The document provides target and achievement details for construction work in week 11-17 March 2023 for Ashiana Tarang project by Ashiana Housing Limited, noting several areas like foundation, super structure, and masonry work fell short of targets due to issues like shortage of shuttering manpower and unavailable workfront. Overall achievement was 2,204 against a target of 6,186 for direct project expenses, with total achievement including 10% overhead being 2,425 against a target of 6,805. The total area completed was 1,690 square feet against a target of 4,758 square feet.
The document provides target and achievement details for construction work in week 11-17 March 2023 for Ashiana Tarang project by Ashiana Housing Limited, noting several areas like foundation, super structure, and masonry work fell short of targets due to issues like shortage of shuttering manpower and unavailable workfront. Overall achievement was 2,204 against a target of 6,186 for direct project expenses, with total achievement including 10% overhead being 2,425 against a target of 6,805. The total area completed was 1,690 square feet against a target of 4,758 square feet.
The document provides target and achievement details for construction work in week 11-17 March 2023 for Ashiana Tarang project by Ashiana Housing Limited, noting several areas like foundation, super structure, and masonry work fell short of targets due to issues like shortage of shuttering manpower and unavailable workfront. Overall achievement was 2,204 against a target of 6,186 for direct project expenses, with total achievement including 10% overhead being 2,425 against a target of 6,805. The total area completed was 1,690 square feet against a target of 4,758 square feet.
Phase - All Achvd. Area Target Vs Achievement for the week (11th Mar'23 - 17th Mar'23) 18.03.23 All Value in ''000 Sr. No. Description Target Achieved Value Remark Failure in Foundation due to shortage of shuttering 1 Foundation 769 227 manpower
Failure in super structure due to shortage of
2 Super Structure 2,087 119 shuttering manpower Failure in masonry work Due to unavailable 3 Masonry Work 342 128 workfront because of Loft Shuttering.
4 Flooring Work 381 304
5 Sealing & Water Proofing Work - -
Failure in Door & windows due to shortage of 6 Door & Windows 1,345 827 Aluminium manpower 7 Electrical 88 63 8 Plumbing 205 116 9 Painting 394 280 10 MS Work 14 - 11 Direct Project Expences 561 140 12 Features - - Club/Learning HUB/Nursery 13 - - School/Commercial 14 Others - - Total 6,186 2,204 Add 10% Overhead 619 220 Total With Overhead 6,805 2,425 36% Area(Sft) 4,758 1,690