%
0 0 STEEL BENDING MACHINE 1 0.00% ###
0 0 STEEL CUTTING MACHINE 1 38.77% ###
Total 0 60 CONCRETE PUMP 3
CONCRETE TRUCK 1
EXCAVATOR 0
WELDING MACHINE 1
MOBILE CRANE 1
Total 0 22
SHOP DRAWING
OVER DUE ≥ 14
DESCRIPTION TOTAL NO PLANNED SUBMITTED APPROVED REVISE UNDER REVIEW DAYS REJECTED TOTAL LLI ORDERD LLI N/A
General 0 0 0 0 0 0
Civil & Structural 85 58 15 12 12 0 0 0 0
Architectural 0 0 0 0 0 0
Electrical 1 1 0 0 0 0 0 0
Mechanical 2 2 2 0 0 0 0
Total 0 0 88 58 16 14 14 0 0 0 0
MATERIAL SUBMITTALS
OVER DUE ≥ 21
DESCRIPTION TOTAL NO PLANNED SUBMITTED APPROVED REVISE UNDER REVIEW REJECTED N/A
DAYS
General 0 0 0 0
Civil & Structural 19 12 2 5 5 0 0
Architectural 0 0 0 0 0 0 0
Mechanical 1 1 1 0 0
Electrical 2 2 0 0 0 0
Total 0 0 22 14 2 6 6 0 0
METHOD STATEMENTS
OVER DUE ≥ 14
DESCRIPTION TOTAL NO PLANNED SUBMITTED APPROVED REVISE UNDER REVIEW DAYS REJECTED N/A
General 0 0 0 0 0 0 0
Civil & Structural 0 9 5 1 3 3 0 0
Architectural 0 1 1 0 0 0 0 0
Mechanical 0 0 0 0 0 0 0 0
Electrical 0 0 0 0 0 0 0 0
Total 0 0 10 6 1 3 3 0 0
NCR
DESCRIPTION ISSUED REPLIED CLOSED PENDING
CIV
MEP
HSE
Total
Up to the Period Ending Total Gross Value Due IPC Paid Payment 100%
November-21
December-21
January-22
February-22
March-22
April-22 4,085,172.00
May-22
June-22
July-22
August-22 Jul-22
September-22
October-22
Spreadsheet Field 1-Oct-21 1-Nov-21 1-Dec-21 1-Jan-22 1-Feb-22 1-Mar-22 1-Apr-22 1-May-22 1-Jun-22 1-Jul-22 1-Aug-22 1-Sep-22
Planned Total Cost 628,798.00 533,259.61 966,553.30 1,077,218.50 1,302,826.86 1,259,820.49 1,393,311.35 931,822.40 1,020,540.39 1,077,066.80 857,234.53 261,547.78
Cum Budgeted Total Cost 628,798.00 1,162,057.61 2,128,610.90 3,205,829.41 4,508,656.26 5,768,476.76 7,161,788.11 8,093,610.51 9,114,150.90 10,191,217.69 11,048,452.22 11,310,000.00
Actual Total Cost 609,192.29 420,672.96 50,010.16 628,583.35 297,907.43 729,878.22 421,477.32 851,561.14
Cum Actual Total Cost 609,192.29 1,029,865.25 1,079,875.41 1,708,458.76 2,006,366.20 2,736,244.42 3,157,721.74 4,009,282.88
3.50%
80.00%
3.10%
69.75% 70.00%
3.00%
67.90%
66.28%
64.27%
62.30%
61.20%
59.26%
60.00%
2.50%
57.08%
54.77%
2.31%
52.75%
51.05%
2.15%
2.18%
50.00%
48.90%
47.13%
2.02% 2.02%
2.01%
2.00%
45.54%
1.97%
1.94% 1.94%
44.12%
1.91%
42.41% 1.85%
1.84%
1.83%
1.81%
40.58% 1.77%
1.72%
1.71%
40.00%
1.70%
1.69% 38.77%
1.62%37.22% 1.62%
1.59%
35.60% 1.55%
1.51%
1.50% 1.49%
33.88%
1.46%
1.42%
32.04%
1.38%
1.34%
30.02%
1.29% 30.00%
1.25% 1.25% 28.81%
1.23%
1.21% 1.21% 27.80%
1.20%
27.12% 1.18% 1.18%
1.16%
1.15%
26.34%
25.87%
1.10% 1.10%
25.18%
24.62%
23.98%
23.70%
1.01%
1.00% 22.93% 22.83%
0.98% 0.98%
0.97% 0.97%
21.85%
21.55%
0.92%
0.91% 20.95%
20.72% 0.90%
0.85% 19.74%
19.38%
20.18%
20.00%
19.10% 0.83%
0.82%
0.80% 0.80% 18.56% 0.80%
18.13%
0.77% 0.77% 0.77%
