You are on page 1of 98

ROAD CLOSING RE

ROAD DATE
NO REG. NO. ACTIVITY
NUMBER START FINISH
lowering & loading unloading
1 JO/RCP/X/22/00001 532 21-Oct 26-Oct
material
lowering & loading unloading
2 JO/RCP/X/22/00002 539 21-Oct 26-Oct
material

3 JO/RCP/X/22/00003 522 21-Oct 26-Oct Critical erection mechanical


equipment : Compressor
Installation waller beam of
4 JO/RCP/X/22/00004 532 24-Oct 27-Oct
Drumpit Z-160-08;06
Unloading scrap pile from Area
5 JO/RCP/X/22/00005 523 21-Oct 26-Oct
40-B1

6 JO/RCP/X/22/00006 526 24-Oct 30-Oct Loading unloading material and


pouring concrete
7 JO/RCP/X/22/00007 523 24-Oct 30-Oct Mobilization crane (Moving)
Loading unloading & lowering
8 JO/RCP/X/22/00008 532 24-Oct 30-Oct
material
Loading unloading & lowering
9 JO/RCP/X/22/00009 528 24-Oct 30-Oct material
Transfer material shell plate
10 JO/RCP/X/22/00010 539 22-Oct 27-Oct
from area 44 to 41
Transfer material shell plate
11 JO/RCP/X/22/00011 532 24-Oct 30-Oct from area 44 to 41
Loading unloading crane
12 JO/RCP/X/22/00012 519 24-Oct 30-Oct
component (temporary)
Loading unloading sheet piles
13 JO/RCP/X/22/00013 523 25-Oct 31-Oct from area 39 : Road 523 to area
37 to 47
Loading unloading & lowering
14 JO/RCP/X/22/00014 533 26-Oct 1-Nov material (No more than 1 hour
close road cause main access)
Loading unloading & lowering
15 JO/RCP/X/22/00015 537 26-Oct 1-Nov
material
Loading unloading & lowering
16 JO/RCP/X/22/00016 520 26-Oct 1-Nov
material

17 JO/RCP/X/22/00017 530 26-Oct 1-Nov Loading unloading & lowering


material
Loading unloading & lowering
18 JO/RCP/X/22/00018 519 26-Oct 1-Nov
material
Loading unloading, lowering
19 JO/RCP/X/22/00019 520 25-Oct 31-Oct
material pipe

20 JO/RCP/X/22/00020 531 27-Oct 2-Nov Erection mechanical equipment


21 JO/RCP/X/22/00021 537 26-Oct 1-Nov Loading unloading material
iInstallation waller beam of
22 JO/RCP/X/22/00022 532 28-Oct 3-Nov
drumpit
Loading unloading spool pipe
23 JO/RCP/X/22/00023 532 27-Oct 28-Oct
material
Loading unloading material and
24 JO/RCP/X/22/00024 523 28-Oct 3-Nov
pouring concrete
Loading unloading material and
25 JO/RCP/X/22/00025 525 A 28-Oct 3-Nov
pouring concrete
Sheet piling, loading unloading
26 JO/RCP/X/22/00026 539 28-Oct 3-Nov
relocate and moving pile
27 JO/RCP/X/22/00027 523 27-Oct 2-Nov Loading unloading pipe
28 JO/RCP/X/22/00028 523 28-Oct 3-Nov Unloading sheet pile material
29 JO/RCP/X/22/00029 523 29-Oct 4-Nov Pull out Sheet piles
Loading unloading material and
30 JO/RCP/X/22/00030 532 31-Oct 6-Nov
lowering
Loading unloading material and
31 JO/RCP/X/22/00031 522 31-Oct 6-Nov lowering
Loading unloading material and
32 JO/RCP/X/22/00032 523 31-Oct 6-Nov lowering
Loading unloading material steel
33 JO/RCP/X/22/00033 532 1-Nov 7-Nov structure, ground assembly,
erection
Loading unloading moving and
34 JO/RCP/X/22/00034 523 31-Oct 6-Nov lifting material pipe and pipe
support
35 JO/RCP/X/22/00035 526 1-Nov 7-Nov Excavation at area 31
Loading unloading sheet piles
36 JO/RCP/XI/22/00036 523 1-Nov 7-Nov from area 39 : Road 523 to area
44 & 46
37 JO/RCP/XI/22/00037 525 A 2-Nov 8-Nov Lifting K.O Drum (C-082-53)

38 JO/RCP/XI/22/00038 523 2-Nov 8-Nov


Pouring concrete and loading unloading material

Loading unloading pipe &


39 JO/RCP/XI/22/00039 523 3-Nov 9-Nov
marterial

Loading unloading, moving and


40 JO/RCP/XI/22/00040 539 4-Nov 10-Nov
install sheet piles

Installation sheet pile and


41 JO/RCP/XI/22/00041 537 3-Nov 9-Nov
loading unloading

42 JO/RCP/XI/22/00042 531 3-Nov 9-Nov Lifting mechanical equipment


43 JO/RCP/XI/22/00043 537 4-Nov 10-Nov Loading unloading precast manhole
531, 537,
44 JO/RCP/XI/22/00044 7-Nov 7-Nov Moving crane from Train B to A
539
Loading unloading Container 40
45 JO/RCP/XI/22/00045 542 6-Nov 6-Nov
feet
Loading unloading Container 40
46 JO/RCP/XI/22/00046 519 6-Nov 6-Nov
feet
Loading unloading Container 40
47 JO/RCP/XI/22/00047 519 7-Nov 7-Nov
feet
Loading unloading Container 40
48 JO/RCP/XI/22/00048 525 7-Nov 7-Nov
feet
49 JO/RCP/XI/22/00049 525 7-Nov 13-Nov Loading unoading material
50 JO/RCP/XI/22/00050 532 7-Nov 13-Nov Loading unoading material
51 JO/RCP/XI/22/00051 525 7-Nov 13-Nov Loading unoading material
Erection steel sturcutre (PR-082-
52 JO/RCP/XI/22/00052 522 8-Nov 14-Nov
01)
Erection steel sturcutre (PR-054-
53 JO/RCP/XI/22/00053 UNKNOWN 9-Nov 15-Nov
01)

54 JO/RCP/XI/22/00054 523 8-Nov 14-Nov Loading unloading sheet pile

55 JO/RCP/XI/22/00055 537 9-Nov 15-Nov Loading unloading sheet pile

56 JO/RCP/XI/22/00056 523 8-Nov 14-Nov Loading unloading sheet pile

Civil work : backfill, pouring


57 JO/RCP/XI/22/00057 523 8-Nov 10-Nov concrete
Loading unloading material steel
58 JO/RCP/XI/22/00058 532 8-Nov 14-Nov structure, ground assembly,
erection
Loading unloading precast
59 JO/RCP/XI/22/00059 542 9-Nov 15-Nov
manhole
60 JO/RCP/XI/22/00060 532 9-Nov 13-Nov Loading unloading material
Loading unloading & lowering
61 JO/RCP/XI/22/00061 525 A 10-Nov 16-Nov
material
Loading unloading & lowering
62 JO/RCP/XI/22/00062 520 11-Nov 17-Nov
material

Loading unloading & lowering


63 JO/RCP/XI/22/00063 533 11-Nov 17-Nov
material

Loading unloading & lowering


64 JO/RCP/XI/22/00064 530 11-Nov 17-Nov
material
Loading unloading & lowering
65 JO/RCP/XI/22/00065 537 11-Nov 17-Nov
material
Loading unloading & lowering
66 JO/RCP/XI/22/00066 519 11-Nov 17-Nov
material

67 JO/RCP/XI/22/00067 525 A 10-Nov 16-Nov Excavation dutch bank

68 JO/RCP/XI/22/00068 532 11-Nov 17-Nov Excavation dutch bank


69 JO/RCP/XI/22/00069 519 12-Nov 18-Nov Excavation for FW Line
70 JO/RCP/XI/22/00070 538 11-Nov 11-Nov Loading unloading material : rebar
71 JO/RCP/XI/22/00071 525 10-Nov 16-Nov Pouring mass concrete
72 JO/RCP/XI/22/00072 537 11-Nov 17-Nov Loading unloading material
Loading unloading & Lowering
73 JO/RCP/XI/22/00073 523 11-Nov 17-Nov
material

Loading unloading, sheet pile,


74 JO/RCP/XI/22/00074 539 11-Nov 16-Nov
moving and relocate

Loading unloading & lowering


75 JO/RCP/XI/22/00075 539 11-Nov 16-Nov
material
76 JO/RCP/XI/22/00076 538 11-Nov 11-Nov Pouring concrete 6-10 Qubic
77 JO/RCP/XI/22/00077 525 B 13-Nov 19-Nov Excavation for crossing road
78 JO/RCP/XI/22/00078 523 12-Nov 18-Nov Cutting pile
79 JO/RCP/XI/22/00079 525 11-Nov 17-Nov Lifting Feed Surge Drum
Moving crane from area 40
80 JO/RCP/XI/22/00080 523 12-Nov 12-Nov (STR-052-07-09) to (STR-052-
02,03)
Install waller beam in drumpit :
81 JO/RCP/XI/22/00081 532 12-Nov 18-Nov
(Z-160-06,08)
Loading unloading, moving,
82 JO/RCP/XI/22/00082 525 B 14-Nov 20-Nov lifting, lowering material pipe
83 JO/RCP/XI/22/00083 532 14-Nov 20-Nov Repair drainage
Loading unloading & arrange
84 JO/RCP/XI/22/00084 523 14-Nov 20-Nov
material pipe

85 JO/RCP/XI/22/00085 525 14-Nov 14-Nov Pouring concrete

Loading unloading, ground


86 JO/RCP/XI/22/00086 532 15-Nov 16-Nov
assembly steel structure
Loading unloading & lowering
87 JO/RCP/XI/22/00087 525 15-Nov 21-Nov
material pipe

Loading unloading & lowering


88 JO/RCP/XI/22/00088 532 15-Nov 21-Nov
material pipe

Dumping soil, casting concrete,


89 JO/RCP/XI/22/00089 523 15-Nov 21-Nov loading unloading rebar & scrap
pile
Dumping soil, casting concrete,
90 JO/RCP/XI/22/00090 537 16-Nov 22-Nov loading unloading rebar & scrap
pile
91 JO/RCP/XI/22/00091 523 15-Nov 21-Nov Loading unloading sheet piles

92 JO/RCP/XI/22/00092 531 15-Nov 21-Nov Lifting mechanical equipment

Loading unloading material &


93 JO/RCP/XI/22/00093 522 16-Nov 22-Nov
erection
Erection steel sturcutre (PR-054-
94 JO/RCP/XI/22/00094 UNKNOWN 16-Nov 22-Nov
01)
Loading unloading & lowering
95 JO/RCP/XI/22/00095 523 17-Nov 23-Nov
pipe
Loading unloading & lowering
96 JO/RCP/XI/22/00096 528 16-Nov 22-Nov
material

97 JO/RCP/XI/22/00097 524 16-Nov 22-Nov Loading unloading & lowering


material
Loading unloading & lowering
98 JO/RCP/XI/22/00098 525 A 17-Nov 23-Nov
material
Loading unloading & lowering
99 JO/RCP/XI/22/00099 539 17-Nov 23-Nov
material
Loading unloading material pipe,
100 JO/RCP/XI/22/00100 542 16-Nov 22-Nov
equipment and tools
Loading unloading material pipe,
101 JO/RCP/XI/22/00101 537 16-Nov 22-Nov
equipment and tools
Loading unloading matertial
102 JO/RCP/XI/22/00102 532 16-Nov 19-Nov
pipe

103 JO/RCP/XI/22/00103 532 16-Nov 24-Nov Duct Bank Excavation

104 JO/RCP/XI/22/00104 523 15-Nov 21-Nov Loading unloading spun piles

Loading unloading precast slab


105 JO/RCP/XI/22/00105 542 17-Nov 23-Nov
and fence for bicycle parking lot

106 JO/RCP/XI/22/00106 537 17-Nov 23-Nov Repair drainage


107 JO/RCP/XI/22/00107 523 18-Nov 18-Nov Install spun pile for drainage

Loading unloading material,


108 JO/RCP/XI/22/00108 523 19-Nov 24-Nov pouring concrete and cutting
pile

109 JO/RCP/XI/22/00109 523 18-Nov 19-Nov Loading unloading material


110 JO/RCP/XI/22/00110 525 A 19-Nov 24-Nov Lifting cargo
111 JO/RCP/XI/22/00111 UNKNOWN 19-Nov 24-Nov Loading unloading material
112 JO/RCP/XI/22/00112 532 21-Nov 24-Nov Loading unloading & erection
113 JO/RCP/XI/22/00113 523 21-Nov 27-NovLoading unloading and lowering material
114 JO/RCP/XI/22/00114 525 22-Nov 28-Nov Loading unloading material
115 JO/RCP/XI/22/00115 532 22-Nov 28-NovLoading unloading and lowering material
116 JO/RCP/XI/22/00116 528 23-Nov 29-NovLoading unloading and lowering material
117 JO/RCP/XI/22/00117 524 23-Nov 29-NovLoading unloading and lowering material
118 JO/RCP/XI/22/00118 522 21-Nov 27-Nov Lifting Air Fan Cooler
Loading unloading material,
119 JO/RCP/XI/22/00119 523 22-Nov 28-Nov pouring concrete, excavation
and cutting pile
120 JO/RCP/XI/22/00120 523 22-Nov 28-Nov Loading unloading sheet piles
Loading unloading material,
121 JO/RCP/XI/22/00121 537 23-Nov 29-Nov pouring concrete, excavation
and cutting pile
Loading unloading & erection
122 JO/RCP/XI/22/00122 522 22-Nov 28-Nov
steel structure
Erection steel strucutre :
123 JO/RCP/XI/22/00123 UNKNOWN 22-Nov 28-Nov
stairway

124 JO/RCP/XI/22/00124 523 22-Nov 28-Nov Loading unloading material pipe


125 JO/RCP/XI/22/00125 522 22-Nov 28-Nov Lifting for air fan cooler
Loading unloading & ground
126 JO/RCP/XI/22/00126 532 22-Nov 28-Nov assembly SS
Installation struting beam at
127 JO/RCP/XI/22/00127 532 23-Nov 29-Nov drumpit Z-160
Loading unloading & lowering
128 JO/RCP/XI/22/00128 523 24-Nov 30-Nov
pipe
129 JO/RCP/XI/22/00129 532 24-Nov 30-Nov General civil work
Lifting & assembly
130 JO/RCP/XI/22/00130 525 A 24-Nov 30-Nov
DEISOHEXANIZER Platform
Loading unloading crane
131 JO/RCP/XI/22/00131 439 24-Nov 30-Nov
component (temporary)

132 JO/RCP/XI/22/00132 525 A 24-Nov 30-Nov Loading unloading & lowering


material pipe
Loading unloading & lowering
133 JO/RCP/XI/22/00133 539 24-Nov 30-Nov
material pipe
Loading unloading & lowering
134 JO/RCP/XI/22/00134 520 25-Nov 1-Dec
material pipe
Loading unloading & lowering
135 JO/RCP/XI/22/00135 519 25-Nov 1-Dec
material pipe
Loading unloading & lowering
136 JO/RCP/XI/22/00136 537 25-Nov 1-Dec
material pipe

137 JO/RCP/XI/22/00137 530 25-Nov 1-Dec Loading unloading & lowering


material pipe
Loading unloading & lowering
138 JO/RCP/XI/22/00138 533 25-Nov 1-Dec
material pipe
Loading unloading & install
139 JO/RCP/XI/22/00139 539 24-Nov 30-Nov
sheet piles

140 JO/RCP/XI/22/00140 532 25-Nov 27-Nov Loading unloading, erection pipe

Excavation for crossing road


141 JO/RCP/XI/22/00141 523 25-Nov 1-Dec
pipe FW
Loading unloading material &
142 JO/RCP/XI/22/00142 523 26-Nov 2-Dec
pouring concrete, cutting pile
143 JO/RCP/XI/22/00143 525 26-Nov 26-Nov Pouring concrete
Loading unloading material steel
144 JO/RCP/XI/22/00144 537 26-Nov 2-Dec
structure
Loading unloading material
145 JO/RCP/XI/22/00145 523 26-Nov 2-Dec
structure
Loading unloading material
146 JO/RCP/XI/22/00146 523 27-Nov 27-Nov
structure
Loading unloading & lowering
147 JO/RCP/XI/22/00147 523 1-Dec 7-Dec
pipe

