: QB0109
QUOTATION
PROJECT:
ITEMS: Renovation Works (Architecture and MEP) & Add 5F+6F
St.187, SK Tumnob Teuk, Khan Chamkar Mon, Phnom Penh, Cambodia
Date: 24-Feb-2017
QUOTATION
PROJECT:
ITEMS: Renovation Works (Architecture and MEP) & Add 5F+6F
St.187, SK Tumnob Teuk, Khan Chamkar Mon, Phnom Penh, Cambodia
From :
PROJECT:
ITEMS: Renovation Works (Architecture and MEP) & Add 5F+6F
BILL OF QUANTITY SUMMARY
A APPENDIX - A : PRELIMINARY WORKS 7,250.00
B APPENDIX - B : STRUCTURE WORKS 80,788.40
C APPENDIX - C : ARCHITECTURE WORKS 84,455.06
D APPENDIX - D: ELECTRICAL AND MECANIC WORKS -
E APPENDIX - E: PLUMBING SYSTEM WORKS -
Note:
a. -This quotation is based on our drawings provided
- Dimension follow drawing if change or deference from actual site
will be establish as variable order (VO)
We trust the above quotation is reasonable and we look forward to your soonest reply.
Please feel free to contact me for further clarification.
Yours sincerely
Prepared By Checked By Confirmed and Accepted By
Page 2 of 11
BILL OF QUANTITY
PROJECT:
ITEMS: Renovation Works (Architecture and MEP) & Add 5F+6F
St.187, SK Tumnob Teuk, Khan Chamkar Mon, Phnom Penh, Cambodia
Date: 24-Feb-2017
APPENDIX - A : PRELIMINARY WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
1 Preliminary Works
1.01 Letter of construction permit lot - 1.00 - 1,500.00 - 1,500.00 1,500.00
1.02 Temporary water and electrical usage (max. 8 moths) lot - 1.00 - 2,000.00 - 2,000.00 2,000.00
1.03 First connection electricity from EDC or upgrade lot - 1.00 - 200.00 - 200.00 200.00
1.04 Mobilize and demobilization fee lot - 1.00 - 300.00 - 300.00 300.00
1.05 Temporary warehose, worker camp and toilet lot - 1.00 150.00 50.00 150.00 50.00 200.00
1.06 Site safty, banner and other notation lot - 1.00 100.00 50.00 100.00 50.00 150.00
1.07 Project Management Fee lot - 1.00 - 2,400.00 - 2,400.00 2,400.00
1.08 As-built drawing lot - 1.00 - 500.00 - 500.00 500.00
Sub-Total 7,250.00
Page 3 of 11
BILL OF QUANTITY
APPENDIX - B : STRUCTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
1 Foundation Works
1.01 Supply and install borepile D:0.5m, 35MPa cylinder test m CPAC, CMC 105.00 82.50 - 8,662.50 - 8,662.50
@BP01
1.02 Supply labor and equipment to remove head of bore pcs - 10.00 - 66.00 - 660.00 660.00
pile max. depth 1.2m
Pilecap Works
Supply and construct:-
1.03 Soil excavation for pile cap lot - 1.00 - 312.50 - 312.50 312.50
1.04 Soil backfill for pile cap lot - 1.00 - 250.00 - 250.00 250.00
1.05 Compaction stone backfill h:0.2m m3 - 5.00 20.70 11.60 103.50 58.00 161.50
1.06 Lean concrete h:0.1m m3 - 3.00 67.20 16.00 201.60 48.00 249.60
1.07 Concrete C35MPa (cylinder test) m3 CPAC, CMC 14.00 88.20 29.00 1,234.80 406.00 1,640.80
1.08 Steel bar SD390MPa for main bar kg V; Pomina 1,925.00 0.60 0.40 1,155.00 770.00 1,925.00
1.09 Formwork by brick m2 - 45.40 6.00 6.50 272.40 295.10 567.50
1.10 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
