JO piping TFT

Updated: 28/03/2023 Full close road 510


PT. ETI PIF10 01 Loading unloading
27 Mar – 02 Apr
Full close road 502
Pipe joint
PT. JEL ME05
27 Mar – 02 Apr
Full close road 502
02 Loadig unloading material
14 23-29 Mar

JO piping TFT
Open close road 510
15 Loading unloading
17 03 27 Mar – 02 Apr
BPN 1

Jln. 104 05 04

08 JO piping TFT
Open close road 510
Loading unloading
06 27 Mar – 02 Apr

11
07

09