148 JO/RCP/XI/22/00148 523 28-Nov 4-Dec Loading unloading material pipe

Loading unloading, pouring


149 JO/RCP/XI/22/00149 537 29-Nov 5-Dec concrete, excavation, dumping
soil, cutting pile
Loading unloading, pouring
150 JO/RCP/XI/22/00150 523 29-Nov 5-Dec concrete, excavation, dumping
soil, cutting pile

151 JO/RCP/XI/22/00151 523 29-Nov 5-Dec Loading unloading sheet piles


152 JO/RCP/XI/22/00152 532 29-Nov 5-Dec Repair drainage
153 JO/RCP/XI/22/00153 539 1-Dec 7-Dec Loading unloading material
Loading unloading & lowering
154 JO/RCP/XI/22/00154 532 29-Nov 5-Dec
material pipe
Loading unloading & lowering
155 JO/RCP/XI/22/00155 525 29-Nov 5-Dec
material pipe
156 JO/RCP/XI/22/00156 525 A 1-Dec 7-Dec Loading unloading material
157 JO/RCP/XI/22/00157 522 30-Nov 6-Dec Erection steel structure
158 JO/RCP/XI/22/00158 UNKNOWN 30-Nov 6-Dec Erection steel structure
Loading unloading material
159 JO/RCP/XI/22/00159 523 29-Nov 5-Dec
piping
Loading unloading install
160 JO/RCP/XI/22/00160 537 30-Nov 6-Dec
formwork (SUMPIT)

161 JO/RCP/XI/22/00161 532 1-Dec 7-Dec General civil work

162 JO/RCP/XI/22/00162 525 A 30-Nov 6-Dec General civil work


163 JO/RCP/XI/22/00163 523 30-Nov 6-Dec Lifting cargo
Ground assembly & lifting air fan
164 JO/RCP/XI/22/00164 522 30-Nov 6-Dec
cooler
Assembly materil & lifting
165 JO/RCP/XI/22/00165 525 A 1-Dec 7-Dec
Deisohexanizer Platform
166 JO/RCP/XI/22/00166 330 1-Dec 7-Dec Civil work
Loading unloading and lowering
167 JO/RCP/XI/22/00167 528 1-Dec 7-Dec
material
Loading unloading and lowering
168 JO/RCP/XI/22/00168 533 2-Dec 8-Dec
material
Loading unloading and lowering
169 JO/RCP/XI/22/00169 520 2-Dec 8-Dec
material
Loading unloading and lowering
170 JO/RCP/XI/22/00170 519 2-Dec 8-Dec
material
Loading unloading and lowering
171 JO/RCP/XI/22/00171 537 2-Dec 8-Dec
material
Loading unloading and lowering
172 JO/RCP/XI/22/00172 530 2-Dec 8-Dec
material
Loading unloading material,
173 JO/RCP/XI/22/00173 523 3-Dec 9-Dec pouring concrete and cutting
pile

174 JO/RCP/XI/22/00174 532 2-Dec 8-Dec Excavation and pouring concrete


175 JO/RCP/XI/22/00175 533 2-Dec 8-Dec Excavation for firewater pipeline
Loading unloading and lowering
176 JO/RCP/XI/22/00176 UNKNOWN 2-Dec 8-Dec material

177 JO/RCP/XI/22/00177 532 2-Dec 5-Dec Loading unloading and erection

Install manhole, loading


178 JO/RCP/XI/22/00178 537 2-Dec 4-Dec
unloading manhole
Moving crawler crane 80 ton
179 JO/RCP/XI/22/00179 523 3-Dec 6-Dec from area 40 to 31
Moving crawler crane 80 ton
180 JO/RCP/XI/22/00180 523 4-Dec 7-Dec
from area 31 to 29
181 JO/RCP/XI/22/00181 538 3-Dec 3-Dec Loading unloading rebar
182 JO/RCP/XI/22/00182 532 3-Dec 9-Dec Loading unloading material SS
Installation of road crossing
183 JO/RCP/XI/22/00183 523 4-Dec 10-Dec
drainage
Loading unloading material steel
184 JO/RCP/XI/22/00184 523 5-Dec 11-Dec
structure
Loading unloading material steel
185 JO/RCP/XI/22/00185 537 5-Dec 11-Dec
structure
Loading unloading & lowering
186 JO/RCP/XI/22/00186 524 5-Dec 11-Dec
material pipe

187 JO/RCP/XI/22/00187 523 5-Dec 11-Dec Loading unloading material pipe


and support
Excavation & loading unloading
188 JO/RCP/XI/22/00188 526 5-Dec 11-Dec
sheet pile
Loading unloading, dumping
189 JO/RCP/XI/22/00189 537 6-Dec 12-Dec soil, pouring concrete,
excavation
Loading unloading, dumping
190 JO/RCP/XI/22/00190 523 6-Dec 12-Dec soil, pouring concrete,
excavation
Loading unloading material
191 JO/RCP/XI/22/00191 537 6-Dec 12-Dec
rebar ,sheet pile, spun pile
192 JO/RCP/XI/22/00192 538, 532 7-Dec 13-Dec Crane Mobilization
193 JO/RCP/XI/22/00193 522 7-Dec 13-Dec Lifting Air Fan Cooler
Lifting Depropanizer Reflux
194 JO/RCP/XI/22/00194 532 7-Dec 13-Dec
Drum
195 JO/RCP/XI/22/00195 525 A 6-Dec 7-Dec Pouring concrete
196 JO/RCP/XI/22/00196 520 6-Dec 12-Dec Lifting Air Fan Cooler
197 JO/RCP/XI/22/00197 532 8-Dec 14-Dec Civil work
198 JO/RCP/XI/22/00198 UNKNOWN 8-Dec 14-Dec Install stairway
Erection steel strucutre and
199 JO/RCP/XI/22/00199 522 8-Dec 14-Dec
loading unloading
Excavation, loading unloading,
200 JO/RCP/XI/22/00200 523 8-Dec 14-Dec
sheet piling,
Excavation, loading unloading,
201 JO/RCP/XI/22/00201 530 8-Dec 14-Dec sheet piling,
Loading unloading material,
202 JO/RCP/XI/22/00202 523 10-Dec 16-Dec pouring concrete and cutting
pile
Loading unloading & lowering
203 JO/RCP/XI/22/00203 523 8-Dec 14-Dec
pipe
Loading unloading & lowering
204 JO/RCP/XI/22/00204 523 8-Dec 14-Dec
material pipe
Loading unloading material
205 JO/RCP/XI/22/00205 330 9-Dec 15-Dec
piping

206 JO/RCP/XI/22/00206 532 9-Dec 15-Dec Loading unloading & lowering


material pipe
Loading unloading material
207 JO/RCP/XI/22/00207 519 9-Dec 15-Dec
piping
Loading unloading & lowering
208 JO/RCP/XI/22/00208 528 9-Dec 15-Dec
material pipe
Loading unloading material
209 JO/RCP/XI/22/00209 525 9-Dec 15-Dec
piping
Loading unloading & lowering
210 JO/RCP/XI/22/00210 530 9-Dec 15-Dec
material pipe

211 JO/RCP/XI/22/00211 211 9-Dec 15-Dec Loading unloading & lowering


material pipe

Loading unloading & lowering


212 JO/RCP/XI/22/00212 533 9-Dec 15-Dec
material pipe

Loading unloading & lowering


213 JO/RCP/XI/22/00213 520 9-Dec 15-Dec
material pipe
214 JO/RCP/XI/22/00214 11-Dec 17-Dec Repair drainage
Loading unloading & lowering
215 JO/RCP/XI/22/00215 523 10-Dec 16-Dec
material pipe
Loading unloading material steel
216 JO/RCP/XI/22/00216 523 12-Dec 18-Dec
structure
Loading unloading material steel
217 JO/RCP/XI/22/00217 537 12-Dec 18-Dec
structure
Loading unloading, assembly
218 JO/RCP/XI/22/00218 532 10-Dec 16-Dec
and erection SS
Lifting for FEED SURGE DRUM &
219 JO/RCP/XI/22/00219 520 10-Dec 16-Dec
FLARE KO DRUM
220 JO/RCP/XI/22/00220 539 12-Dec 18-Dec Moving crane to area 47
Loading unloading & erection
221 JO/RCP/XI/22/00221 532 10-Dec 14-Dec
pipe 20

222 JO/RCP/XI/22/00222 526 12-Dec 18-Dec Boom down CC-8800

Loading unloading, pouring


223 JO/RCP/XI/22/00223 523 13-Dec 19-Dec
concrete, excavation
Loading unloading, pouring
224 JO/RCP/XI/22/00224 537 13-Dec 19-Dec
concrete, excavation
Excavation, install rebar &
225 JO/RCP/XI/22/00225 532 15-Dec 21-Dec formwork, install pipe pcv 6
inch, lean concrete and backfill
Moving crane & Assembly CC-
226 JO/RCP/XI/22/00226 532 13-Dec 19-Dec
2500
Loading unloading & Erection
227 JO/RCP/XI/22/00227 531 13-Dec 19-Dec tank
Loading unloading & Erection
228 JO/RCP/XI/22/00228 537 13-Dec 19-Dec
tank
229 JO/RCP/XI/22/00229 229 14-Dec 15-Dec Loading unloading material
Unloading waller beam of
230 JO/RCP/XI/22/00230 532 14-Dec 20-Dec Drumpit
Loading unloading, moving and
231 JO/RCP/XI/22/00231 523 14-Dec 20-Dec
lowering pipe material
Loading unloading spun pile
232 JO/RCP/XI/22/00232 523 15-Dec 21-Dec
material
Loading unloading material
233 JO/RCP/XI/22/00233 538 15-Dec 15-Dec
rebar
Excvavation, loading unloading
234 JO/RCP/XI/22/00234 526 15-Dec 21-Dec
and pouring cocnrete
Loading unloading and erection
235 JO/RCP/XI/22/00235 532 15-Dec 19-Dec
pipe
Install & erection acc for Co-
236 JO/RCP/XI/22/00236 535 15-Dec 21-Dec Boiler Combuster
Loading unloading material,
237 JO/RCP/XI/22/00237 523 17-Dec 23-Dec pouring concrete and cutting
pile
lowering & loading unloading
238 JO/RCP/XI/22/00238 524 15-Dec 21-Dec
material
lowering & loading unloading
239 JO/RCP/XI/22/00239 523 15-Dec 21-Dec
material
lowering & loading unloading
240 JO/RCP/XI/22/00240 528 16-Dec 22-Dec
material
241 JO/RCP/XI/22/00241 532 16-Dec 22-Dec loading unloading material
242 JO/RCP/XI/22/00242 330 16-Dec 22-Dec loading unloading material
243 JO/RCP/XI/22/00243 519 16-Dec 22-Dec loading unloading material
244 JO/RCP/XI/22/00244 525 A 16-Dec 22-Dec loading unloading material
245 JO/RCP/XI/22/00245 520 16-Dec 22-Dec loading unloading material
lowering & loading unloading
246 JO/RCP/XI/22/00246 533 16-Dec 22-Dec
material
lowering & loading unloading
247 JO/RCP/XI/22/00247 537 16-Dec 22-Dec
material
lowering & loading unloading
248 JO/RCP/XI/22/00248 530 16-Dec 22-Dec
material
Erection material piping &
249 JO/RCP/XI/22/00249 535 16-Dec 22-Dec equipment
250 JO/RCP/XI/22/00250 537 19-Dec 25-Dec Loading unloading material SS
Lifting NHT Feed Surge Drum,
251 JO/RCP/XI/22/00251 520 17-Dec 23-Dec
Separator KO Drum
Loading unloading, lifting,
252 JO/RCP/XI/22/00252 525 A 17-Dec 23-Dec
moving lowering pipe 72 inch
253 JO/RCP/XI/22/00253 523 19-Dec 25-Dec Loading unloading material SS
254 JO/RCP/XI/22/00254 537 17-Dec 23-Dec Loading unloading material

Loading unloading, ground


255 JO/RCP/XI/22/00255 532 17-Dec 23-Dec
assembly, erection material SS
Manual digging for crossing road
256 JO/RCP/XI/22/00256 542 18-Dec 24-Dec
cable pipe
257 JO/RCP/XI/22/00257 538 17-Dec 17-Dec Pouring concrete
258 JO/RCP/XI/22/00258 538 19-Dec 19-Dec Pouring concrete
259 JO/RCP/XI/22/00259 542 20-Dec 26-Dec Loading unloading
260 JO/RCP/XI/22/00260 523 19-Dec 25-Dec Loading unloading sheet pile
261 JO/RCP/XI/22/00261 542 19-Dec 25-Dec Moving crane
Loading unloading, pouring
262 JO/RCP/XI/22/00262 537 20-Dec 26-Dec concrete, excavation, soil
dumping, lifting cutting pile
Loading unloading, pouring
263 JO/RCP/XI/22/00263 523 20-Dec 26-Dec concrete, excavation, soil
dumping, lifting cutting pile
Loading unloading pipe to PR-
264 JO/RCP/XI/22/00264 532 20-Dec 26-Dec
064

265 JO/RCP/XI/22/00265 523 20-Dec 23-Dec Moving crawler crane 80 ton

Loading unloading, pouring


266 JO/RCP/XI/22/00266 537 20-Dec 26-Dec
concrete
Lifting of tank (Amine & Sulfur
267 JO/RCP/XI/22/00267 531 21-Dec 27-Dec
Storage)
Lifting for Depropanizer Reflux
268 JO/RCP/XI/22/00268 532 21-Dec 27-Dec
Drum
lowering & loading unloading
269 JO/RCP/XI/22/00269 528 22-Dec 28-Dec
material pipe

270 JO/RCP/XI/22/00270 519 22-Dec 28-Dec Loading unloading material pipe

271 JO/RCP/XI/22/00271 525A 22-Dec 28-Dec Loading unloading material pipe

272 JO/RCP/XI/22/00272 520 22-Dec 28-Dec Loading unloading material pipe

273 JO/RCP/XI/22/00273 523 22-Dec 28-Dec lowering & loading unloading


material pipe

274 JO/RCP/XI/22/00274 524 22-Dec 28-Dec Loading unloading material pipe

lowering & loading unloading


275 JO/RCP/XI/22/00275 537 22-Dec 28-Dec
material pipe
lowering & loading unloading
276 JO/RCP/XI/22/00276 533 22-Dec 28-Dec
material pipe

277 JO/RCP/XI/22/00277 537 22-Dec 28-Dec Loading unloading material

278 JO/RCP/XI/22/00278 535 21-Dec 27-Dec Lifting cargo

Loading unloading crane


279 JO/RCP/XI/22/00279 539 21-Dec 27-Dec
component (temporary)
538, 539,
280 JO/RCP/XI/22/00280 22-Dec 28-Dec Mobilization crane (Moving)
532
281 JO/RCP/XI/22/00281 542 21-Dec 27-Dec Excavation and lowering pipe
Loading unloading & pouring
282 JO/RCP/XI/22/00282 537 22-Dec 28-Dec
concrete

283 JO/RCP/XI/22/00283 528 21-Dec 27-Dec Excavation

284 JO/RCP/XI/22/00284 532 22-Dec 28-Dec Backfill & compact soil


285 JO/RCP/XI/22/00285 532 22-Dec 28-Dec Dismantle CC-2500
286 JO/RCP/XI/22/00286 523 22-Dec 28-Dec Loading unoading material
287 JO/RCP/XI/22/00287 525A 24-Dec 30-Dec Reconfig SCX-1500
288 JO/RCP/XI/22/00288 535 22-Dec 28-Dec Loading unloading, erection
Loading unloading material,
289 JO/RCP/XI/22/00289 523 24-Dec 30-Dec cutting pile and pouring
concrete
Loading unloading, ground
290 JO/RCP/XI/22/00290 532 24-Dec 30-Dec
assembly, erection material SS
Loading unloading & lowering
291 JO/RCP/XI/22/00291 542 23-Dec 29-Dec
pipe
292 JO/RCP/XI/22/00292 526 23-Dec 29-Dec Transport crane
Loading unloading material steel
293 JO/RCP/XI/22/00293 523 26-Dec 1-Jan
structure
Loading unloading material steel
294 JO/RCP/XI/22/00294 537 26-Dec 1-Jan
structure
Loading unloading, dumping
295 JO/RCP/XI/22/00295 523 27-Dec 2-Jan soil, pouring concrete,
excavation
Loading unloading, dumping
296 JO/RCP/XI/22/00296 537 27-Dec 2-Jan soil, pouring concrete,
excavation
Loading unloading & lowering
297 JO/RCP/XI/22/00297 537 27-Dec 2-Jan
pipe
Transfer material shell plate
298 JO/RCP/XI/22/00298 532 27-Dec 2-Jan
from area 44 to 41
299 JO/RCP/XI/22/00299 542 28-Dec 3-Jan Excavation for FW Line