Sub-Total 15,340.72
2 GF Structure Works
Ground Beam Works
Supply and construct:-
2.01 Soil excavation for ground beam lot - 1.00 - 650.00 - 650.00 650.00
2.02 Soil backfill for ground beam lot - 1.00 - 507.50 - 507.50 507.50
2.03 Compaction stone backfill h:0.2m m3 - 6.00 20.70 11.60 124.20 69.60 193.80
2.04 Lean concrete h:0.1m m3 - 3.00 67.20 16.00 201.60 48.00 249.60
2.05 Concrete C30MPa (cylinder test) m3 CPAC, CMC 17.00 75.60 29.00 1,285.20 493.00 1,778.20
2.06 Steel bar SD390MPa for main bar kg V; Pomina 2,249.00 0.60 0.40 1,349.40 899.60 2,249.00
2.07 Formwork by brick 10cm thk. m2 - 96.90 6.00 6.50 581.40 629.85 1,211.25
2.08 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
GF Column Works
Supply and construct:-
2.16 Concrete C35MPa (cylinder test) m3 CPAC, CMC 6.00 88.20 29.00 529.20 174.00 703.20
2.17 Steel bar SD390MPa for main bar kg V; Pomina 828.00 0.60 0.40 496.80 331.20 828.00
2.18 Formwork by plywood m2 - 61.80 9.60 6.50 593.28 401.70 994.98
2.19 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
Sub-Total 17,741.39
Page 4 of 11
APPENDIX - B : STRUCTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
3 1F Structure Works
1F Beam Works
Supply and construct:-
3.01 Concrete C30MPa (cylinder test) m3 CPAC, CMC 9.00 75.60 29.00 680.40 261.00 941.40
3.02 Steel bar SD390MPa for main bar kg V; Pomina 3,190.00 0.60 0.40 1,914.00 1,276.00 3,190.00
3.03 Formwork by plywood m2 - 23.00 9.60 6.50 220.80 149.50 370.30
1F Slab Works
Supply and construct:-
3.04 Concrete C30MPa (cylinder test) m3 CPAC, CMC 22.00 75.60 29.00 1,663.20 638.00 2,301.20
3.05 Steel bar SD390MPa for main bar kg V; Pomina 2,408.00 0.60 0.40 1,444.80 963.20 2,408.00
3.06 Formwork by plywood m2 - 165.80 9.60 6.50 1,591.68 1,077.70 2,669.38
3.07 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
1F Column Works
Supply and construct:-
3.08 Concrete C30MPa (cylinder test) m3 CPAC, CMC 5.00 75.60 29.00 378.00 145.00 523.00
3.09 Steel bar SD390MPa for main bar kg V; Pomina 814.00 0.60 0.40 488.40 325.60 814.00
3.10 Formwork by plywood m2 - 49.20 9.60 6.50 472.32 319.80 792.12
3.11 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
1F Staircase Works
Supply and construct:-
3.12 Concrete C30MPa (cylinder test) m3 CPAC, CMC 2.00 75.60 29.00 151.20 58.00 209.20
3.13 Steel bar SD390MPa for main bar kg V; Pomina 154.00 0.60 0.40 92.40 61.60 154.00
3.14 Formwork by plywood m2 - 10.60 9.60 6.50 101.76 68.90 170.66
Sub-Total 14,743.26
4 2F Structure Works
2F Beam Works
Supply and construct:-
4.01 Concrete C30MPa (cylinder test) m3 CPAC, CMC 12.00 75.60 29.00 907.20 348.00 1,255.20
4.02 Steel bar SD390MPa for main bar kg V; Pomina 2,915.00 0.60 0.40 1,749.00 1,166.00 2,915.00
4.03 Formwork by plywood m2 - 21.20 9.60 6.50 203.52 137.80 341.32
2F Slab Works
Supply and construct:-
4.04 Concrete C30MPa (cylinder test) m3 CPAC, CMC 21.00 75.60 29.00 1,587.60 609.00 2,196.60
