Ashiana Housing Limited.

Project Name - Ashiana Tarang


Phase - All
Achvd. Area
Target Vs Achievement for the week (11th Mar'23 - 17th Mar'23)
18.03.23
All Value in ''000
Sr. No. Description Target Achieved Value Remark
Failure in Foundation due to shortage of shuttering
1 Foundation 769 227
manpower

Failure in super structure due to shortage of


2 Super Structure 2,087 119
shuttering manpower
Failure in masonry work Due to unavailable
3 Masonry Work 342 128
workfront because of Loft Shuttering.

4 Flooring Work 381 304

5 Sealing & Water Proofing Work - -


Failure in Door & windows due to shortage of
6 Door & Windows 1,345 827
Aluminium manpower
7 Electrical 88 63
8 Plumbing 205 116
9 Painting 394 280
10 MS Work 14 -
11 Direct Project Expences 561 140
12 Features - -
Club/Learning HUB/Nursery
13 - -
School/Commercial
14 Others - -
Total 6,186 2,204
Add 10% Overhead 619 220
Total With Overhead 6,805 2,425 36%
Area(Sft) 4,758 1,690