Excavation, laoding unloading,


300 JO/RCP/XI/22/00300 528, 524 27-Dec 2-Jan
dumping soil and concrete work

301 JO/RCP/XI/22/00301 528 28-Dec 3-Jan Excavation work

Loading unloading material


302 JO/RCP/XI/22/00302 523 28-Dec 3-Jan
spool pipe
303 JO/RCP/XI/22/00303 533 29-Dec 4-Jan Loading unloading material
304 JO/RCP/XI/22/00304 537 29-Dec 4-Jan Loading unloading material
Lowering & loading unloading
305 JO/RCP/XI/22/00305 530 29-Dec 4-Jan
material
Lowering & loading unloading
306 JO/RCP/XI/22/00306 524 29-Dec 4-Jan
material
Lowering & loading unloading
307 JO/RCP/XI/22/00307 528 29-Dec 4-Jan
material

308 JO/RCP/XI/22/00308 523 29-Dec 4-Jan Lowering & loading unloading


material
309 JO/RCP/XI/22/00309 525A 29-Dec 4-Jan Loading unloading material
310 JO/RCP/XI/22/00310 519 29-Dec 4-Jan Loading unloading material
311 JO/RCP/XI/22/00311 520 29-Dec 4-Jan Loading unloading material
Lowering & loading unloading
312 JO/RCP/XI/22/00312 522 30-Dec 5-Jan
material
Lowering & loading unloading
313 JO/RCP/XI/22/00313 542 30-Dec 5-Jan
material
Loading unloading & erection
314 JO/RCP/XI/22/00314 525B 29-Dec 4-Jan pipe 20
Loading unloading marterial
315 JO/RCP/XI/22/00315 528 29-Dec 29-Dec
steel structure
Transport riser from area 22 to
316 JO/RCP/XI/22/00316 525A 29-Dec 30-Dec
39 with SPMT
317 JO/RCP/XI/22/00317 542 29-Dec 4-Jan Loading and lifting cargo
318 JO/RCP/XI/22/00318 539 29-Dec 4-Jan Loading equipment
319 JO/RCP/XI/22/00319 526 29-Dec 4-Jan Loading equipment
320 JO/RCP/XI/22/00320 537 30-Dec 31-Dec Install MANHOLE
Cutting pile, pouring concrete,
321 JO/RCP/XI/22/00321 523 31-Dec 6-Jan
loading unloading
Loading unloading & lowering
322 JO/RCP/XI/22/00322 525 30-Dec 5-Jan pipe material
Loading unloading material steel
323 JO/RCP/XI/22/00323 532 31-Dec 6-Jan
structure

324 JO/RCP/XI/22/00324 520 31-Dec 6-Jan Civil work : duct bank


325 JO/RCP/XI/22/00325 523 1-Jan 1-Jan Loading unloading sheet pile
20-Dec 26-Dec
ROAD CLOSING REGISTRATION
NEED SIKA
AREA SUBCONT ROAD STATUS
YES NO
44 PT. Kokoh Semesta Open Close x

44 PT. Kokoh Semesta Open Close x

28 PT. Yeonhab (SM-02) Full Closed x

41 PT. SSP (CV-03) Full Closed x

40 JO CIVIL - TASK FORCE Open Close x

31 JO CIVIL - TASK FORCE Half Close x


36 SARENS Open Close x
42 PT. Kokoh Semesta Open Close - Full x

29 PT. Kokoh Semesta Open Close - Full x

44 PT. Fajar Eka Youone Open Close - Full x

41 PT. Fajar Eka Youone Open Close - Full x

39 SARENS Open Close x x

39 JO CIVIL - TASK FORCE Open Close - Full x

50 PT. Kokoh Semesta Open Close - Full x x

39 PT. Kokoh Semesta Open Close - Full x x

35 PT. Kokoh Semesta Open Close - Half x x

39 PT. Kokoh Semesta Open Close - Full x x

39 PT. Kokoh Semesta Open Close - Full x x

28 PT. SSP (PIU-02) Open Close - Full x

47 PT. Yeonhab (SM-02) Full Closed x


46 PT. Tekniko Half Close x
41 PT. SSP (CV-03) Half Close x

41 PT. Inbang (SMP-04) Half Close x

39 JO CIVIL - TASK FORCE Half Close x

39 JO CIVIL - TASK FORCE Half Close x

47 PT. Eti Civil (CV-24) Full Closed x


39 PT. Daeah (PIU-03) Half/Full x
46 JO CIVIL - TASK FORCE Half Close x
35 PT. Tekniko Half Close x
Full Closed (Open-
40 PT. Kokoh Semesta x
closed)
Full Closed (Open-
30 PT. Kokoh Semesta closed) x

Full Closed (Open-


29 -30 PT. Kokoh Semesta closed) x

41 PT. Yeonhab (SM-02) Half Close x

40 PT. SSP (PIF-08) Half Close x

31 JO CIVIL - TASK FORCE Half Close x

40 JO CIVIL - TASK FORCE Half Close x

37 PT. Yeonhab (SM-02) Full Close x

40 B1 JO CIVIL - TASK FORCE Full Close x

40 B1 PT. Daeah (PIU-03) Half Close x

47 PT. Eti Civil (CV-24) Full Close x

46 JO CIVIL - TASK FORCE Half Close x

47 PT. Yeonhab (SM-02) Full Close x x


46, 47 PT. Tekniko Half Close x
47 PT. Yeonhab (SM-02) Full Close x
50 PT. Powertech Full Close x

38 PT. Powertech Full Close x

38 PT. Powertech Full Close x x

38 PT. Powertech Half Close x


37 PT. Kokoh Semesta Full Close x
42 PT. Kokoh Semesta Full Close x
35 PT. The Far East (CV-16) Full Close x
28 PT. JEL (SSE-01) Half Close x

29 PT. JEL (SSE-01) Half Close x

35,37,39,4
4,47 JO CIVIL - TASK FORCE Half Close x

46 JO CIVIL - TASK FORCE Half Close x

46 JO CIVIL - TASK FORCE Half Close x

PT. Bahana Cipta Internusa


28 (CV-14) Half Close x

41 PT. Yeonhab (SM-02) Half Close x

50 JO - CIVIL Open Close x x


44 PT. Tekniko Full Close x
37 PT. Kokoh Semesta Full Close - Open Close x

35 PT. Kokoh Semesta Full Close - Open Close x

50 B PT. Kokoh Semesta Full Close - Open Close x x

54 PT. Kokoh Semesta Full Close - Open Close x

51 PT. Kokoh Semesta Full Close - Open Close x x


39 PT. Kokoh Semesta Full Close - Open Close x x

PT. Bahana Cipta Internusa


37, 39 Full Close x
(CV-14)
PT. Bahana Cipta Internusa
42 Full Close x
(CV-14)
39 JO - CIVIL UNDERGROUND Full Close x
42 PT. Powertech Full Close x
35 PT. The Far East (CV-16) Half Close x
46 PT. SSA (SM-02) Half Close x
45 PT. Daeah (PIU-03) Half Close (Open-close) x

47 PT. Eti Civil (CV-24) Half Close (Open-close) x

44 PT. Kokoh Semesta Full Close (Open-Close) x


42 PT. Powertech Full Close x
41, 39 JO - CIVIL UNDERGROUND Full Close x
I-R13 PT. Koin Construction (CV-25) Half Close x
35 PT SARENS (HL-01) Full Close x

40 PT. JEL (SSE-01) Full Close x

41 PT. SSP (CV-03) Half Close x

41 PT. SSP (PIU-02) Full Close x


41, 44 JO - CIVIL Open Close x
40 PT. SSP (PIF-08) Half Close x

38 PT. Powertech Full Close x

41 PT. Yeonhab (SM-02) Half Close x

37 PT. Kokoh Semesta Half Close x

42 PT. Kokoh Semesta Full Close x

40, 46 JO - CIVIL TFT Full & Half Close x

46 JO - CIVIL TFT Half Close x


35,37,39,4
JO - CIVIL TFT Half Close x
7

47 PT. Yeonhab (SM-02) Full Close x

28 PT JEL (SSE-01) Half Close x

29 PT. JEL (SSE-01) Half Close x

45 PT. Daeah (PIU-03) Half Close x

29 PT. Kokoh Semesta Full Close x

31 PT. Kokoh Semesta Full Close x

37 PT. Kokoh Semesta Full Close x

44 PT. Kokoh Semesta Half Close x x

50 PT. JEL(PIF-14) Half Close x x

50 PT. JEL(PIF-14) Half Close x x

41 PT. Inbang (PIF-13) Half Close x

PT. Bahana Cipta Internusa


42 Full Close x
(CV-14)

36, 39 JO - CIVIL Half Close x

50 JO - CIVIL Half Close x x

50, 47 JO - CIVIL Half Close x


PT. Koin Construction (CV-
R12/R13 Half Close x
25)

R12/R13 PT. Koin Construction (CV- Half Close x


25)

PT. Koin Construction (CV-


44 Half Close x
25)
35 PT. Sarens (HL-01) Full Close x
29, 31 PT. Eti Building (BD-02) Half Close x
41 PT. Inbang (PIF-13) Half Close x
29 PT. Kokoh Semesta Full Close x
35 PT. Kokoh Semesta Half Close x
42 PT. Kokoh Semesta Half Close x
29 PT. Kokoh Semesta Half Close x
29 PT. Kokoh Semesta Full Close x
28 PT. Yeonhab (SM-02) Half Close x

40 B1 &
JO CIVIL - TASK FORCE Half Close x
46

35, 37, 39 JO CIVIL - TASK FORCE Half Close x

46 JO CIVIL - TASK FORCE Half Close x

28 PT. JEL (SSE-01) Half Close x

29 PT. JEL (SSE-01) Half Close x

39 PT. Daeah (PIU-03) Half Close x


28 PT. Sarens (HL-01) Half Close x
41 PT. Yeonhab (SM-02) Half Close x

41 PT. SSP (CV-03) Half Close x

45 PT. Daeah (PIU-03) Half Close x


42 PT. Bahana Cipta Internusa (CV-14) Full Close x
37 PT. Yeonhab (SM-02) Half Close x

44 PT. Sarens (HL-01) Half Close x

37 PT. Kokoh Semesta Half Close x

44 PT. Kokoh Semesta Full Close x

35 PT. Kokoh Semesta Half Close x

37 PT. Kokoh Semesta Half Close x

51 PT. Kokoh Semesta Half Close x

54 PT. Kokoh Semesta Half Close x

50 B PT. Kokoh Semesta Full Close x

47 JO CIVIL - TASK FORCE Full Close x

41 PT. Inbang (PIF-13) Half Close x

29 JO CIVIL - UNDERGROUND Full Close x


PT. Koin Construction (CV-
R12/R13 Half Close x
25)
38 PT. Powertech Full Close x
46 PT. SSA (SM-02) Half Close x

44 PT. SSA (SM-02) Half Close x

41 PT. JEL (SSE-01) Half Close x

45 PT. Daeah (PIU-03) Half Close x

29, 31 PT. Kokoh Semesta Half Close x

46 JO CIVIL - TASK FORCE Half Close x

40 B1 - 46 JO CIVIL - TASK FORCE Half Close x

35, 37,39,
JO CIVIL - TASK FORCE Half Close x
47
41, 44 JO CIVIL Half Close x
44 PT. Kokoh Semesta Half Close x
42 PT. Kokoh Semesta Full Close x

37 PT. Kokoh Semesta Full Close x


39 PT. Kokoh Semesta Full Close x
28 PT. JEL (SSE-01) Half Close x
29, 31 PT. JEL (SSE-01) Half Close x
39 PT. Daeah (PIU-03) Half Close x

50 PT. Tekniko Half Close x

PT. Bahana Cipta Internusa


42 Full Close x
(CV-14)
PT. Bahana Cipta Internusa
37, 39 Full Close x
(CV-14)
44 PT. Sarens (HL-01) Full Close x
28 PT. Yeonhab (SM-02) Full Close x

37 PT. Yeonhab (SM-02) Full Close x


47 JO CIVIL - TASK FORCE Full Close x
29 PT. Kokoh Semesta Full Close x
50 B PT. Kokoh Semesta Full Close x

35 PT. Kokoh Semesta Half Close x

39 PT. Kokoh Semesta Half Close x

51 PT. Kokoh Semesta Full Close x

54 PT. Kokoh Semesta Full Close x

R12/R13 PT. Koin Construction (CV-25) Half Close x

41 PT. SSP (CV-03) Half Close x


50, 51 JO CIVIL Full Close x
29, 31 PT. Kokoh Semesta Full Close x

41 PT. Inbang (PIF-13) Half Close x

50 PT. Tekniko Full Close x

40, 31 PT. JEL (SSE-01) Full Close x

31, 29 PT. JEL (SSE-01) Full Close x


42 PT. Powertech Full Close x
41 PT. Yeonhab (SM-02) Half Close x
40, 41 JO CIVIL Half Close x

44 PT. SSA (SM-02) Half Close x

46 PT. SSA (SM-02) Half Close x

29 PT. Kokoh Semesta Full Close x

37 PT. KRD (PIU-02.01) Half Close x

31 JO CIVIL - TASK FORCE Half Close x

46 JO CIVIL - TASK FORCE Half Close x

40 B1, 46 JO CIVIL - TASK FORCE Half Close x


R-80 JO CIVIL - TASK FORCE Half Close x
47 to 41 PT. Yeonhab (SM-02) Full Close x
28 PT. Yeonhab (SM-02) Full Close x
41 PT. Yeonhab (SM-02) Full Close x
38 PT. Powertech Full Close x
28 PT. Sarens (HL-01) Full Close x
PT. Bahana Cipta Internusa
42 Full Close x
(CV-14)
29, 31 PT. JEL (SSE-01) Half Close x
28 PT. JEL (SSE-01) Half Close x

47 JO CIVIL - TASK FORCE Full Close x

35, 37, 39 JO CIVIL - TASK FORCE Half Close x

R12/R13 PT. Koin Construction (CV-25) Half Close x

39 PT. Daeah (PIU-03) Half Close x

29, 31 PT. Kokoh Semesta Full Close x

44 PT. Kokoh Semesta Full Close x

42 PT. Kokoh Semesta Full Close x

39 PT. Kokoh Semesta Half Close x

31 PT. Kokoh Semesta Full Close x

37 PT. Kokoh Semesta Half Close x

54 PT. Kokoh Semesta Full Close x

51 PT. Kokoh Semesta Full Close x

50B PT. Kokoh Semesta Full Close x

35 PT. Kokoh Semesta Full Close x


44, 47, 50 JO CIVIL Open - Close x
45 PT. Daeah (PIU-03) Half Close x
44 PT. SSA (SM-02) Half Close x

46 PT. SSA (SM-02) Half Close x

41 PT. Yeonhab (SM-02) Half Close x

35 PT. Yeonhab (SM-02) Full Close x


47 PT. Yeonhab (SM-02) Full Close x
41 PT. Inbang (PIF-13) Full Close x

36 PT. Sarens (HL-01) Full Close x

40 B, 46 JO CIVIL - TASK FORCE Half Close x

46 JO CIVIL - TASK FORCE Half Close x

PT. Bahana Cipta Internusa


42 (CV-14) Full Close x

41 PT. Sarens (HL-01) Full Close x

47 PT. Yeonhab (SM-02) Full Close x

47 PT. Yeonhab (SM-02) Full Close x


38 PT. Powertech Half Close x
41 PT. SSP (CV-03) Full Close x

37 PT. KRD (PIU-02.01) Half Close x

28, 35 JO CIVIL Half Close x

42 PT. Powertech Full Close x

31 JO CIVIL - TASK FORCE Half Close x

41 PT. Inbang (PIF-13) Half Close x

40 PT. Daeah E&C (SMP-01) Half Close x

R12/R13 PT. Koin Construction (CV- Half Close x


25)

29 PT. Kokoh Semesta Full Close (Open-Close) x


29 PT. Kokoh Semesta Half Close x

29 PT. Kokoh Semesta Full Close (Open-Close) x


29 PT. Kokoh Semesta Half Close (Open-close) x
44 PT. Kokoh Semesta Half Close (Open-close) x
39 PT. Kokoh Semesta Half Close (Open-close) x
37 PT. Kokoh Semesta Half Close (Open-close) x
35 PT. Kokoh Semesta Half Close (Open-close) x
50 B PT. Kokoh Semesta Full Close (Open-Close) x