17.65%
17.38%
16.94%
0.71%
16.14% 16.17%
0.69%
0.67% 15.62%
15.16%
0.64%
0.62%
0.60% 13.82%
13.68%
12.83%
12.53%
0.52%
11.86%
0.50%
0.50%
0.48% 11.35%
10.66%
9.95%
0.40% 0.40% 9.43%
10.00%
9.04%
8.81%
8.50%
8.27% 8.29%
8.01% 8.12%
0.31%
0.30% 0.30% 0.30% 0.30%
6.78%
6.59% 6.59% 6.59%
6.35% 6.45%
0.26% 6.22% 6.26% 6.28%
6.00%
5.80%
5.60%
5.20% 0.22%
4.90% 5.00% 0.21%
0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20%
4.70% 0.20% 0.20% 0.20% 0.20%
4.50%
4.20% 0.17%
4.00%
3.68% 3.80%
0.15%
0.14% 0.14%
3.20%
2.90% 3.00%
0.11% 0.11%
0.10% 2.50% 0.10% 0.10% 0.10%
0.09% 2.17% 2.30%
1.89% 2.00%
1.75% 0.07%
1.50% 1.60%
0.05%
1.07% 1.20% 0.04%
1.00%
0.80% 0.02%
0.50%
0.00%
0.40%
0.00% 0.00%
0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.05%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3.20%
2.90% 3.00%
0.11% 0.11%
0.10% 2.50% 0.10% 0.10% 0.10%
0.09% 2.17% 2.30%
1.89% 2.00%
1.75% 0.07%
1.50% 1.60%
0.05%
1.07% 1.20% 0.04%
1.00%
0.80% 0.02%
0.50%
0.00%
0.40%
0.00% 0.00%
0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.05%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
03-Sep-20 10-Sep-20 17-Sep-20 24-Sep-20 01-Oct-20 08-Oct-20 15-Oct-20 22-Oct-20 29-Oct-20 05-Nov-20 12-Nov-20 19-Nov-20 26-Nov-20 03-Dec-20 10-Dec-20 17-Dec-20 24-Dec-20 31-Dec-20 07-Jan-21 14-Jan-21 21-Jan-21 28-Jan-21 04-Feb-21 11-Feb-21 18-Feb-21 25-Feb-21 ### ### ### ### 01-Apr-21 08-Apr-21 15-Apr-21 22-Apr-21 29-Apr-21 06-May-21 13-May-21 20-May-21 27-May-21 03-Jun-21 10-Jun-21 17-Jun-21 24-Jun-21 01-Jul-21 08-Jul-21 15-Jul-21 22-Jul-21 29-Jul-21 05-Aug-21 12-Aug-21 19-Aug-21 26-Aug-21 02-Sep-21 09-Sep-21 16-Sep-21 23-Sep-21 30-Sep-21 07-Oct-21 14-Oct-21 21-Oct-21 28-Oct-21 ### ### ### ### 02-Dec-21 09-Dec-21 16-Dec-21 23-Dec-21 30-Dec-21 06-Jan-22 13-Jan-22 20-Jan-22
Planned Weekly % 0.05% 0.09% 0.26% 0.67% 1.10% 1.51% 3.10% 1.49% 0.77% 0.91% 1.91% 0.97% 0.85% 1.94% 0.52% 0.80% 0.71% 0.48% 0.97% 0.64% 0.98% 0.83% 1.38% 0.77% 0.92% 1.25% 1.25% 1.69% 1.21% 2.02% 1.84% 1.72% 1.62% 1.55% 1.81% 1.83% 1.71% 1.42% 1.59% 1.77% 2.15% 1.70% 2.02% 2.31% 2.18% 1.94% 1.10% 1.97% 2.01% 1.62% 1.85% 0.80% 0.11% 0.17% 0.21% 0.31% 0.62% 1.23% 0.69% 1.18% 1.29% 1.34% 1.01% 1.21% 1.18% 0.82% 0.80% 0.77% 0.90% 0.98% 1.15% 1.20% 1.16%
Cum Planned % 0.05% 0.14% 0.40% 1.07% 2.17% 3.68% 6.78% 8.27% 9.04% 9.95% 11.86% 12.83% 13.68% 15.62% 16.14% 16.94% 17.65% 18.13% 19.10% 19.74% 20.72% 21.55% 22.93% 23.70% 24.62% 25.87% 27.12% 28.81% 30.02% 32.04% 33.88% 35.60% 37.22% 38.77% 40.58% 42.41% 44.12% 45.54% 47.13% 48.90% 51.05% 52.75% 54.77% 57.08% 59.26% 61.20% 62.30% 64.27% 66.28% 67.90% 69.75% 8.01% 8.12% 8.29% 8.50% 8.81% 9.43% 10.66% 11.35% 12.53% 13.82% 15.16% 16.17% 17.38% 18.56% 19.38% 20.18% 20.95% 21.85% 22.83% 23.98% 25.18% 26.34%