4.05 Steel bar SD390MPa for main bar kg V; Pomina 2,239.00 0.60 0.40 1,343.40 895.60 2,239.00
4.06 Formwork by plywood m2 - 153.60 9.60 6.50 1,474.56 998.40 2,472.96
4.07 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
2F Column Works
Supply and construct:-
4.08 Concrete C30MPa (cylinder test) m3 CPAC, CMC 5.00 75.60 29.00 378.00 145.00 523.00
4.09 Steel bar SD390MPa for main bar kg V; Pomina 814.00 0.60 0.40 488.40 325.60 814.00
4.10 Formwork by plywood m2 - 49.20 - 6.50 - 319.80 319.80
4.11 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
2F Staircase Works
Supply and construct:-
4.12 Concrete C30MPa (cylinder test) m3 CPAC, CMC 2.00 75.60 29.00 151.20 58.00 209.20
4.13 Steel bar SD390MPa for main bar kg V; Pomina 198.00 0.60 0.40 118.80 79.20 198.00
4.14 Formwork by plywood m2 - 23.20 - 6.50 - 150.80 150.80
Sub-Total 13,834.88
5 3F Structure Works
3F Beam Works
Supply and construct:-
5.01 Concrete C30MPa (cylinder test) m3 CPAC, CMC 12.00 75.60 29.00 907.20 348.00 1,255.20
5.02 Steel bar SD390MPa for main bar kg V; Pomina 2,915.00 0.60 0.40 1,749.00 1,166.00 2,915.00
5.03 Formwork by plywood m2 - 21.10 - 6.50 - 137.15 137.15
3F Slab Works
Supply and construct:-
Page 5 of 11
APPENDIX - B : STRUCTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
5.04 Concrete C30MPa (cylinder test) m3 CPAC, CMC 21.00 75.60 29.00 1,587.60 609.00 2,196.60
5.05 Steel bar SD390MPa for main bar kg V; Pomina 2,239.00 0.60 0.40 1,343.40 895.60 2,239.00
5.06 Formwork by plywood m2 - 153.50 - 6.50 - 997.75 997.75
5.07 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
3F Column Works
Supply and construct:-
5.08 Concrete C30MPa (cylinder test) m3 CPAC, CMC 5.00 75.60 29.00 378.00 145.00 523.00
5.09 Steel bar SD390MPa for main bar kg V; Pomina 814.00 0.60 0.40 488.40 325.60 814.00
5.10 Formwork by plywood m2 - 49.20 - 6.50 - 319.80 319.80
5.11 Service pumping truck of concrete time - 1.00 - 100.00 - 100.00 100.00
Sub-Total 11,597.50
6 4F (Roof) Structure Works
4F (Roof) Beam Works
Supply and construct:-
6.01 Concrete C30MPa (cylinder test) m3 CPAC, CMC 11.00 75.60 29.00 831.60 319.00 1,150.60
6.02 Steel bar SD390MPa for main bar kg V; Pomina 2,558.00 0.60 0.40 1,534.80 1,023.20 2,558.00
6.03 Formwork by plywood m2 - 18.60 - 6.50 - 120.90 120.90
Sub-Total 7,530.65
Page 6 of 11
BILL OF QUANTITY
APPENDIX - C : ARCHITECTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
1 Wall and Partition
Brick wall 10cm thk.
Supply and install brick 10cm thk. from floor to bottom
slab.
1.01 Ground floor (GF) m2 - 189.00 5.40 2.70 1,020.60 510.30 1,530.90
1.02 First floor (1F) m2 - 108.00 5.40 2.70 583.20 291.60 874.80
1.03 Second floor (2F) m2 - 54.00 5.40 2.70 291.60 145.80 437.40
1.04 Third floor (3F) m2 - 39.00 5.40 2.70 210.60 105.30 315.90
1.05 Roof floor (RF) m2 - 50.00 5.40 2.70 270.00 135.00 405.00
Internal plastering
Supply material and labor for plastering internal brick
wall both side 20mm thk.