51 PT. Kokoh Semesta Full Close (Open-Close) x

54 PT. Kokoh Semesta Half Close (Open-close) x

40 PT. Daeah E&C (SMP-01) Half Close (Open-close) x


46 PT. SSA (SM-02) Half Close x
35 PT. Yeonhab (SM-02) Full Close x

37 PT KRD (PIU-02.01) Half Close x


44 PT. SSA (SM-02) Half Close x
PT MIGAS MANDIRI
44, 47 Half Close x
PRATAMA HILIR (TFT)

41 PT. Yeonhab (SM-02) Half Close x

50 JO - ELECTRICAL Full Close x


42 PT. Powertech Full Close x
42 PT. Powertech Full Close x
50 PT. Daeah (PIU-03) Half Close x
35 until
JO CIVIL - TASK FORCE Half Close x
47
40 to 50 PT. Sarens (HL-01) Full Close x

46 JO CIVIL - TASK FORCE Half Close x

40B1 - 46 JO CIVIL - TASK FORCE Half Close x

41 PT. Inbang (PIF-13) Half Close x

29 to 40 PT. JEL (SSE-01) Full Close x

44, 47 PT. MMPH - TASK FORCE Half Close x


47 PT. Yeonhab (SM-02) Full Close x

41 PT. Yeonhab (SM-02) Full Close x

31 PT. Kokoh Semesta Half Close x

39 PT. Kokoh Semesta Half Close x

39 PT. Kokoh Semesta Half Close x

35 PT. Kokoh Semesta Half Close x

29 PT. Kokoh Semesta Full Close x

31 PT. Kokoh Semesta Half Close x

51 PT. Kokoh Semesta Half Close x

50B PT. Kokoh Semesta Full Close x

PT. Kumyi Plant Indonesia


47 Half Close x
(SC-01)

40 JO CIVIL - TASK FORCE Full Close x

44 JO CIVIL - TASK FORCE Full Close x

41 PT. Yeonhab (SM-02) Full Close x


50 JO CIVIL - UNDERGROUND Full Close x
50 PT. Tekniko Half Close x

PT. Encona Inti Industri (CV-


R60 Full Close x
05)

PT. Bahana Cipta Internusa


42 Full Close x
(CV-14)
41 PT. Sarens (HL-01) Full Close x
40 PT. KRD (PIF-08.01) Half Close x
37 PT. KRD (PIF-08.01) Half Close x
40 PT. Daeah E&C (SMP-01) Full Close x

PT. Koin Construction (CV-


R12/R13 Half Close x
25)

41 PT. Yeonhab (SM-02) Half Close x

50 PT. Daeah (PIU-03) Full Close x


36 PT. Sarens (HL-01) Full Close x
44 PT. SSA (SM-02) Half Close x

46 PT. SSA (SM-02) Half Close x

40B1 - 46 JO CIVIL - TASK FORCE Half Close x

46 JO CIVIL - TASK FORCE Half Close x

50 PT. Daeah (PIU-03) Half Close x

41, 44 PT. Fajar Eka Youone Full Close x


50 JO CIVIL - UNDERGROUND Full Close x

31 JO CIVIL - TASK FORCE Half Close x

PT. Encona Inti Industri (CV-


R60 Full Close x
05)

40,41,39 PT. Daeah (PIU-03) Half Close x


50B PT. Kokoh Semesta Half Close (Open-close) x
51 PT. Kokoh Semesta Full Close (Open-Close) x
54 PT. Kokoh Semesta Full Close (Open-Close) x

31 PT. Kokoh Semesta Full Close (Open-Close) x

31 PT. Kokoh Semesta Full Close (Open-Close) x

29 PT. Kokoh Semesta Full Close (Open-Close) x


39 PT. Kokoh Semesta Half Close (Open-close) x
39 PT. Kokoh Semesta Half Close (Open-close) x
35 PT. Kokoh Semesta Half Close (Open-close) x
30 PT. Kokoh Semesta Half Close (Open-close) x

50 PT. Daeah (PIU-03) Full Close (Open-Close) x

41 PT. Inbang (PIF-13) Full Close x

29 PT. JEL (SSE-01) Full Close x

39 PT. Rekind (ME-06) Full Close x


40 PT. Sarens (HL-01) Full Close x
44 PT. Sarens (HL-01) Half Close x
36 PT. Sarens (HL-01) Half Close x
50 PT. Tekniko Half Close x
PT. Koin Construction (CV-
R12/R13 Half Close x
25)

37 PT. Daeah (PIU-03) Half Close x

41 PT. Yeonhab (SM-02) Half Close x

PT. Bahana Cipta Internusa


27, 28 Full Close x
(CV-14)
39 JO CIVIL - TASK FORCE Half Close x
Full Close x
ROAD PERMIT
REMARKS
STATUS

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED
CLOSED
CLOSED

CLOSED

CLOSED

CLOSED

3162/HSSESAFETY/X/2022 CLOSED

CLOSED

3109/HSSESAFETY/X/2022 CLOSED

3106/HSSESAFETY/X/2022 CLOSED

3107/HSSESAFETY/X/2022 CLOSED

3105/HSSESAFETY/X/2022 CLOSED

3104/HSSESAFETY/X/2022 CLOSED

CLOSED

Alternative road : 523, 532,


CLOSED
519
CLOSED
CLOSED

CLOSED

depend on CP position CLOSED

Coordinate with yeonhab &


CLOSED
inbang
Coordinate with JO HSE
CLOSED
Incharge
Open Close CLOSED
CLOSED
CLOSED
Coordinate with PT FEY CLOSED

If between area 27-28 need to


issue SIKA CLOSED

Coordinated with SC's Nearby CLOSED

CLOSED

Coordinated with SC's Nearby CLOSED

CLOSED

Coordinated with FIELD


ENGINEER if FULL CLOSED CLOSED

CLOSED
Shall inform to JO HSE
Incharge if close the road and CLOSED
prepare alternate route

Coordinate with JO HSE


CLOSED
Incharge before close the road

Coordinate with JO HSE


CLOSED
Incharge before close the road

Coordinate with JO HSE


CLOSED
Incharge before close the road

3222/HSSE/SAFETY/XI/2022 CLOSED
CLOSED
Inform to HSE JO prior to start
CLOSED
mobilization
CLOSED

CLOSED

3244/HSSE/SAFETY/XI/2022 CLOSED

CLOSED
CLOSED
CLOSED
CLOSED
CLOSED

CLOSED

Contact JO HSE Incharge to


coordinate with other SC Road
Close Permit before staring CLOSED
work

Contact JO HSE Incharge to


coordinate with other SC Road
CLOSED
Close Permit before staring
work

Contact JO HSE Incharge to


coordinate with other SC Road
CLOSED
Close Permit before staring
work

West side CLOSED

CLOSED

3247/HSSE/SAFETY/XI/2022 CLOSED
CLOSED
CLOSED

CLOSED

If possible, do lowering from


inside area 50 to ensure the CLOSED
alternate road 542 is not block

CLOSED

CLOSED
Lowering only, must reported
to KPB for blocking road CLOSED
duration

CLOSED

Alternative road : 539 CLOSED


CLOSED
Alternative road : 539 CLOSED
CLOSED
CLOSED
CLOSED

Not allowed full closed, inform


JO HSE Incharge before CLOSED
starting closing road
Inform to HSE JO prior to start
CLOSED
mobilization
CLOSED
CLOSED
Only during cutting pile CLOSED
Temporary only CLOSED

1 day only for moving unit CLOSED

CLOSED

CLOSED
Temporary only CLOSED
CLOSED

Full Close during pouring CLOSED


concrete

CLOSED

CLOSED

Start afternoon to prevent


road block & coordination with CLOSED
JO Mech team

Full : Night / Half : Day only


CLOSED
loading unloading

CLOSED
Half Clsoe at Day ONLY CLOSED

Full close max 3 hours, alt road


CLOSED
: 525 A & 519

CLOSED

Temporary only CLOSED

Open Close CLOSED

Open Close CLOSED

Open Close CLOSED

Open Close CLOSED

Open Close CLOSED

SIKA : 3285 CLOSED

SIKA : 3285 CLOSED

CLOSED

CLOSED

Full Close only afrtenoon : 16


CLOSED
WITA

SIKA : 3247 CLOSED

Open Close CLOSED


CLOSED

CLOSED

One Day Only CLOSED


CLOSED
Temporary ROAD CLOSED
3 Days Only CLOSED
Open Close CLOSED
Open Close CLOSED
Open Close CLOSED
Open Close CLOSED
Open Close CLOSED
CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED
CLOSED
CLOSED

Not allowed full closed CLOSED

Open Close CLOSED


CLOSED
CLOSED

CLOSED

Open Close CLOSED

Open Close CLOSED

Open Close CLOSED

Open Close CLOSED

Open Close (Only allowed after lunch time) CLOSED

Open Close CLOSED

Open Close CLOSED

Coordination with other SC's CLOSED

CLOSED

CLOSED
Only allowed closing road,
CLOSED
afternoon only
CLOSED
CLOSED

CLOSED

CLOSED

Open Close CLOSED

Coordinate with Koin Civil & BMI CLOSED

Aware of min-safety distance 1m from Excavation


CLOSED

CLOSED

CLOSED
Open Close CLOSED
Open Close CLOSED
Open Close CLOSED

Open Close CLOSED


Open Close CLOSED
CLOSED
CLOSED
CLOSED

CLOSED

CLOSED

CLOSED
Alternate road 539 & 531 CLOSED
Coordination with other SC's :
CLOSED
ETI SEANTERO & JEL

CLOSED
CLOSED
CLOSED
Only allowed at Saturday & Sunday CLOSED

CLOSED

CLOSED

Alternative road 330 & 523 CLOSED

CLOSED

CLOSED

CLOSED
SIKA : 3366 CLOSED
CLOSED

CLOSED

CLOSED

CLOSED

CLOSED
CLOSED
CLOSED
Open Close CLOSED

CLOSED

CLOSED

Open Close CLOSED

CLOSED

CLOSED

CLOSED

CLOSED
CLOSED
Coordinate with other SC'S CLOSED
CLOSED
CLOSED
CLOSED
CLOSED
CLOSED
CLOSED
CLOSED

CLOSED

CLOSED

CLOSED

Only allowed at lunch time 11-13pm CLOSED

Coordination with other SC's CLOSED

Open Close CLOSED

Open Close CLOSED

Open Close CLOSED

Coordinate with other SC'S CLOSED

CLOSED

Open Close CLOSED

Inform to RU-V Marine/Fire CLOSED


Fighting
Lowering only at 9am-12am,
alternate riad 542 and no CLOSED
closing road at 537

Open Close CLOSED


Open Close CLOSED
Open Close CLOSED
CLOSED

CLOSED

CLOSED

CLOSED
CLOSED
CLOSED

Open full road before start this CLOSED


activity

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED
1 day only CLOSED
CLOSED

CLOSED

Temporary - Open Closed CLOSED

1 day only CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

Coordinate with JO Piping TFT CLOSED


CLOSED

Coordination with another SC's


CLOSED
Surround Area 29-31
CLOSED
CLOSED
SIKA : 3385 CLOSED
CLOSED
SIKA : 3386 CLOSED
SIKA : 3384 CLOSED

SIKA : 3386 CLOSED

SIKA : 3388 CLOSED

CLOSED
CLOSED
Full close during erection
CLOSED
equipment

CLOSED
CLOSED
CLOSED

CLOSED

allowed 2 hours only, with


CLOSED
alternate road 533 & 537
1 day only CLOSED
1 day only CLOSED
CLOSED
Full close during traveling
CLOSED
crane and must escorting
CLOSED

CLOSED

CLOSED

CLOSED

Full Close at Afternoon time


CLOSED
only

CLOSED
CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

Open Close CLOSED

CLOSED

CLOSED

Open Close CLOSED

CLOSED

Do not closed area 36 for road


CLOSED
alternative

CLOSED

CLOSED
SIKA = 3450 CLOSED
CLOSED

Coordinate with
SARENS/JEL(SSE-01) and KOIN CLOSED
ME

CLOSED
CLOSED
CLOSED
CLOSED
CLOSED

CLOSED

CLOSED

No. Sika : CLOSED


CLOSED
CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED
No. Sika : 3450 CLOSED

CLOSED

CLOSED

CLOSED
OPEN
OPEN
OPEN

Coordination with other SC's to


OPEN
arrange close road priority
Coordination with other SC's to
OPEN
arrange close road priority

OPEN
OPEN
OPEN
OPEN
OPEN

OPEN

OPEN

CLOSED

CLOSED
OPEN
OPEN
OPEN
One Day Only CLOSED
OPEN

OPEN

OPEN

OPEN
CLOSED
OPEN
R
Location Closing
DATE
Road
No. Road Closing
Code Registration Road
Date Issued Date Expired Date Area Number

### (JO/RCP/ISBL/23/I) ### ### ### 40 523


2 (JO/RCP/ISBL/23/I) ### ### ### 41 - 44 523, 532
3 (JO/RCP/ISBL/23/I) ### ### ### 44 523
4 (JO/RCP/ISBL/23/I) ### ### ### 46 537

5 (JO/RCP/ISBL/23/I) ### ### ### 50 542


6 (JO/RCP/ISBL/23/I) ### ### ### 50 537
7 (JO/RCP/ISBL/23/I) ### ### ### 40 - 46 523

8 (JO/RCP/ISBL/23/I) ### ### ### 46 537


9 (JO/RCP/ISBL/23/I) ### ### ### 31 528, 524

10 (JO/RCP/ISBL/23/I) ### ### ### 31 524

11 (JO/RCP/ISBL/23/I) ### ### ### 38 519


12 (JO/RCP/ISBL/23/I) ### ### ### 42 532

13 (JO/RCP/ISBL/23/I) ### ### ### 44 330


14 (JO/RCP/ISBL/23/I) ### ### ### 44 532
15 (JO/RCP/ISBL/23/I) ### ### ### 50 542
16 (JO/RCP/ISBL/23/I) ### ### ### 39,40,41 523
17 (JO/RCP/ISBL/23/I) ### ### ### 41 532
18 (JO/RCP/ISBL/23/I) ### ### ### 37 525-A
19 (JO/RCP/ISBL/23/I) ### ### ### 36 526
20 (JO/RCP/ISBL/23/I) ### ### ### 31 523
21 (JO/RCP/ISBL/23/I) ### ### ### 31 528
22 (JO/RCP/ISBL/23/I) ### ### ### 35 520
23 (JO/RCP/ISBL/23/I) ### ### ### 39 519
24 (JO/RCP/ISBL/23/I) ### ### ### 50B 533
25 (JO/RCP/ISBL/23/I) ### ### ### 51 537
26 (JO/RCP/ISBL/23/I) ### ### ### 54 530
27 (JO/RCP/ISBL/23/I) ### ### ### 29 523

28 (JO/RCP/ISBL/23/I) ### ### ### 31 - 46 523

29 (JO/RCP/ISBL/23/I) ### ### ### 27, 28 520

30 (JO/RCP/ISBL/23/I) ### ### ### 42 538


31 (JO/RCP/ISBL/23/I) ### ### ### 47 531
32 (JO/RCP/ISBL/23/I) ### ### ### 41 531

33 (JO/RCP/ISBL/23/I) ### ### ### 44 523

34 (JO/RCP/ISBL/23/I) ### ### ### 40 535


35 (JO/RCP/ISBL/23/I) ### ### ### 46 537
36 (JO/RCP/ISBL/23/I) ### ### ### 50 537
37 (JO/RCP/ISBL/23/I) ### ### ### 44 537
38 (JO/RCP/ISBL/23/I) ### ### ### 50 542
39 (JO/RCP/ISBL/23/I) ### ### ### 41 532