Actual Weekly % % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.50% 0.30% 0.20% 0.20% 0.30% 0.10% 0.15% 0.14% 0.11% 0.30% 0.20% 0.40% 0.10% 0.20% 0.60% 0.20% 0.20% 0.30% 0.20% 0.20% 0.10% 0.20% 0.40% 0.20% 0.20% 0.22% 0.04% 0.02% 0.07% 0.10% 0.14% 0.00% 0.00%
Cum Actual % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.50% 0.80% 1.00% 1.20% 1.50% 1.60% 1.75% 1.89% 2.00% 2.30% 2.50% 2.90% 3.00% 3.20% 3.80% 4.00% 4.20% 4.50% 4.70% 4.90% 5.00% 5.20% 5.60% 5.80% 6.00% 6.22% 6.26% 6.28% 6.35% 6.45% 6.59% 6.59% 6.59%
Cum Planned %
Planned Weekly %
Actual Weekly % %
Cum Actual %
103,625,016.00
103,625,016.00
Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22
Planned Total Cost 51,812.51 93,262.51 269,425.04 694,287.61 1,139,875.18 1,564,737.74 3,212,375.50 1,544,012.74 797,912.62 942,987.65 1,979,237.81 1,005,162.66 880,812.64 2,010,325.31 538,850.08 829,000.13 735,737.61 497,400.08 1,005,162.66 ### ### ### 1,430,025.22 ### ### ### ### ### ### ### ### ### ### 1,606,187.75 ### 1,896,337.79 1,771,987.77 1,471,475.23 1,647,637.75 ### ### ### ### ### ### ### ### ### ### ### ### 829,000.13 113,987.52 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
Cum Budgeted Total Cost 51,812.51 145,075.02 414,500.06 1,108,787.67 2,248,662.85 3,813,400.59 7,025,776.08 8,569,788.82 9,367,701.45 10,310,689.09 12,289,926.90 13,295,089.55 14,175,902.19 16,186,227.50 16,725,077.58 17,554,077.71 18,289,815.32 18,787,215.40 19,792,378.06 ### ### ### 23,761,216.17 ### ### ### ### ### ### ### ### ### ### 40,175,418.70 ### 43,947,369.29 45,719,357.06 47,190,832.29 48,838,470.04 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
Actual Total Cost 0.00 0.00 0.00 0.00 0.00 0.00 518,125.08 310,875.05 207,250.03 207,250.03 310,875.05 103,625.02 155,437.52 145,075.02 113,987.52 310,875.05 207,250.03 414,500.06 103,625.02 ### ### ### 207,250.03 ### ### ### ### ### ### ### ### ### ### 20,725.00 ### 103,625.02 145,075.02 0.00 0.00
Cum Actual Total Cost 0.00 0.00 0.00 0.00 0.00 0.00 518,125.08 829,000.13 1,036,250.16 1,243,500.19 1,554,375.24 1,658,000.26 1,813,437.78 1,958,512.80 2,072,500.32 2,383,375.37 2,590,625.40 3,005,125.46 3,108,750.48 ### ### ### 4,352,250.67 ### ### ### ### ### ### ### ### ### ### 6,507,651.00 ### 6,683,813.53 6,828,888.55 6,828,888.55 6,828,888.55
YASEEM CITY
3,500,000.00 100,000,000.00
90,000,000.00
3,000,000.00
80,000,000.00
2,500,000.00
70,000,000.00
60,000,000.00
2,000,000.00
50,000,000.00
1,500,000.00
40,000,000.00
30,000,000.00
1,000,000.00
20,000,000.00
500,000.00
10,000,000.00
- -
1.60% 30.00%
27.80%
1.46%
26.34%
1.40%
25.18%
1.34%
25.00%
1.2 9%
23.98%
1.23%
22.83%
1.21%
1.20%
1.20%
1.18% 1.1 8%
21.85%
1.16%
1.15%
20.95%
20.18%
20.00%
19.38%
1.0 1%
1.00%
18.56%
0.98%
17.38%
0.90%
16.17%