1.10 Ground floor (GF) m2 - 395.00 2.80 1.70 1,106.00 671.50 1,777.50
1.11 First floor (1F) m2 - 404.00 2.80 1.70 1,131.20 686.80 1,818.00
1.12 Second floor (2F) m2 - 350.00 2.80 1.70 980.00 595.00 1,575.00
1.13 Third floor (3F) m2 - 397.00 2.80 1.70 1,111.60 674.90 1,786.50
External plastering
Supply material and labor for plastering internal brick
wall both side 20mm thk.
1.14 Ground floor (GF) m2 - 277.00 2.80 2.70 775.60 747.90 1,523.50
1.15 First floor (1F) m2 - 297.00 2.80 2.70 831.60 801.90 1,633.50
1.16 Second floor (2F) m2 - 251.00 2.80 2.70 702.80 677.70 1,380.50
1.17 Third floor (3F) m2 - 417.00 2.80 2.70 1,167.60 1,125.90 2,293.50
1.18 Roof floor (RF) m2 - 99.00 2.80 2.70 277.20 267.30 544.50
Sub-Total 30,509.00
2 Wall Finish
Internal Painting
Supply and apply emulsion paint white color (not gloss)
by Skim coat+Sealler+Painting color 5years of
2.01 Groundt floor (GF) m2 Jotun 163.00 2.20 1.20 358.60 195.60 554.20
2.02 First floor (1F) m2 Jotun 291.00 2.20 1.20 640.20 349.20 989.40
2.03 Second floor (2F) m2 Jotun 243.00 2.20 1.20 534.60 291.60 826.20
2.04 Third floor (3F) m2 Jotun 367.00 2.20 1.20 807.40 440.40 1,247.80
Page 7 of 11
APPENDIX - C : ARCHITECTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
External Painting
Supply and apply emulsion paint white color (not gloss)
Skim coat+Sealler+Painting color 7years of guaranty
2.08 Ground floor (GF) m2 Jotun 385.00 2.80 1.20 1,078.00 462.00 1,540.00
2.09 First floor (1F) m2 Jotun 244.00 2.80 1.20 683.20 292.80 976.00
2.10 Second floor (2F) m2 Jotun 254.00 2.80 1.20 711.20 304.80 1,016.00
2.11 Third floor (3F) m2 Jotun 387.00 2.80 1.20 1,083.60 464.40 1,548.00
2.12 Roof floor (RF) m2 Jotun 142.00 2.80 1.20 397.60 170.40 568.00
2.13 External Painting (Spay Dot Paint) m2 Jotun 64.00 2.80 2.70 179.20 172.80 352.00
Supply and apply emulsion paint white color (not gloss)
Skim coat+Sealler+Painting color 7years of guaranty
for façade décor
Sub-Total 10,002.20
3 Ceiling Works
Cove ceiling
Supply and install cove ceiling by gypsum 9mm thk.
(ELEPHANT brand) and apply U-90 paint white color.