40 (JO/RCP/ISBL/23/I) ### ### ### 40 523

41 (JO/RCP/ISBL/23/I) ### ### ### 44 330

42 (JO/RCP/ISBL/23/I) ### ### ### 42 532

43 (JO/RCP/ISBL/23/I) ### ### ### 29.4 523

44 (JO/RCP/ISBL/23/I) ### ### ### 31.36 528

45 (JO/RCP/ISBL/23/I) ### ### ### 50 537

46 (JO/RCP/ISBL/23/I) ### ### ### 40 523

47 (JO/RCP/ISBL/23/I) ### ### ### 35 525

48 (JO/RCP/ISBL/23/I) ### ### ### 50 537

49 (JO/RCP/ISBL/23/I) ### ### ### 41 532

50 (JO/RCP/ISBL/23/I) ### ### ### 31 524.528

51 (JO/RCP/ISBL/23/I) ### ### ### 29 523

52 (JO/RCP/ISBL/23/I) ### ### ### 31 528

53 (JO/RCP/ISBL/23/I) ### ### ### 35 520

54 (JO/RCP/ISBL/23/I) ### ### ### 37 519

55 (JO/RCP/ISBL/23/I) ### ### ### 50B 533

56 (JO/RCP/ISBL/23/I) ### ### ### 51 537

57 (JO/RCP/ISBL/23/I) ### ### ### 54 530

58 (JO/RCP/ISBL/23/I) ### ### ### 37 525

59 (JO/RCP/ISBL/23/I) ### ### ### 47 330

60 (JO/RCP/ISBL/23/I) ### ### ### 41 523

61 (JO/RCP/ISBL/23/I) ### ### ### 35 525

62 (JO/RCP/ISBL/23/I) ### ### ### 37 525

63 (JO/RCP/ISBL/23/I) ### ### ### 29 523


64 (JO/RCP/ISBL/23/I) ### ### ### 40 535

65 (JO/RCP/ISBL/23/I) ### ### ### 29 528

66 (JO/RCP/ISBL/23/I) ### ### ### R12/R13 523

67 (JO/RCP/ISBL/23/I) ### ### ### 28 523

68 (JO/RCP/ISBL/23/I) ### ### ### 29 523

69 (JO/RCP/ISBL/23/I) ### ### ### 39 519.531

70 (JO/RCP/ISBL/23/I) ### ### ### 29 518

71 (JO/RCP/ISBL/23/I) ### ### ### 41 532

72 (JO/RCP/ISBL/23/I) ### ### ### 41 525B

73 (JO/RCP/ISBL/23/I) ### ### ### 35 520

74 (JO/RCP/ISBL/23/I) ### ### ### 44 523

75 (JO/RCP/ISBL/23/I) ### ### ### 45 523

76 (JO/RCP/ISBL/23/I) ### ### ### 29.31 528.524

77 (JO/RCP/ISBL/23/I) ### ### ### 50 537

78 (JO/RCP/ISBL/23/I) ### ### ### 50 542

79 (JO/RCP/ISBL/23/I) ### ### ### 41 531

80 (JO/RCP/ISBL/23/I) ### ### ### 46.5 537

81 (JO/RCP/ISBL/23/I) ### ### ### 50 542

82 (JO/RCP/ISBL/23/I) ### ### ### 50 537

83 (JO/RCP/ISBL/23/I) ### ### ### 44 330

84 (JO/RCP/ISBL/23/I) ### ### ### 44 532

85 (JO/RCP/ISBL/23/I) ### ### ### 39,54,44 519,531,537

86 (JO/RCP/ISBL/23/I) ### ### ### 40 523

87 (JO/RCP/ISBL/23/I) ### ### ### 31 524

88 (JO/RCP/ISBL/23/I) ### ### ### 50 537

89 (JO/RCP/ISBL/23/I) ### ### ### 41.44 532

90 (JO/RCP/ISBL/23/I) ### ### ### 47 330

91 (JO/RCP/ISBL/23/I) ### ### ### 39 525A

92 (JO/RCP/ISBL/23/I) ### ### ### 41 532

93 (JO/RCP/ISBL/23/I) ### ### ### 44 523

94 (JO/RCP/ISBL/23/I) ### ### ### 29 528

95 (JO/RCP/ISBL/23/I) ### ### ### 29 518


96 (JO/RCP/ISBL/23/I) ### ### ### 41 523

97 (JO/RCP/ISBL/23/I) ### ### ### 41 525B

98 (JO/RCP/ISBL/23/I) ### ### ### 28 522

99 (JO/RCP/ISBL/23/I) ### ### ### 54 530

100 (JO/RCP/ISBL/23/I) ### ### ### 39 519

101 (JO/RCP/ISBL/23/I) ### ### ### 31 528

102 (JO/RCP/ISBL/23/I) ### ### ### 37 525

103 (JO/RCP/ISBL/23/I) ### ### ### 35 520

104 (JO/RCP/ISBL/23/I) ### ### ### 40 535

105 (JO/RCP/ISBL/23/I) ### ### ### 31 524

106 (JO/RCP/ISBL/23/I) ### ### ### 40 523

107 (JO/RCP/ISBL/23/I) ### ### ### 41 532

108 (JO/RCP/ISBL/23/I) ### ### ### 50 537

109 (JO/RCP/ISBL/23/I) ### ### ### R12/R13 537

110 (JO/RCP/ISBL/23/I) ### ### ### 29.31 523

111 (JO/RCP/ISBL/23/I) ### ### ### 51 537

112 (JO/RCP/ISBL/23/I) ### ### ### 31.36 523

113 (JO/RCP/ISBL/23/I) ### ### ### 29 523

114 (JO/RCP/ISBL/23/I) ### ### ### 28 522

115 (JO/RCP/ISBL/23/I) ### ### ### 44 523

116 (JO/RCP/ISBL/23/I) ### ### ### 41 525 B

117 (JO/RCP/ISBL/23/I) ### ### ### 41 532

118 (JO/RCP/ISBL/23/I) ### ### ### 40 523

119 (JO/RCP/ISBL/23/I) ### ### ### 44.47 330

120 (JO/RCP/ISBL/23/I) ### ### ### 31 528.524

121 (JO/RCP/ISBL/23/I) ### ### ### 40 535

122 (JO/RCP/ISBL/23/I) ### ### ### 40 523

123 (JO/RCP/ISBL/23/I) ### ### ### 35 525

124 (JO/RCP/ISBL/23/I) ### ### ### 40 B 523

125 (JO/RCP/ISBL/23/I) ### ### ### 28 520

126 (JO/RCP/ISBL/23/I) ### ### ### 31.32 524

127 (JO/RCP/ISBL/23/I) ### ### ### 29 522


128 (JO/RCP/ISBL/23/I) ### ### ### 31.32 524

129 (JO/RCP/ISBL/23/I) ### ### ### 29 528

130 (JO/RCP/ISBL/23/I) ### ### ### 41.44 532

131 (JO/RCP/ISBL/23/I) ### ### ### 50 537

132 (JO/RCP/ISBL/23/I) ### ### ### 50 542

133 (JO/RCP/ISBL/23/I) ### ### ### 41 519

134 (JO/RCP/ISBL/23/I) ### ### ### 28.35 520

135 (JO/RCP/ISBL/23/I) ### ### ### 35 525

136 (JO/RCP/ISBL/23/I) ### ### ### 35 523

137 (JO/RCP/ISBL/23/I) ### ### ### 44 523

138 (JO/RCP/ISBL/23/I) ### ### ### 37 525 A

139 (JO/RCP/ISBL/23/I) ### ### ### 47 538

140 (JO/RCP/ISBL/23/I) ### ### ### 37 519

141 (JO/RCP/ISBL/23/I) ### ### ### 54 530

142 (JO/RCP/ISBL/23/I) ### ### ### 31 528

143 (JO/RCP/ISBL/23/I) ### ### ### 35 520

144 (JO/RCP/ISBL/23/I) ### ### ### 37 525

145 (JO/RCP/ISBL/23/I) ### ### ### 39 525

146 (JO/RCP/ISBL/23/I) ### ### ### 29 518

147 (JO/RCP/ISBL/23/I) ### ### ### 31 523

148 (JO/RCP/ISBL/23/I) ### ### ### 41 525 B

149 (JO/RCP/ISBL/23/I) ### ### ### 41 523

150 (JO/RCP/ISBL/23/I) ### ### ### 41 532

151 (JO/RCP/ISBL/23/I) ### ### ### 29 522

152 (JO/RCP/ISBL/23/I) ### ### ### 28 522

153 (JO/RCP/ISBL/23/I) ### ### ### 44 330

154 (JO/RCP/ISBL/23/I) ### ### ### 47 538

155 (JO/RCP/ISBL/23/I) ### ### ### R12/R13 523

156 (JO/RCP/ISBL/23/I) ### ### ### 44 523

157 (JO/RCP/ISBL/23/I) ### ### ### 29 528

158 (JO/RCP/ISBL/23/I) ### ### ### 41 532

159 (JO/RCP/ISBL/23/I) ### ### ### 41 525B


160 (JO/RCP/ISBL/23/I) ### ### ### 35 525A

161 (JO/RCP/ISBL/23/I) ### ### ### 35 525

162 (JO/RCP/ISBL/23/I) ### ### ### 40.45 534

163 (JO/RCP/ISBL/23/I) ### ### ### 50 537

164 (JO/RCP/ISBL/23/I) ### ### ### 45 523

165 (JO/RCP/ISBL/23/I) ### ### ### 40 523

166 (JO/RCP/ISBL/23/I) ### ### ### 29 518

167 (JO/RCP/ISBL/23/I) ### ### ### 44 330

168 (JO/RCP/ISBL/23/I) ### ### ### 44.47 330

169 (JO/RCP/ISBL/23/I) ### ### ### 35.38 525

170 (JO/RCP/ISBL/23/I) ### ### ### 41 525B

171 (JO/RCP/ISBL/23/I) ### ### ### 50 533

172 (JO/RCP/ISBL/23/I) ### ### ### 40 523

173 (JO/RCP/ISBL/23/I) ### ### ### 31.36 523

174 (JO/RCP/ISBL/23/I) ### ### ### 31 524

175 (JO/RCP/ISBL/23/I) ### ### ### 46.5 537

176 (JO/RCP/ISBL/23/I) ### ### ### 40 523

177 (JO/RCP/ISBL/23/I) ### ### ### 37 525A

178 (JO/RCP/ISBL/23/I) ### ### ### 44 523

179 (JO/RCP/ISBL/23/I) ### ### ### 37 523

180 (JO/RCP/ISBL/23/I) ### ### ### 41.44 532

181 (JO/RCP/ISBL/23/I) ### ### ### 50 537

182 (JO/RCP/ISBL/23/I) ### ### ### 35 520

183 (JO/RCP/ISBL/23/I) ### ### ### 37 519

184 (JO/RCP/ISBL/23/I) ### ### ### 31 528

185 (JO/RCP/ISBL/23/I) ### ### ### 44 330

186 (JO/RCP/ISBL/23/I) ### ### ### 37 525

187 (JO/RCP/ISBL/23/I) ### ### ### 29.31 524, 528

188 (JO/RCP/ISBL/23/I) ### ### ### 45.46 UNKNOWN

189 (JO/RCP/ISBL/23/I) ### ### ### 35 523

190 (JO/RCP/ISBL/23/I) ### ### ### 28 520

191 (JO/RCP/ISBL/23/I) ### ### ### 28 522


192 (JO/RCP/ISBL/23/I) ### ### ### 50 542

193 (JO/RCP/ISBL/23/I) ### ### ### 50 537

194 (JO/RCP/ISBL/23/I) ### ### ### 44 523

195 (JO/RCP/ISBL/23/I) ### ### ### 44,45,R13 523

196 (JO/RCP/ISBL/23/I) ### ### ### 41 532

197 (JO/RCP/ISBL/23/I) ### ### ### 29 522

198 (JO/RCP/ISBL/23/I) ### ### ### 36 526

199 (JO/RCP/ISBL/23/I) ### ### ### 37 525A

200 (JO/RCP/ISBL/23/I) ### ### ### 41 525

201 (JO/RCP/ISBL/23/I) ### ### ### 39 525


202 (JO/RCP/ISBL/23/I) ### ### ### 47 330
203 (JO/RCP/ISBL/23/I) ### ### ### 50 542

204 (JO/RCP/ISBL/23/I) ### ### ### 51 A

205 (JO/RCP/ISBL/23/I) ### ### ### 40 523

206 (JO/RCP/ISBL/23/I) ### ### ### 44, 47 330

207 (JO/RCP/ISBL/23/I) ### ### ### 44 523

208 (JO/RCP/ISBL/23/I) ### ### ### 44, 47 537

209 (JO/RCP/ISBL/23/I) ### ### ### 47 538

210 (JO/RCP/ISBL/23/I) ### ### ### 41 523

211 (JO/RCP/ISBL/23/I) ### ### ### 35 525

212 (JO/RCP/ISBL/23/I) ### ### ### 31, 40 523

213 (JO/RCP/ISBL/23/I) ### ### ### 31 524

214 (JO/RCP/ISBL/23/I) ### ### ### 35 525

215 (JO/RCP/ISBL/23/I) ### ### ### 29 528

216 (JO/RCP/ISBL/23/I) ### ### ### R12/R13 523

217 (JO/RCP/ISBL/23/I) ### ### ### 41 525 B

218 (JO/RCP/ISBL/23/I) ### ### ### 41 532

219 (JO/RCP/ISBL/23/I) ### ### ### 37 523

220 (JO/RCP/ISBL/23/I) ### ### ### 31 524

221 (JO/RCP/ISBL/23/I) ### ### ### 29 518

222 (JO/RCP/ISBL/23/I) ### ### ### 50 537

223 (JO/RCP/ISBL/23/I) ### ### ### 44 523


224 (JO/RCP/ISBL/23/I) ### ### ### 40 523

225 (JO/RCP/ISBL/23/I) ### ### ### 29 518

226 (JO/RCP/ISBL/23/I) ### ### ### 39 523

227 (JO/RCP/ISBL/23/I) ### ### ### 40 523

228 (JO/RCP/ISBL/23/I) ### ### ### 46.5 537

229 (JO/RCP/ISBL/23/I) ### ### ### 50 537

230 (JO/RCP/ISBL/23/I) ### ### ### 50 542

231 (JO/RCP/ISBL/23/I) ### ### ### 29 518518

232 (JO/RCP/ISBL/23/I) ### ### ### 37 525 B

233 (JO/RCP/ISBL/23/I) ### ### ### 29.31 528

234 (JO/RCP/ISBL/23/I) ### ### ### 31 528, 524

235 (JO/RCP/ISBL/23/I) ### ### ### 50 542

236 (JO/RCP/ISBL/23/I) ### ### ### 50 537

237 (JO/RCP/ISBL/23/I) ### ### ### 29 528

238 (JO/RCP/ISBL/23/I) ### ### ### 40 535, 542

239 (JO/RCP/ISBL/23/I) ### ### ### 40 INSIDE 523

240 (JO/RCP/ISBL/23/I) ### ### ### 40, 45 534

241 (JO/RCP/ISBL/23/I) ### ### ### 29 523

242 (JO/RCP/ISBL/23/I) ### ### ### 31 528

243 (JO/RCP/ISBL/23/I) ### ### ### 29 518

244 (JO/RCP/ISBL/23/I) ### ### ### R12/R13 523

245 (JO/RCP/ISBL/23/I) ### ### ### 50 542

246 (JO/RCP/ISBL/23/I) ### ### ### 29 518

247 (JO/RCP/ISBL/23/I) ### ### ### 36, 37 523

248 (JO/RCP/ISBL/23/I) ### ### ### 29 523

249 (JO/RCP/ISBL/23/I) ### ### ### 40, 36 527

250 (JO/RCP/ISBL/23/I) ### ### ### 29 518

251 (JO/RCP/ISBL/23/I) ### ### ### 31 523

252 (JO/RCP/ISBL/23/I) ### ### ### 29.31 528

253 (JO/RCP/ISBL/23/I) ### ### ### 46, 50 537

254 (JO/RCP/ISBL/23/I) ### ### ### 37 523

255 (JO/RCP/ISBL/23/I) ### ### ### 46 523


256 (JO/RCP/ISBL/23/I) ### ### ### 28 523

257 (JO/RCP/ISBL/23/I) ### ### ### 29 528

258 (JO/RCP/ISBL/23/I) ### ### ### 50 537

259 (JO/RCP/ISBL/23/I) ### ### ### 50 537

260 (JO/RCP/ISBL/23/I) ### ### ### 46, 50 537

261 (JO/RCP/ISBL/23/I) ### ### ### 50 537

262 (JO/RCP/ISBL/23/I) ### ### ### R12/R13 523

263 (JO/RCP/ISBL/23/I) ### ### ### 29 528

264 (JO/RCP/ISBL/23/I) ### ### ### 40, 45 534

265 (JO/RCP/ISBL/23/I) ### ### ### 31 528, 524

266 (JO/RCP/ISBL/23/I) ### ### ### 29 518

267 (JO/RCP/ISBL/23/I) ### ### ### 31 518

268 (JO/RCP/ISBL/23/I) ### ### ### 36 523

269 (JO/RCP/ISBL/23/I) ### ### ### 45.46 537

270 (JO/RCP/ISBL/23/I) ### ### ### 40 535

271 (JO/RCP/ISBL/23/I) ### ### ### 50 537

272 (JO/RCP/ISBL/23/I) ### ### ### 50 537

273 (JO/RCP/ISBL/23/I) ### ### ### R12/R13 523

274 (JO/RCP/ISBL/23/I) ### ### ### 537

275 (JO/RCP/ISBL/23/I) ### ### ### 40 523

276 (JO/RCP/ISBL/23/I) ### ### ### 40 534

277 (JO/RCP/ISBL/23/I) ### ### ### 40 523

278 (JO/RCP/ISBL/23/III) ### ### ### 36 523

279 (JO/RCP/ISBL/23/III) ### ### ### 29 518

280 (JO/RCP/ISBL/23/III) ### ### ### 31 524, 528

281 (JO/RCP/ISBL/23/III) ### ### ### 28, 31 523

282 (JO/RCP/ISBL/23/III) ### ### ### 46, 50 537

283 (JO/RCP/ISBL/23/III) ### ### ### 36, 37 523

284 (JO/RCP/ISBL/23/III) ### ### ### 31, 28 523

285 (JO/RCP/ISBL/23/III) ### ### ### 45.5 542

286 (JO/RCP/ISBL/23/III) ### ### ### R13 523

287 (JO/RCP/ISBL/23/III) ### ### ### R13 523


288 (JO/RCP/ISBL/23/III) ### ### ### 50 537

289 (JO/RCP/ISBL/23/III) ### ### ### 50 542

290 (JO/RCP/ISBL/23/III) ### ### ### 31 528, 524

291 (JO/RCP/ISBL/23/III) ### ### ### 29 518

292 (JO/RCP/ISBL/23/III) ### ### ### 50B 537

293 (JO/RCP/ISBL/23/III) ### ### ### 31 524

294 (JO/RCP/ISBL/23/III) ### ### ### 46, 50 537

295 (JO/RCP/ISBL/23/III) ### ### ### 50 533