0.82%
15.16%
0.80% 0.80%
0.80% 15.00%
0.77%
13.82%
0.6 9%
12.53%
0.6 2%
11.35%
0.60%
10.66%
10.00%
9.4 3%
8.81%
8.50%
8.29%
8.12%
8.01%
0.40%
0.31%
5.00%
0.2 1%
0.20%
0.17%
0.1 1%
0.00% 0.00%
27-Jan-22 03-Feb-22 10-Feb-22 17-Feb-22 24-Feb-22 ### ### ### ### ### 07-Apr-22 14-Apr-22 21-Apr-22 28-Apr-22 ### ### ### ### 02-Jun-22 09-Jun-22 16-Jun-22 23-Jun-22 30-Jun-22 07-Jul-22 14-Jul-22 21-Jul-22 31-Jul-22
1.46%
27.80% 29.21% 30.53% 32.20% 33.86% 35.78% 37.75% 39.91% 42.22% 44.64% 47.23% 49.71% 52.38% 54.88% 56.25% 59.78% 64.24% 68.71% 73.81% 78.14% 83.23% 87.44% 90.91% 94.00% 95.06% 97.24% 100.00%
###
###
26-Aug-21 02-Sep-21 09-Sep-21 16-Sep-21 23-Sep-21 30-Sep-21 07-Oct-21 14-Oct-21 21-Oct-21 28-Oct-21 04-Nov-21 11-Nov-21 18-Nov-21 25-Nov-21 02-Dec-21 09-Dec-21 16-Dec-21 23-Dec-21 30-Dec-21 06-Jan-22 13-Jan-22 20-Jan-22 27-Jan-22 03-Feb-22 10-Feb-22 17-Feb-22 24-Feb-22 03-Mar-22 10-Mar-22 17-Mar-22 24-Mar-22 31-Mar-22 07-Apr-22 14-Apr-22 21-Apr-22 28-Apr-22 05-May-22 12-May-22 19-May-22 26-May-22 02-Jun-22 09-Jun-22 16-Jun-22 23-Jun-22 30-Jun-22 07-Jul-22 14-Jul-22 21-Jul-22 31-Jul-22
Planned Weekly % 0.80% 0.10% 0.05% 0.30% 0.25% 0.10% 0.60% 0.60% 0.25% 1.10% 2.54% 1.11% 1.08% 1.08% 1.40% 1.30% 1.09% 1.38% 1.19% 1.65% 1.22% 1.66% 1.85% 1.97% 1.87% 2.10% 2.73% 2.54% 2.90% 2.97% 3.38% 3.88% 4.56% 4.26% 4.34% 5.15% 1.80% 3.89% 3.63% 3.30% 3.37% 2.46% 1.86% 1.66% 1.05% 1.04% 0.20% 1.54% 2.15%
Cum Planned % 7.50% 7.60% 7.65% 7.95% 8.20% 8.30% 8.90% 9.50% 9.75% 10.85% 13.39% 14.50% 15.58% 16.66% 18.06% 19.36% 20.45% 21.83% 23.02% 24.67% 25.89% 27.55% 29.40% 31.37% 33.24% 35.34% 38.07% 40.61% 43.51% 46.48% 49.86% 53.74% 58.30% 62.56% 66.90% 72.05% 73.85% 77.74% 81.37% 84.67% 88.04% 90.50% 92.36% 94.02% 95.07% 96.11% 96.31% 97.85% 100.00%
Actual Weekly % % 0.10% 0.60% 0.05% 0.72% 0.03% 0.20% 0.40% 0.35% 0.10% 0.24% 0.19% 0.19% 0.19% 1.52%
Cum Actual % 5.50% 6.10% 6.15% 6.87% 6.90% 7.10% 7.50% 7.85% 7.95% 8.19% 8.38% 8.57% 8.76% 10.28%
Pla nned W eek l y % Act ua l Weekly % % CumPl an ned % Cum Actu al % Row7
6% 120%
5.15%
100.00%
5% 100%
97.85%
96.11% 96.31%
95.07%
94.02%
92.36%
4.56%
90.50%
88.04%
4.34%
4.26%
84.67%
81.37%
4% 80%
3.88% 3.89%
77.74%
73.85%
3.63%
72.05%
3.38% 3.37%
66.90%
3.30%
62.56%
3% 2.97% 60%
2.90% 58.30%
2.73%
53.74%
2.54% 2.54%
49.86%
2.46%
46.48%
43.51%
2.15%
2.10%
40.61%
2% 1.97% 40%
38.07%
1.85% 1.87% 1.86%
1.80%
35.34%
1.30% 25.89%
24.67% 1.22%
1.19%
23.02%
1.10% 1.11% 1.09%
1.08% 1.08% 21.83%
1.05% 1.04%
20.45%
1% 19.36% 20%
18.06%
16.66%
0.80%
15.58%
0.72% 14.50%
13.39%
0.60% 0.60% 0.60%
10.85%
9.50% 9.75% 10.28%
8.90%
8.20% 8.30% 0.40%
8.76%
6.87%
7.10%
7.50%
0.35%
0.30%
6.90%
6.10% 6.15%
5.50% 0.25% 0.25% 0.24%
0.20% 0.19% 0.19% 0.19% 0.20%
0.10%
0.10% 0.10% 0.10%
0.05%
0.05%
0.03%
0% 0%