3.01 Ground floor (GF) m2 - 30.10 6.60 5.80 198.66 174.58 373.24
3.02 First floor (1F) m2 - 23.00 6.60 5.80 151.80 133.40 285.20
3.07 Ground floor (GF) m2 - 5.40 5.50 2.30 29.70 12.42 42.12
3.08 First floor (1F) m2 - 7.10 5.50 2.30 39.05 16.33 55.38
3.09 Second floor (2F) m2 - 7.10 5.50 2.30 39.05 16.33 55.38
3.10 Third floor (3F) m2 - 2.10 5.50 2.30 11.55 4.83 16.38
Sub-Total 4,028.06
4 Floor Finished Works
Floor Tile (Ceramic Tile 60cmx60cm)
Supply and install new ceramic floor tile size 60x60cm
(tile supply by contractor below price 10$/m2)
4.01 Ground floor (GF) m2 - 122.00 16.30 3.90 1,988.60 475.80 2,464.40
4.02 First floor (1F) m2 - 114.00 16.30 3.90 1,858.20 444.60 2,302.80
4.03 Second floor (2F) m2 - 115.00 16.30 3.90 1,874.50 448.50 2,323.00
4.04 Third floor (3F) m2 - 105.00 16.30 3.90 1,711.50 409.50 2,121.00
Page 8 of 11
APPENDIX - C : ARCHITECTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
4.06 First floor (1F) m2 - 29.00 16.30 3.90 472.70 113.10 585.80
4.07 Second floor (2F) m2 - 18.00 16.30 3.90 293.40 70.20 363.60
4.08 Third floor (3F) m2 - 40.00 16.30 3.90 652.00 156.00 808.00
Skirting Tile
Supply and install skirting by new ceramic tile size:
60x10cm (tile supply by contractor below price 10$/m2)
4.15 Ground floor (GF) m - 52.00 3.90 1.30 202.80 67.60 270.40
4.16 First floor (1F) m - 137.00 3.90 1.30 534.30 178.10 712.40
4.17 Second floor (2F) m - 111.00 3.90 1.30 432.90 144.30 577.20
4.18 Third floor (3F) m - 103.00 3.90 1.30 401.70 133.90 535.60
4.19 Roof floor (RF) m - 43.00 3.90 1.30 167.70 55.90 223.60
Wall Tile m2 -
Supply and install new ceramic wall tile size:
(30x60)cm with height H: 1.20m (tile supply by
contractor below price 10$/m2)
4.20 Ground floor (GF) m2 - 36.00 14.30 3.90 514.80 140.40 655.20
4.21 First floor (1F) m2 - 24.00 14.30 3.90 343.20 93.60 436.80
4.22 Second floor (2F) m2 - 24.00 14.30 3.90 343.20 93.60 436.80
4.23 Third floor (3F) m2 - 13.00 14.30 3.90 185.90 50.70 236.60
Marble
Supply and install marble on staircase (marble supply
by contractor below price 40$/m2)
Waterproof
Supply and apply waterproof on slab by Sika Top Seal
107 c/w height H: 0.20m on wall
4.27 Ground floor (GF) m2 - 8.00 8.50 - 68.00 - 68.00
4.28 First floor (1F) m2 - 50.00 8.50 - 425.00 - 425.00
4.29 Second floor (2F) m2 - 37.00 8.50 - 314.50 - 314.50
4.30 Third floor (3F) m2 - 53.00 8.50 - 450.50 - 450.50
4.31 Roof floor (RF) m2 - 111.00 8.50 - 943.50 - 943.50
Sub-Total 22,998.90
5 Door and Window Works
Door Works
5.01 D1:Double Glass Swing Door Size: Set - 1.00 1,458.00 - 1,458.00 - 1,458.00
(W:6.548xH:3.93)m
Supply and install double glass swing door overall size:
(W:2.00xH:2.40)m by tempered glass 10mm thk. c/w
long handle H: 1.2m and glass wall partition normal
clear glass 10mm thk. c/w normal U-channel @ 1F
(main entrance)
Page 9 of 11
APPENDIX - C : ARCHITECTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
5.02 D2:Double Glass Swing Door Size: Set - 2.00 1,120.00 - 2,240.00 - 2,240.00
(W:3.45xH:3.65)m
Supply and install double glass swing door overall size:
(W:1.80xH:2.40)m by tempered glass 10mm thk. c/w
normal handle and framing by rec-aluminum