296 (JO/RCP/ISBL/23/III) ### ### ### 50 537

297 (JO/RCP/ISBL/23/III) ### ### ### 46 537

298 (JO/RCP/ISBL/23/III) ### ### ### R-13 523

299 (JO/RCP/ISBL/23/III) ### ### ### R12/R13 523

300 (JO/RCP/ISBL/23/III) ### ### ### 45, 46 535

301 (JO/RCP/ISBL/23/III) ### ### ### 50 537

302 (JO/RCP/ISBL/23/III) ### ### ### 32 524

303 (JO/RCP/ISBL/23/III) ### ### ### R-13 537

304 (JO/RCP/ISBL/23/III) ### ### ### 50 to 31 537 to 523

305 (JO/RCP/ISBL/23/III) ### ### ### 29 518

306 (JO/RCP/ISBL/23/III) ### ### ### 40 523

307 (JO/RCP/ISBL/23/III) ### ### ### 31 524

308 (JO/RCP/ISBL/23/III) ### ### ### 31 524, 528

309 (JO/RCP/ISBL/23/III) ### ### ### 46, 50 537

310 (JO/RCP/ISBL/23/III) ### ### ### R-13 523

311 (JO/RCP/ISBL/23/III) ### ### ### R12/R13 523

312 (JO/RCP/ISBL/23/III) ### ### ### 40 523

313 (JO/RCP/ISBL/23/III) ### ### ### 31 524

314 (JO/RCP/ISBL/23/III) ### ### ### 29 518

315 (JO/RCP/ISBL/23/III) ### ### ### 36 527

316 (JO/RCP/ISBL/23/III) ### ### ### 36 527

317 (JO/RCP/ISBL/23/III) ### ### ### 50 537

318 (JO/RCP/ISBL/23/III) ### ### ### 40 535

319 (JO/RCP/ISBL/23/III) ### ### ### 29 518


320 (JO/RCP/ISBL/23/III) ### ### ### R-13 523

321 (JO/RCP/ISBL/23/III) ### ### ### 50 537

322 (JO/RCP/ISBL/23/III) ### ### ### 50 533

323 (JO/RCP/ISBL/23/III) ### ### ### 40 523

324 (JO/RCP/ISBL/23/III) ### ### ### 40 523

325 (JO/RCP/ISBL/23/III) ### ### ### R-13 523

326 (JO/RCP/ISBL/23/III) ### ### ### 31 524

327 (JO/RCP/ISBL/23/III) ### ### ### 40 523

328 (JO/RCP/ISBL/23/III) ### ### ### 40 Wes site SS-107

329 (JO/RCP/ISBL/23/III) ### ### ### 46, 50 537

330 (JO/RCP/ISBL/23/III) ### ### ### 50 537

331 (JO/RCP/ISBL/23/III) ### ### ### 29 518

332 (JO/RCP/ISBL/23/III) ### ### ### 50 533

333 (JO/RCP/ISBL/23/III) ### ### ### 40 523

334 (JO/RCP/ISBL/23/III) ### ### ### 46 537

335 (JO/RCP/ISBL/23/III) ### ### ### 31 524, 528

336 (JO/RCP/ISBL/23/III) ### ### ### 36 527

337 (JO/RCP/ISBL/23/III) ### ### ### 40 523

338 (JO/RCP/ISBL/23/III) ### ### ### 40 523

339 (JO/RCP/ISBL/23/III) ### ### ### 40 535

340 (JO/RCP/ISBL/23/III) ### ### ### 29 518

341 (JO/RCP/ISBL/23/III) ### ### ### 50 537

342 (JO/RCP/ISBL/23/III) ### ### ### 36 527

343 (JO/RCP/ISBL/23/III) ### ### ### 50 537

344 (JO/RCP/ISBL/23/III) ### ### ### R-13 523

345 (JO/RCP/ISBL/23/III) ### ### ### 31 524

346 (JO/RCP/ISBL/23/III) ### ### ### 45 523

347 (JO/RCP/ISBL/23/III) ### ### ### 40 523

348 (JO/RCP/ISBL/23/IV) ### ### Friday, April 7, 2023 31 526

349 (JO/RCP/ISBL/23/IV) ### ### Friday, April 7, 2023 50 537

350 (JO/RCP/ISBL/23/IV) ### ### Friday, April 7, 2023 40 WRDN

351 (JO/RCP/ISBL/23/IV) ### ### ### 29 518


352 (JO/RCP/ISBL/23/IV) ### ### ### 40 523

353 (JO/RCP/ISBL/23/IV) ### ### ### 36 523

354 (JO/RCP/ISBL/23/IV) ### ### ### 40

355 (JO/RCP/ISBL/23/IV) ### ### ### 36 527

356 (JO/RCP/ISBL/23/IV) ### ### ### 36 527

357 (JO/RCP/ISBL/23/IV) ### ### ### 50, 46 537

358 (JO/RCP/ISBL/23/IV) ### ### ### 29 518

359 (JO/RCP/ISBL/23/IV) ### ### ### R-13 523

360 (JO/RCP/ISBL/23/IV) ### ### ### 31 524

361 (JO/RCP/ISBL/23/IV) ### Friday, April 7, 2023 ### 50 537

362 (JO/RCP/ISBL/23/IV)Friday, April 7, 2023 Friday, April 7, 2023 ### 40 523

363 (JO/RCP/ISBL/23/IV)Friday, April 7, 2023 Friday, April 7, 2023 ### 45 523

364 (JO/RCP/ISBL/23/IV)Friday, April 7, 2023 Friday, April 7, 2023 ### 46 537

365 (JO/RCP/ISBL/23/IV)Friday, April 7, 2023 Friday, April 7, 2023 ### 40 535

366 (JO/RCP/ISBL/23/IV) ### ### ### 40 No Number

367 (JO/RCP/ISBL/23/IV) ### ### ### 50 537

368 (JO/RCP/ISBL/23/IV) ### ### ### 50 537

369 (JO/RCP/ISBL/23/IV) ### ### ### 50 537

370 (JO/RCP/ISBL/23/IV) ### ### ### 40 523

371 (JO/RCP/ISBL/23/IV) ### ### ### 29 518

372 (JO/RCP/ISBL/23/IV) ### ### ### 40 535

373 (JO/RCP/ISBL/23/IV) ### ### ### 40 535

374 (JO/RCP/ISBL/23/IV) ### ### ### 31 524

375 (JO/RCP/ISBL/23/IV) ### ### ### 36 527

376 (JO/RCP/ISBL/23/IV) ### ### ### 50 542

377 (JO/RCP/ISBL/23/IV) ### ### ### 31 524

378 (JO/RCP/ISBL/23/IV) ### ### ### 29 518

379 (JO/RCP/ISBL/23/IV) ### ### ### 50 537

380 (JO/RCP/ISBL/23/IV) ### ### ### 46, 50 542, 535

381 (JO/RCP/ISBL/23/IV) ### ### ### R-13 523

382 (JO/RCP/ISBL/23/IV) ### ### ### 46 537

383 (JO/RCP/ISBL/23/IV) ### ### ### 36 526


384 (JO/RCP/ISBL/23/IV) ### ### ### 50 537

385 (JO/RCP/ISBL/23/IV) ### ### ### 40 -

386 (JO/RCP/ISBL/23/IV) ### ### ### 31 523, 526, 527

387 (JO/RCP/ISBL/23/IV) ### ### ### 36 526

388 (JO/RCP/ISBL/23/IV) ### ### ### 46.5 542, 535

389 (JO/RCP/ISBL/23/IV) ### ### ### 29 518

390 (JO/RCP/ISBL/23/IV) ### ### ### 40 523

391 (JO/RCP/ISBL/23/IV) ### ### ### 50 537

392 (JO/RCP/ISBL/23/IV) ### ### ### 36 527

393 (JO/RCP/ISBL/23/IV) ### ### ### 29 518

394 (JO/RCP/ISBL/23/IV) ### ### ### 40 535

395 (JO/RCP/ISBL/23/IV) ### ### ### 29 518

396 (JO/RCP/ISBL/23/IV) ### ### ### 31 524

397 (JO/RCP/ISBL/23/IV) ### ### ### R-13 523

398 (JO/RCP/ISBL/23/IV) ### ### ### 40 535

399 (JO/RCP/ISBL/23/IV) ### ### ### 40,45,46,50 535, 542

400 (JO/RCP/ISBL/23/IV) ### ### ### 50 537

401 (JO/RCP/ISBL/23/IV) ### ### ### 40 535

402 (JO/RCP/ISBL/23/IV) ### ### ### 29 528


403
404
###
RDMP JO / ISBL - ROAD CLOSING REGISTRATION

PERSONE
Activity (Work Description) Company
Supervisor (by
SC)

JAYUS
Moving crane 80ton from area 40 to area 29 PT. JEL (SSE-01) SUWANDI
Repair drainage (Maintenance) RDMP JO - CIVIL ANANIAS W

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Loading unloading & lowering pipe PT. DAEAH E&C (PIU-03) AYIK P
Loading unloading & lowering pipe PT. DAEAH E&C (PIU-03) AYIK P
Loading unloading, pouring concrete, excavation, dumping soil RDMP JO - TFT CIVIL M. SHOLEH

Loading unloading, pouring concrete, excavation, dumping soil RDMP JO - TFT CIVIL M. SHOLEH
Loading unloading, pouring concrete, excavation, dumping soil RDMP JO - TFT CIVIL MARZUKI

Excavation for Interconnecting R-60 PT. ENCONA INTI INDUSTRI (CV-05) RANDA

Loading unloading material electrical (lightning) & grounding cable PT. SHINBO GUT JO (EL-02) ADE KURNIA
Loading unloading & lowering pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Excavation for FW Line JO CIVIL - UNDERGROUND LUKY
Excavation for FW Line JO CIVIL - UNDERGROUND LUKY
Loading unloading & lowering pipe PT. DAEAH E&C (PIU-03) AYIK P
Loading unloading soil PT. TEKNIKO (CV-02) BUDIYANTO
Loading unloading material piping PT. KRD (PIF-08.01) IMAM PAMBUDI
Loading unloading equipment and load test SL-6000 PT. SARENS (HL-01) SUYANTO
Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading, moving, lowering material pipe & support PT. KRD (PIU-02.01) BIMA CANDRA
PT. KOIN CONSTRUCTION
Pouring concrete, loading unloading and cutting pile BAMBANG ROY
(CV-23)
PT. BAHANA CIPTA
General civil work (install dutch bank) ANGGAR
INTERNUSA (CV-14)
Loading unloading material PT. POWERTECH (BD-02) CAHYADI
Repair drainage (Maintenance) JO CIVIL - UNDERGROUND ANANIAS W
Loading unloading material PT. SSP CV HARTONO
PT. INBANG DUTA FIRZA
Loading unloading material steel structure FAJAR
(SMP-04)
Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) BAGAS
Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN
Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN
Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P
Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P
Loading unloading, ground assembly, erection material steel structure PT. YEONHAB (SM-02) KIKI IRAWAN

Loading unloading, soil dumping, excavation, pouring concrete RDMP JO - TFT CIVIL M SHOLEH

Loading unloading pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading and lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Moving crane 80ton from area 29 to area 40 PT. JEL (SSE-01) JAYUS SUWANDI

Excavation for Interconnecting R-60 PT. ENCONA INTI INDUSTRI (CV-05) RANDA

Loading unloading : hebel PT. POWERTECH (BD-02) CAHYADI

Loading unloading and lowering material pipe PT. DAEAH E&C (PIU-03) BAGAS

Loading unloading material pipe 42 inch using crane kato 55 ton PT. INBANG DUTA FIRZA (PIF-13)
NOVA LUDIANTO

Pulling out sheet piles PT. TEKNIKO (CV-02) ALI RAHMAN

Loading unloading soil PT. TEKNIKO (CV-02) ALI RAHMAN

Excavation, loading unloading, dumping soil and concrete work RDMP JO - TFT CIVIL LINUS. A

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) BAGAS


Pouring concrete, excavation, leveling soil & gravel, loading
RDMP JO - TFT CIVIL HARYO BINTORO
unloading material
Loading unloading material using crane kato 55 ton PT. INBANG DUTA FIRZA (PIF-13) FAJAR

Disposal soil, lifting rebar & formwork, pouring concrete PT. THE FAR EAST (CV-16) M. SALMA

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Moving crane 150 ton from area 29 to area 31 PT. JEL (SSE-01) JAYUS SUWANDI
Loading and lifting cargo PT. SARENS (HL-01) SUYANTO

Loading unloading material : manhole PT. KOIN CONSTRUCTION (CV-23)


AGUS BUDIANTO

Loading unloading material, cutting and pouring concrete PT. KOIN CONSTRUCTION (CV-23)
AGUS BUDIANTO

Loading unloading, moving, lowering material pipe & support PT. KRD (PIU-02.01) NOPRIN

Loading unloading, moving, lowering material pipe & support PT. KRD (PIU-02.01) NOPRIN

Piling work and moving crane PT. ETI CIVIL SYAMSURIANSYAH

Loading unloading material steel structure PT. JEL (SSE-01) BUDIONO

Loading unloading material steel structure, erection PT. YEONHAB (SM-02) KIKI IRAWAN

Loading unloading material PT. INBANG DUTA FIRZA (PIF-13)


NOVA LUDIANTO

Loading unloading material PT. INBANG DUTA FIRZA (PIF-13)


NOVA LUDIANTO

Loading unloading, erection, bolt tightening steel structure material PT. INBANG DUTA FIRZA (SMP-04) SUTOYO

Loading unloading, pouring concrete, excavation, dumping soil RDMP JO - TFT CIVIL M SHOLEH

Loading unloading, pouring concrete, excavation, dumping soil RDMP JO - TFT CIVIL LINUS SEPTA

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading material rebar PT. SSP CV HARTONO

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

loading unloading pipe at laydown PT. JEL (PIF-14) SAMSUL

loading unloading pipe at laydown PT. JEL (PIF-14) SAMSUL

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Moving crane from area 39 to area 44 PT. ETI SPUN PILE (PKG-03) NUR SETYADI

Loading unloading material pipe PT. DAEAH E&C (PIU-03) BAGAS

Duct bank : civil work PT. BAHANA CIPTA INTERNUSA (CV-14)


SUGITO

Loading unloading hseet pile PT. TEKNIKO (CV-02) ALI RAHMAN

Loading unloading material & soil PT. TEKNIKO (CV-02) ALI RAHMAN

Loading unloading, excavation/leveling soil and concrete work RDMP JO - CIVIL ERVAN MAULANA

Loading unloading material scaffolding PT. KUMYI PLANT INDONESIA (SC-02)


ANDI FIRMAN

Loading unloading material pipe PT. INBANG DUTA FIRZA (PIF-13)


NOVA LUDIANTO

Sumpit work, concrete work and loading unloading material PT. THE FAR EAST (CV-16) M. SALMA

Loading unloading material : manhole PT. KOIN CONSTRUCTION (CV-23) MUJIMAN

Loading unloading material PT. JEL (SSE-05) JAYUS SUWANDI


Loading unloading & lowering material pipe PT. KRD (PIU-02.01) NOPRIN

Loading unloading & lowering material pipe PT. KRD (PIU-02.01) NOPRIN

Loading unloading & lowering material pipe PT. KRD (PIU-02.01) NOPRIN

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading and lifting cargo PT. SARENS (HL-01) SUYANTO

