BID EVALUATION FOR 1 – 460V MOTOR CONTROL CENTRE
PURCHASE REQUISITION NUMBER – 10249290

1.0 SUMMARY OF BID EVALUATION.

VENDOR TECHNICAL COMMERCIAL DELIVERY BID REMARKS


(UNIT COST / TT$) VALIDITY
1 TOSL Engineering Limited Not Technically Compliant Not Specified Not Specified Not Specified Petrotrin’s requirements not met. Offer rejected.
2 Tang How Brothers Inc. Not Technically Compliant 268,094.49 7 weeks Not Specified Petrotrin’s requirements not met. Offer rejected.
3 HADCO Limited Not Technically Compliant 197,000.00 9-12 weeks Not Specified Petrotrin’s requirements not met. Offer rejected.
4 Neal and Massy Energy Services Meets Petrotrin’s 167,000.00 12-14 weeks 30 days Lowest Bidder which met Petrotrin’s
Ltd. Specifications. Technically requirements
Compliant
5 PowerLite Products Ltd. Not Technically Compliant 146,935.33 4-8 weeks Not Specified Petrotrin’s requirements not met. Offer rejected.
6 EIL Ltd Meets Petrotrin’s 170,000.00 18 weeks 30 days Petrotrin’s commercial requirements not met.
Specifications. Technically The quoted cost does not include freight. Offer
Compliant rejected.
7 OHM International Corp. Not Technically Compliant Not Specified Not Specified Not Specified Petrotrin’s requirements not met. Offer rejected.

8 Marenco International Not Technically Compliant Not Specified Not Specified Not Specified Petrotrin’s requirements not met. Offer rejected.
9 ECM Ltd. Not Technically Compliant 120,634.00 10-12 weeks Not Specified Petrotrin’s requirements not met. Offer rejected.

10 Sterlin’s Electrical Supplies Not Technically Compliant Not Specified Not Specified Not Specified Petrotrin’s requirements not met. Offer rejected.
11 Leading Edge Exporters Inc. Not Technically Compliant Not Specified Not Specified Not Specified Petrotrin’s requirements not met. Offer rejected.

2023-03-20
Petroleum Company of Trinidad and Tobago Limited
Centralised Engineering and Construction Division
Electrical / Instrument Department
Sheet 2 of 2
2.0 RECOMMENDATION
It is recommended that an order be placed with Neal and Massy Energy Services Limited for the supply of one (1) 460V Motor Control Centre at a total price of
TT$167,000.00 and a delivery period of 12-14 weeks.

3.0 JUSTIFICATION

Lowest bid which met Petrotrin’s Specifications. Detailed evaluation attached in Appendix A.

Prepared By: ___________________ Date: ______________ Reviewed By: _____________________ Date: _______________
Christopher Walton Ganesh Sookdeo
Electrical Engineer I Superintendent, Electrical Engineering

Approved By: ___________________ Date: _______________


Narayan Ramtahal
General Manager, Engineering and Construction