Minutes of Meeting dated 14-03-2023 between HEIL and Climate Connect pertaining to open points of REMC Telangana Project

to be completed before TOC of the REMC project.


NOA: CC-CS/1014-SR1/SCADA-4110/3/G7/NOA-I/9037 dt 01.07.2020 - Supply contract
NOA: CC-CS/1014-SR1/SCADA-4110/3/G7/NOA-II/9038 dt 01.07.2020 – Service contract
Date: 14-03-2023

Name of the Agency: M/s Hitachi Energy India Limited (formerly ABB Power Products and Systems India Limited) & M/s Climate Connect
Critical Points
Sl no Point description TSSLDC remarks Status 14 Mar 2023
Not properly implemented in all the related modules to which
moderation effects. For example if the moderation is done in Demonstrated and issues were observed and M/s Climate Connect clarified that
1 Moderation Tab curtailment report the plant is shown as curtailed even though the issue observed were due to backend testing and same is now resloved and
no curtailment issued. shall be tested by TSTRANSCO. Additionally, Notifications to QCA to be
implemented during the AMC period.

Clarification call with Climate Connect Data Science team held on 14th March,
Clarification needed for IFT and combiner algorithm as it is
2023. M/s Climate connect explained the working of forecasting and stated that
observed that for dummy plants also forecasts are generated
system is under stablization.
2 Forecasting tool eventhough co-ordinates etc , data not provided. Climate
Once the FSP is commercialised after the Provisional Taking Over the dummy
Connect and Reconnect forecast is available for such plants but
plant forecasting shall be addressed with the FSPs within 15 days.
IFT and Kreate tech forecast is missing.

For deviation settlement mechanism (DSM) and scheduling


purpose, it is advised to consider previous latest available
schedules if a generator fail to submit schedules upto 10 days.
Done by Climate Connect. TSTRANSCO will initiate testing of this point which
3 Scheduling tool( DSM) After 10 days, schedules shall be considered as zero for DSM.
will take a time period of 10 consecutive days.
Ushas has submitted intraday revision after a gap of more than
10 days, no machine generated schedule was observed when
checked after 3 days eventhough it was within 10 days.
Climate Connect shall provide training on F&S modules to HEIL engineers for 10
4 Training
mandays.
It was agreed by HEIL/ Climate connect to complete all the SAVT pending points
as per MOM dt 8th Sept 2022 (along with List 1 and List 2) and the points
5 SAVT MOM points
communicted thereafter (minor points list) within 30 days of operational
acceptance.
It was agreed that once Provisional Taking Over is confirmed, the
6 Commercialisation of FSP's commercialisation of FSPs shall be completed by Climate Connect within 1
week.

As discussed Climate Connect to ensure that the F&S application redundancy on


7 F&S application redundancy
FCT and web servers. Kindly confirm.
All documents related to REMC project as per the technical Climate Connect to share the final revisions of the training documents and
8 Project Documentation
specification shall be handed over to TSSLDC. operation manuals within 10 days.
Climate Connect agreed to participate in the meeting with QCAs to resolve the
9 Meeting with QCAs
issues raised by them.

HEIL
Luft),03/2023
Climate Connect