Lifting C-054-09 PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Lifting pump PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Loading unloading, moving, lowering material pipe & support PT. KRD (PIU-02.01) SIDIK

Loading unloading material instrument PT. CHANGWON WAWAN

Loading unloading material, cutting pile and pouring concrete PT. KOIN CONSTRUCTION (CV-23) YULIANTO

Movign crane 80 ton PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material pipe & support PT. KRD (PIU-02.01) NOPRIN

Loading unloading material pipe & support and container PT. KRD (PIU-02.01) NOPRIN

Loading unloading, erection, bolt tightening steel structure material PT. INBANG DUTA FIRZA (SMP-04) SUTOYO

Erection, loading unloading material piping PT. INBANG DUTA FIRZA (PIF-13) SAEFANI

Erection, loading unloading material piping PT. INBANG DUTA FIRZA (PIF-13) SAEFANI

Lifting pump PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Loading unloading, cutting pile and pouring concrete RDMP JO - TFT CIVIL SETIYO WIDODO

Excavation, loading unloading, dumping soil and concrete work RDMP JO - TFT CIVIL MARZUKI

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) BAGAS

Loading unloading material pipe PT. DAEAH E&C (PIU-03) BAGAS

Loading unloading material pipe PT. DAEAH E&C (PIU-03) BAGAS

Loading unloading, pouring concrete, excavation, dumping soil RDMP JO - TFT CIVIL M SHOLEH

Excavation for firewater pipeline JO CIVIL - UNDERGROUND LUKY

Excavation for firewater pipeline JO CIVIL - UNDERGROUND LUKY

Loading unloading & erection steel structure PT. BMI MUSLIADI


Civil work : install ducthbank PT. BAHANA CIPTA INTERNUSA (CV-14)
SUGITO

Lifting equipment mechanical = (E-083-05,06,09-A/B) , (A-083-08-A


PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Loading unloading soil & material PT. TEKNIKO (CV-02) ALI RAHMAN

Loading unloading sheet piles PT. TEKNIKO (CV-02) ALI RAHMAN

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading crane components PT. SARENS (HL-01) SUYANTO

Maintenance : repair drainage JO CIVIL ANANIAS W

Loading unloading sheet piles RDMP JO - TFT CIVIL M BAYU

Loading unloading & Install sheet piles RDMP JO - TFT CIVIL PAUL LADJAR

Lifting material at Sumpit, concrete work and soil disposal PT. THE FAR EAST (CV-16) M. SALMA

General erection and install platform PT. YEONHAB (SM-02) PARULIAN

Lifting stack fire heater PT. YEONHAB (SM-02) PARULIAN

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material scaffolding PT. KUMYI PLANT INDONESIA (SC-02)


ANDI FIRMAN

Loading unloading material steel structure PT. JEL (SSE-05) BUDIONO

Loading unloading material steel structure PT. JEL (SSE-05) BUDIONO

Lifting for tank PT. YEONHAB (SM-02) PARULIAN

Moving crane 180 Ton PT. YEONHAB (SM-02) PARULIAN

Loading unloading ,assembly and erection material steel structure PT. YEONHAB (SM-02) PARULIAN

Loading unloading & erection material steel structure PT. BMI AINAYA

Excavation work PT. KRD (PIU-02.01) NOPRIN

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Installation stack including accessories and platform PT. YEONHAB (SM-02) PARULIAN

Loading unloading material & pouring concrete PT. KOIN CONSTRUCTION (CV-23) YULIANTO

Loading unloading material : Rebar/bundle PT. KOIN CONSTRUCTION (CV-23)


AGUS BUDIANTO

Loading unloading material : Rebar/bundle PT. KOIN CONSTRUCTION (CV-23)DARMANTO

Loading unloading material pipe PT. INBANG DUTA FIRZA (PIF-13) SAEFANI

Loading unloading material pipe PT. INBANG DUTA FIRZA (PIF-13) SAEFANI
Loading unloading material pipe PT. INBANG DUTA FIRZA (PIF-13) SAEFANI

Lifting material at Sumpit, concrete work and soil disposal PT. INBANG DUTA FIRZA (SMP-04) ADANG

Excavation for FW Line RDMP JO - CIVIL UNDERGROUND AKBAR

Loading unloading material instrument JO CHANGWON PT ERA WAWAN

Loading unloading material instrument JO CHANGWON PT ERA EDY KUSUMAJATI

General civil work (install dutch bank) PT. BAHANA CIPTA INTERNUSA (CV-14)
LUHUT P

Lifting mechanical equipment : C-054-17 / G-054-14,15/AB PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Loading unloading & lowering material pipe and pipe support PT. KRD (PIU-02.01) DEDY K

Loading unloaidng, pouring concrete, cutting pile SUTEJO

Loading unloading material pipe PT. KRD (PIU-02.01) NOPRIN

General lifting : installation platform & accessories, installation equi PT. YEONHAB (SM-02) PARULIAN

Install pre-cast drainage PT .BAHANA CIPTA INTERNUSA WAHYUDI

General civil work (install ductch bank) PT .BAHANA CIPTA INTERNUSA WAHYUDI

Loading unloading and lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading and lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Loading unloading and pouring concrete RDMP JO - TFT CIVIL M SHOLEH

General lifting , installation platform & accessories deisohexanizer PT. YEONHAB (SM-02) PARULIAN

Loading unloading, erection, bolt tightening steel structure material PT. INBANG DUTA FIRZA (SMP-04) SUTOYO

Loading unloading material piping PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading soil & material PT. TEKNIKO (CV-02) ALI RAHMAN

Loading unloading soil & material, pouring concrete PT. TEKNIKO (CV-02) ALI RAHMAN

Loading unloading pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Excavation, loading unloading, dumping soil and concrete work RDMP JO - TFT CIVIL SONANG

Excavation for firewater pipeline RDMP JO - CIVIL UNDERGROUND LUKY

Install sheet piles & loading unloading RDMP JO - TFT CIVIL PAUL LADJAR

Pouring concrete PT. ETI BUILDING (BD-01) HENDRA

Excavation work PT. KRD (PIU-02.01) NOPRIN


Loading unloading & lowering pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading & lowering pipe PT. DAEAH E&C (PIU-03) AYIK P

Lifting material at Sumpit, concrete work PT. THE FAR EAST (CV-16) M. SALMA

Repair drainage (Maintenance) RDMP JO - CIVIL ANANIAS W

Loading unloading, moving, lowering material pipe & support PT. KRD (PIU-02.01) DEDY K

Loading unloading and erection material steel structure PT. BAKRIE METAL INDUSTRI

Boom down crane CC-2800 for Reconfiguration PT. SARENS (HL-01) SUYANTO

Loading unloading material PT. INBANG DUTA FIRZA (PIF-13)


NOVA LUDIANTO

Loading unloading material PT. INBANG DUTA FIRZA (PIF-13) ARIE REZA

Loading unloading material PT. INBANG DUTA FIRZA (PIF-13) ARIE REZA
Pouring concete, excavation, loading unloading material, soil loading f PT
Excavation & install pre-cast u-ditch PT. BAHANA CIPTA INTERNUSA (CV-14)AKHID

Unloading pre-cast material for U-DITCH PT. BAHANA CIPTA INTERNUSA (CV-14)AKHID

Civil work : install ducthbank (Inside road unit 062-063 PT. BAHANA CIPTA INTERNUSA (CV-14)AKHID

Pouring concrete, loading unloading and cutting pile PT. RECARE SUTEJO

Pouring concrete, loading unloading and cutting pile PT. RECARE SUTEJO

Pouring concrete, loading unloading and cutting pile PT. RECARE SUTEJO

Installation of stack, including accessories & platform PT. YEONHAB (SM-02) PARULIAN

Excavation PT. KRD (PIU-02.01) SIDIK

Loading unloading material, pouring concrete, lifting material at sump PT. THE FAR EAST (CV-16) M. SALMA

Loading unloading & lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material using Tadano GR-300EXL PT. INBANG DUTA FIRZA (PIF-13)
NOVA LUDIANTO
Loading unloading material, pouring concrete, (manhole, rebar
PT. KOIN CONSTRUCTION (CV-23) MUJIMAN
bundle) and backfill
Loading unloading material, pouring concrete, (manhole, rebar
PT. KOIN CONSTRUCTION (CV-23) MUJIMAN
bundle) and backfill
Lifting for installation equipment & loading unloading PT. YEONHAB (SM-02) RAKHA

Loading unloading material pipe PT. INBANG DUTA FIRZA (PIF-13)


FAJAR MASJUDI

Loading unloaidng material pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloaidng material pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading & erection material piping and support PT. DAEAH E&C (SMP-01) RIZKI

Unloading trafo-trasnformer PT. SHINBO GUT JO (EL-02) MUNTOLIP

Loading unloading, erection, bolt tightening steel structure material PT. INBANG DUTA FIRZA (SMP-04) SUTOYO
Moving crawler crane 80 ton from area 40 to area 31 PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading material steel structure PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading material RDMP JO - TFT CIVIL MUSTIKA BAYU

Lifting waste pile, loading unloading RDMP JO - TFT CIVIL WIRA SUCITRA

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Loading unloading material pipe PT. JEL (PIF-14) SAMSUL

Loading unloading material pipe PT. JEL (PIF-14) SAMSUL

Loading unloading lifting cargo PT. SARENS (HL-01) SUYANTO

General erection, install platform & accessories, loading unloading PT. YEONHAB (SM-02) RAKHA

General civil work : install duct bank PT. BAHANA CIPTA INTERNUSA (CV-14)
BAMBANG ROY

Excavation, loading unloading, dumping soil and concrete work RDMP JO - TFT CIVIL SONANG

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading material (rebar, bundle, manhole), pouring cocnret


PT. KOIN CONSTRUCTION (CV-23) MUJIMAN

Boom down, moving crane PT. SARENS (HL-01) SUYANTO

General civil work : install duct bank PT. BAHANA CIPTA INTERNUSA (CV-14)
SUGITO

General civil work : install duct bank PT. BAHANA CIPTA INTERNUSA (CV-14)
SUGITO

Moving crawler crane 80 ton from area 29 to area 40 PT. JEL (SSE-05) JAYUS SUWANDI

Lifting : (E-083-05,06,07-09A/B) PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Erection pipe spool 36 inch at top of piperack RDMP JO - TFT PIPING GILANG

Loading unloading material (rebar, bundle, manhole), pouring cocnret


PT. KOIN CONSTRUCTION (CV-23) YULIANTO

General civil work : install duct bank PT. BAHANA CIPTA INTERNUSA (CV-14)AKHID

Erection pipe spool 37 inch at top side of piperack RDMP JO - TFT PIPING GILANG

Excavation for OSBL Pipeline CWR/FW RDMP JO - CIVIL UNDERGROUND LUKY

Loading unloading material, erection steel structure PT. BMI RESIANTON

Erection steel structure PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading material steel strcuture PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

General civil work : install duct bank PT. BAHANA CIPTA INTERNUSA (CV-14)AKHID

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Loading unloading and lowering material pipe, fit-up, and cutting PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading sheetpile to trailer RDMP JO - TFT CIVIL MUSTIKA BAYU


Excavation for OSBL Pipeline CWR/FW RDMP JO - CIVIL UNDERGROUND LUKY

Loading unloading material and pouring concrete PT. KOIN CONSTRUCTION (CV-23) MUJIMAN

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) AYIK P

Lifting USD Travo PT. SHINBO GUT JO (EL-02) MUNTOLIP

Loading unloading material manhole PT. TEKNIKO (CV-02) HENDRO

Lifting cargo PT. SARENS (HL-01) SUYANTO

Loading unloading material, pouring concrete, cutting pile, backfill PT. KOIN CONSTRUCTION (CV-23) YULIANTO

Loading unloading & lowering pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

General civil work : install duct bank PT. BAHANA CIPTA INTERNUSA (CV-14)
SUGITO

Excavation, loading unloading, dumping soil and concrete work RDMP JO - TFT CIVIL LINUS
PT. KOIN CONSTRUCTION
Ground assembly platform WAHYUDI
(ME-09)
Loading unloading & erection material steel structure PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading Unloading material steel structure PT. SSA (SM-02) GUNAWAN

Moving crane and load test CC-8800 PT. SARENS (HL-01) SUYANTO

Loading unloading sheet piles PT. TEKNIKO (CV-02) HENDRA j

Loading unloading material instrument, tray and cable drum JO CHANGWON PT ERA WIHARIYANTO

Loading unloading material, cutting pile and pouring concrete PT. KOIN CONSTRUCTION (CV-23) YULIANTO

Lifting cargo PT. SARENS (HL-01) SUYANTO

Loading unloading material, assembly anderection material structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Excavation & backfill, pouring concrete PT. TEKNIKO (CV-02) BUDIMAN

Loading unloading material pipe and pipe support PT. KRD (PIF-08.01) RENGGA

Loading unloading material pipe nad lowering pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material steel structure & erection material steel st PT. JEL (SSE-05) JAYUS SUWANDI

Pouring concrete, excavation aloading unloading material and loading RDMP JO - TFT CIVIL LINUS

General civil work : install duct bank PT. BAHANA CIPTA INTERNUSA (CV-14)
BAMBANG S

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Excavation for FW Pipeline RDMP JO - PIPING UNDERGROUND LUKY

Excavation for FW Pipeline RDMP JO - PIPING UNDERGROUND LUKY

Moving crane CC-8800 to reposition lifint CNM PT. SARENS (HL-01) SUYANTO

Loading unloading, assembly & erection material steel structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Pouring concrete, cutting pile, loading unloading material, backfill PT. KOIN CONSTRUCTION (CV-23) YULIANTO
Loading unloading material instrument PT. CHANGWON WAWAN

General civil work : install duct bank (Perpanjangan SIKA - 1) PT. BAHANA CIPTA INTERNUSA (CV-14)AKHID

Excavation for sumpit, loading unloading , pouring concrete and soil RDMP JO - TFT CIVIL LINUS

Loading unloading material steel structure and erection steel structure PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading & lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Install pre-cast drainage PT. BAHANA CIPTA INTERNUSA (CV-14)AKHID

Lifting transformer PT. SHINBO GUT JO (EL-02) KEMAL

Loading unloading sheet piles RDMP JO - TFT CIVIL MUSTIKA BAYU

Loading unloading material, assembly anderection material structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading material, pouring concrete and cutting piles PT. KOIN CONSTRUCTION (CV-23) YULIANTO

Moving crane : CNM Working area PT. SARENS (HL-01) SUYANTO

Loading unloading material instrument, tray, bast frame & cable drum PT. CHANGWON WIHARIYANTO

Pouring concrete, loading unloading material PT. ETI BUILDING (BD-01) NYOMAN

Loading unloading material, assembly anderection material structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Moving crane 150 ton from area 29 to area 31 PT. BAKRIE METAL INDUSTRI RESMIANTON

Loading unloading material steel structure & erection material steel st PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material pipe PT. TRIMITRA WISESA ABADI YUSUF

Excavation, loading unloading soil dumping and concerete pump RDMP JO - TFT CIVIL LINUS

Loading unloading material steel structure PT. SSA (SM-02) GUNAWAN

Loading unloading material, assembly & erection material structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading marterial, pouring concrete and cutting piles PT. KOIN CONSTRUCTION (CV-23) YULIANTO

Loading unloading & lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Lifting C-054-15, 17 PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Loading unloading material piping PT. DAEAH E&C (PIU-03) AYIK P

Boom down for reconfig CC-2800 PT. SARENS (HL-01) SUYANTO

Loading unloading, excavation, pouring concrete and cutting pile PT. RECARE SUTEJO

Moving crane and lifting CC-8800 PT. SARENS (HL-01) SUYANTO

Loading unloading & erection material steel structure PT. JEL (SSE-05) JAYUS SUWANDI
Loading unloading & erection material steel structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading material instrument, tray, bast frame & cable drum PT. CHANGWON WIHARIYANTO

Excavation & backfill, pouring concrete, loading unloading, cutting pi PT. RECARE SUTEJO

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material, pouring concrete and cutting piles PT. KOIN CONSTRUCTION (CV-23) SAMIRIN

Loading unloading, assembly & erection material steel structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading & lifting material pipe PT. TRIMITRA WISESA ABADI YUSUF

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Erection & bolt tightening steel structure (West side of SS-107) PT. SSA (SM-02) GUNAWAN