50x50x1mm Thailand product and glass wall partition
normal clear glass 10mm thk. c/w rec-aluminum
50x50x1mm Thailand product @ 2F (main entrance)
5.03 D3:Single Glass Swing Door Size: Set - 3.00 275.00 - 825.00 - 825.00
(W:1.00xH:2.40)m
Supply and install single glass swing door overall size:
(W:1.00xH:2.40)m by tempered glass 10mm thk. c/w
normal handle and framing by rec-aluminum
50x50x1mm Thailand product and glass wall partition
normal clear glass 10mm thk. c/w rec-aluminum
50x50x1mm Thailand product
5.04 D4:Single Glass Sliding Door Size: Set - 7.00 231.00 - 1,617.00 - 1,617.00
(W:0.90xH:2.10)m
Supply and install single glass sliding door overall size:
(W:0.90xH:2.10)m by tempered glass 10mm thk. c/w
normal handle
5.05 D5:Single Glass Swing Door Size: Set - 3.00 264.00 - 792.00 - 792.00
(W:0.90xH:2.10)m
Supply and install single glass swing door overall size:
(W:0.90xH:2.10)m by tempered glass 10mm thk. c/w
normal handle
5.06 D6:Single Wooden Swing Door Size: Set - 2.00 550.00 - 1,100.00 - 1,100.00
(W:0.90xH:2.15)m
Supply and install single wooden swing door overall
size: (W:0.90xH:2.15)m by HMR wood c/w white spray
paint including normal look and handle
5.07 D7:Single PVC Swing Door Size: (W:0.75xH:2.00)m Set - 4.00 22.00 - 88.00 - 88.00
Supply and install single PVC swing door overall size:
(W:0.75xH:2.0)m by PVC c/w normal look and handle
@ Toilet door
Window Works
5.08 W1: Double Sliding Glass Window m2 - 40.00 31.00 - 1,240.00 - 1,240.00
Size:(W:1.00xH:2.00)m
Supply and install double sliding glass window overall
size: (W:1.00xH:2.00)m by normal clear glass 5mm
thk. c/w aluminum frame Thailand selected original
color as detail drawing
5.09 W2: Fix Glass Size:(W:1.20xH:10.10)m m2 - 12.20 30.00 - 366.00 - 366.00
Supply and install fixed glass overall size:
(W:1.20xH:10.10)m by normal clear glass 10mm thk.
c/w U-Channel frame
5.10 W3: Fix Glass Size:(W:0.70xH:0.50)m m2 - 1.10 30.00 - 33.00 - 33.00
Supply and install double sliding glass window overall
size: (W:0.70xH:0.50)m by normal clear glass 5mm
thk. c/w aluminum frame Thailand selected original
color as detail drawing @ Toilet 1F; 2F; 3F
Glass Works
Partition Glass
Supply and install fix partition glass by normal clear
glass 10mm thk. from floor to bottom slab c/w u-
channel
5.11 Ground floor (GF) m2 - 28.00 30.00 - 840.00 - 840.00
5.12 First floor (1F) m2 - 50.30 30.00 - 1,509.00 - 1,509.00
5.13 Second floor (2F) m2 - 5.10 30.00 - 153.00 - 153.00
Sub-Total 12,261.00
Page 10 of 11
APPENDIX - C : ARCHITECTURE WORKS Unit: US Dollar
Unit Rate Total Price
No. Description Unit Brand Qty. Total
Material Labor Material Labor
6 Handrail
Stainless Steel Handrail
Supply and install metal handrail by stainless steel
Rou-∅76x1.2mm thk. (code: 304) on staircase
6.01 Ground floor (GF) m - 10.00 46.00 - 460.00 - 460.00
6.02 First floor (1F) m - 7.00 46.00 - 322.00 - 322.00
6.03 Second floor (2F) m - 7.00 46.00 - 322.00 - 322.00
Metal Handrail
Supply and install metal handrail by GI-Steel Rec-
50x50x1.2mm c/w matt black spray paint finish
6.04 Second floor (2F) m - 17.10 46.00 - 786.60 - 786.60
6.05 Third floor (3F) m - 15.00 46.00 - 690.00 - 690.00
Page 11 of 11