Erection & bolt tightening steel structure PT. SSA (SM-02) GUNAWAN

Loading unloading material rebar & formwork PT. TEKNIKO (CV-02) ARI

Loading unloading & erection steel structure PT. JEL (SSE-05) JAYUS SUWANDI

Loading unloading, cutting pile and pouring concrete PT. RECARE SUTEJO

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Lifting shell plate & loading unloading shell plate PT. FAJAR EKA YOUONE SUSANTO

Excavation, loading unloading, soil dumping, concrete work (*542 HALF CLOSE)
JO RDMP (TFT-CIVIL) SONANG

Moving crane CC-2800 to Area 22B (TENTATIVE) PT. SARENS (HL-01) SUYANTO

Back fill for FW Pipeline RDMP JO - UG CRYSTIAN

Loading unloading & lowering material pipe PT. KRD (PIU-02.01) SIDIK

Lifting cargo and moving crane PT. SARENS (HL-01) SUYANTO

Lifting : G-054-05 PT. KOIN CONSTRUCTION (ME-09) WAHYUDI

Loading unloading material rebar PT. POWERTECH (BD-02) CAHYADI

Loading unloading pipe PT. DAEAH E&C (PIU-03) BAGAS

Loading unloading material instrument, tray, bast frame & cable drum PT. CHANGWON WIHARIYANTO

Loading unloading, assembly & erection material steel structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading & lowering pipe PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading material, pouring concrete, cutting pile PT. KOIN CONSTRUCTION (CV-23) SAMIRIN

Loading unloading material, pouring concrete, cutting pile PT. KOIN CONSTRUCTION (CV-23) SAMIRIN

Loading unloading & lowering material pipe PT. DAEAH E&C (PIU-03) SULIS

Loading unloading, cutting pile, excavation and pouring concrete PT. RECARE SUTEJO

Erection and bolt tightening steel structure PT. SSA (SM-02) EKO ARIANTO

Loading unloading material steel structure PT. JEL (SSE-05) JAYUS SUWANDI
Loading unloading & lowering pipe material (1 DAY & 2 Hours Only)PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Assembly accessories crane 150 ton (section boom) PT. BAKRIE METAL INDUSTRI RESMIANTON

Inside 40-45 road : Moving crane and lifting PT. SARENS (HL-01) ARJENIS

Install spun piles for road crossing : to support electrical team RDMP JO - CIVIL PILE ANANIAS W

Boom down CC-8800 PT. SARENS (HL-01) SUYANTO

Loading unloading material steel structure PT. SSA (SM-02) EKO ARIANTO

Unloading spool and material (Ocassionally) RDMP JO - TFT PIPING GILANG

Loading unloading, assembly & erection material steel structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading and erection pipe PT. TRIMITRA WISESA ABADI YUSUF

Loading unloading material instrument, tray and cable drum PT. CHANGWON WIHARIYANTO

Loading unloading material, excavation work, pouring concrete, cutting


PT. KOIN CONSTRUCTION (CV-23) SAMIRIN

Loading unloading material, excavation work, pouring concrete, cutting


PT. KOIN CONSTRUCTION (CV-23) SAMIRIN

Loading unloading material shell plate PT. FAJAR EKA YOUONE SUSANTO

Excavation for pipeline UG RDMP JO - CIVIL UNDERGROUND LUKY

Erection & bolt tightening steel structure PT. SSA (SM-02) EKO ARIANTO

Excavation, loading unloading, cutting pile and pouring concrete PT. RECARE SUTOYO

Loading unloading material and dumping soil PT. TEKNIKO (CV-02) HENDRO P

Loading unloading material (1 DAY ONLY) PT. POWERTECH (BD-02) CAHYADI

Loading unloading & lowering material pipe (3 DAYS) PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading material steel structure & erection material steel st PT. JEL (SSE-05) JAYUS SUWANDI

Lifting flue gas line : PT. SARENS (HL-01) SUYANTO

Loading unloading & lowering pipe material PT. KOKOH SEMESTA (PIU-04) MUNAJIR

Loading unloading & lowering pipe material PT. DAEAH E&C (PIU-03) AYIK P

Loading unloading material pipe PT. DAEAH E&C (PIU-03) AYIK P

Manual digging for drainage PT. JEL (PIF-14) MUKLIS

Lifting erection material pipe & loading unloading material pipe PT. TRIMITRA WISESA ABADI GILANG

Unloading pipe spool and material (Occasionally for max 1 hour) RDMP JO - TFT PIPING YUSUF

Loading unloading material instrument : tray, bast frame and cable dr PT. CHANGWON WIHARIYANTO

Assembly boom crane 275 ton PT. DAEAH E&C (SMP-01) SUGIARTO

Loading unloading material, assembly & erection material structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading material shell plate PT. FAJAR EKA YOUONE AGUS MULYONO

Loading unloading & lowering material pipe PT. KOKOH SEMESTA (PIU-04) MUNAJIR
Loading unloading, cutting pile, excavation and pouring concrete and b PT. RECARE SUTEJO

Erection & bolt tightening steel structure (Road between unit 052 - 062/063) PT. SSA (SM-02) EKO ARIANTO

Moving crane 80 ton crawler' PT. JEL (SSE-01) JAYUS SUWANDI

Loading unloaidng, moving, lifting material pipe nad pipe surpport (onl PT. KRD (PIF-08.01) RENGGA

Assembly boom crane 275 ton (3 Days Only) PT. DAEAH E&C (SMP-01) SUGIARTO

Loading unloading material PT. JEL (SSE-01) JAYUS SUWANDI

Loading unloading, nmoving, lifting material pipe and pipe support PT. KRD (PIF-08.01) RENGGA

Loading unloading rebar & formwork and soil PT. TEKNIKO (CV-02) ALI RAHMAN

Boom down CC-8800 PT. SARENS (HL-01) SUYANTO

Lifting and moving crane/preparation PT. SARENS (HL-01) SUYANTO

Lifting flue gas line PT. SARENS (HL-01) SUYANTO

Unloading material piping spool RDMP JO - TFT PIPING GILANG

Loading unloading material pipe PT. TRIMITRA WISESA ABADI M ALI

Loading unloading material, assembly & erection material structure PT. DAEAH E&C (SMP-01) HAFIF PRASETYO

Loading unloading material and spool pipe PT. DAEAH E&C (PIU-03) BAGAS

Assembly boom crane 275 ton PT. DAEAH E&C (SMP-01) SUGIARTO

Loading unloading, cutting pile, excavation, pouring concrete, backfill PT. RECARE SUTEJO

Lifting cargo PT. SARENS (HL-01) SUYANTO

Lifting cargo : Recycle gas compressor PT. SARENS (HL-01) SUYANTO


STRATION

PERSONELL AUTHORITY's SIKA RU-V / KPB


Road Status REMARKS
Permit Holder JO - Area Chief HSE/Rep YES NO
(by SC) Authority/GSI/ SPV

Inform JO HSE Incharge


DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
ANANIAS W BAI KI YONG CHAIRIL ANWAR Half Close - - Temporary
DEAVATI JEON DONG MYOUNG DWI AGUNG Half Close - -
DEAVATI JEON DONG MYOUNG DWI AGUNG Half Close - -

ANITA TIYANI Y CHAIRIL ANWAR Half Close 3456 -


ANITA TIYANI Y CHAIRIL ANWAR Half Close 3452 -
RIFQI PAKSI JANG SUK HYUN DWI AGUNG Half Close - -

RIFQI PAKSI JANG SUK HYUN DWI AGUNG Half Close - -


DAVID GEORGE KIM SOON KYON DWI AGUNG Half Close - -

NOVIA TEGUH DWI AGUNG Full Close - -


Inform JO HSE Incharge
NUR LAILA EKA SEO JEONG GEUN NOEL KUSUMA Half Close - - before closing road

AFFIKAH ADAM NORRIEGA CHAIRIL ANWAR Full Close - - Open/close

AFFIKAH ADAM NORRIEGA CHAIRIL ANWAR Full Close - - Open/close


ADE PUTRA S DWIKY DARMAWANCHAIRIL ANWAR Half Close - -
ADE PUTRA S DWIKY DARMAWANCHAIRIL ANWAR Half Close 3450 -
PRIMA LEE DO HUI NOEL KUSUMA Half Close - -
BAGOES DWI YONG CHUL PARK NOEL KUSUMA Half Close - -
JOLAN RIKY PARK JAE GE NOEL KUSUMA Half Close - -
YOHANES M. FUAD ALI NOEL KUSUMA Full Close - - Open/close
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - Open/close
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - Open/close
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - Open/close
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - Open/close
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - Open/close
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - Open/close
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - Open/close
BIMA CANDRA LEE BO CHAIRIL ANWAR Half Close - -

HARKAT AGUNG LARNO CHAIRIL ANWAR Half Close - -

NIKITA PARK C.H DWI AGUNG Full Close - -

KAFITA PUTRI ASFIANSYAH CHAIRIL ANWAR Full Close - - Open/close


ANANIAS W BAI KI YONG CHAIRIL ANWAR Half Close - - Full Close at Sunday Only
Inform JO HSE Incharge
NUR PUTRI PAUL LEDJAR DWI AGUNG Half Close 40 - before closing road
Inform JO HSE Incharge
LARASATY ASSE NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA FRANKY NOEL KUSUMA Half Close CANCEL before closing road
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close - -
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close - -
ANITA TIYANI Y NOEL KUSUMA Half Close 3452 - EXPIRED SIKA 18 JAN
ANITA TIYANI Y NOEL KUSUMA Half Close 3456 - EXPIRED SIKA 18 JAN
Inform JO HSE Incharge
RUSLINDAH ASSE NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI JANG SUK HYUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANIJEON DONG MYOUNGNOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NOVIA TEGUH. P NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
KAFITA PUTRI ASFIANSYAH NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA KWON JUN HYUK NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RIZKY QILA NIZAR. S NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE KIM SOON KYON DWI AGUNG Half Close - - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Full Close 24 - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Half Close 26 - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Half Close 23 - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Half Close 25 - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Half Close 27 - before closing road
Inform JO HSE Incharge
PRIMA KWON JUN HYUK NOEL KUSUMA Full Close 37 - before closing road
Inform JO HSE Incharge
IRFAN PAMBUDI KU BON MIN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
QILA ROMI S NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ASRI RAMAYANTI AGUSTA PRIADY NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 3453 - before closing road
Inform JO HSE Incharge
RISMA YUNITA LARNO. S NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA LARNO. S NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ASRYAN ADJIE P NOEL KUSUMA Full Close 331 - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RUSLINDAH ASSE NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA RONI SIANIPAR NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA NIZAR. S NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
LARASTY UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI JANG SUK HYUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI KIM SOON KYU NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Half Close 3452 - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Full Close 3456 - before closing road
Inform JO HSE Incharge
NUR PUTRI PAUL LEDJAR NOEL KUSUMA Half Close 63 - before closing road
Inform JO HSE Incharge
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
SILVI PARK JAE GYOUNG NOEL KUSUMA Half Close 61 - before closing road
Inform JO HSE Incharge
SILVI PARK JAE GYOUNG NOEL KUSUMA Half Close 62 - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
EGGY ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ASRIYAN ADJIE P NOEL KUSUMA Full Close 331 - before closing road
Inform JO HSE Incharge
PRIMA KWON JUN HYUK NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
IRFAN PAMBUDI KWON SE HWAN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RAFIE RESALDY H NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA NIZAR. S NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ASRI RAMAYANTI AGUSTA PRIADY NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MICHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA KWON JUN HYUK NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA KWON JUN HYUK NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA KWON JUN HYUK NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close 27 - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close 26 - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close 24 - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 90 - before closing road
Inform JO HSE Incharge
ANGGI PRADITA PARK CHOON HO NOEL KUSUMA - - before closing road
Inform JO HSE Incharge
ANGGI PRADITA PARK CHOON HO NOEL KUSUMA - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NOVI CHARLES NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MICHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close 25 - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
LARASTY ASSE NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ANGGI PRADITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE KIM SOON KYU NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Half Close 114 - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI JANG SUK HYUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
WITO TAFERRYJEON DONG MYOUNGNOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
PEBRIYANTI PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI SURIA ILHAM NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI SURIA ILHAM NOEL KUSUMA Half Close 122 - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Full Close 123 - before closing road
Inform JO HSE Incharge
SYARIFAH IBNU FATONI NOEL KUSUMA Full Close 130 - before closing road
Inform JO HSE Incharge
ANANIAS W BAI KI YONG NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
IRFAN PAMBUDI SHIN JUN YOUNG NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAEK SEUNG NAM SHIN JUN YOUNG NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ASRI AGUSTA P NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close 23 - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RAFIE RESALDY H NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RUSLINDAH HERI GUNAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RUSLINDAH HERI GUNAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
WITO TAFERRYJEON DONG MYOUNGNOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ELISA DEWANTI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
HARKAT AGUNG MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ASRI AGUSTA PRIADY NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
SOFIYAN HADI SHIN DONG JUN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NOVI NICO MARTIN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NOVI NICO MARTIN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ANGGI PRADITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close 61 - before closing road
Inform JO HSE Incharge
RIFQI PAKSI JEON DONG MYOUNGNOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
LARASTY ASSE NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI SURIA ILHAM NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close 26 - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE KIM SOON KYUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
IRFAN PAMBUDI BAEK SEUNG NAM NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
SISCA TANGKEY Y.S. CHOI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ANITA TRIYANI NOEL KUSUMA Full Close 123 - before closing road
Inform JO HSE Incharge
ANITA TRIYANI NOEL KUSUMA Full Close 122 - before closing road
Inform JO HSE Incharge
AGUSTA PRIADY ASRI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAI KI YONG ANANIAS W NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ADHI TEJO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ALVIRA NAYA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Full Close - - before closing road

Inform JO HSE Incharge


NIKITA PARK CHOON HO NOEL KUSUMA Full Close 149 - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ELISA DEWANTI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ASRI AGUSTA PRIADY NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ALVIRA NAYA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road

Inform JO HSE Incharge


RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
QILA HEO TAE WON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
KIKI LEE KYUNG HUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ISNA SEO JEONG GEUN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
LARASATY ASSE NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE C.H. JEON NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI BAEK SEUNG NAM NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close 61 - before closing road
Inform JO HSE Incharge
SILVI PARK JAE GYOUNG NOEL KUSUMA Half Close 193 - before closing road
Inform JO HSE Incharge
SILVI PARK JAE GYOUNG NOEL KUSUMA Half Close 194 - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
MAULINDA NUGRAENI RONALD NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE KIM SOON KYU NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Full Close 123 - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Half Close 124 - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 223 - before closing road
Inform JO HSE Incharge
NIKITA RIDHO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NIKITA RIDHO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ANGGI PRADITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
MELI, BEKTI, YERMIAKIM TAE GYUN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close 149 - before closing road
Inform JO HSE Incharge
MELI, BEKTI, YERMIAKIM TAE GYUN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
WITO TAFERRY UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEAVATI CHOI KYUNG HO NOEL KUSUMA Half Close 230 - before closing road
Inform JO HSE Incharge
PRIMA KWON JUN HYUK NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI SHIN JUN YOUNG NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ISNA SEO JEONG GEUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOUNG CHUL PARK NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE SHIN JUN YOUNG NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ANGGI PRADITA PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEAVATI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 223 - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NOVI WIRYO BUDI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 285 - before closing road
Inform JO HSE Incharge
ERLINA WAHYU K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOUNG CHUL PARK NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
JOLAN RIKY PARK JAE GYOUNG NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE KIM SON KYU NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NIKITA RIDHO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
SYARIFAH MUH FUAD ALI NOEL KUSUMA Full Close 223 - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NOVI KEVIN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Full Close 149 - before closing road
Inform JO HSE Incharge
DAVID GEORGE KIM SANG HYUN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close 230 - before closing road
Inform JO HSE Incharge
NIKITA PARK CHOON HO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ISNA SEO JEONG GEUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI KWON SE HWAN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
HARKAT AGUNG MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 223 - before closing road
Inform JO HSE Incharge
NOVI KEVIN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
SISCA TANGKEY SYAHRIAL NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
WITO TAFERRY UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
GALUH LEE KYUNG HUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RIFQI PAKSI KIM SOON KYU NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEAVATI JEON DONG MYOUNGNOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PEBRIYANTI PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
PRIMA TRIYANI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Half Close 267 - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 439 - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NOVI WIRYO BUDI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Half Close 493 - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
GALUH LEE KYUNG HUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEAVATI WAHYU K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEAVATI WAHYU K NOEL KUSUMA Half Close 470 - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Half Close 493 - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NUGROHO WIRA BUANA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DAVID GEORGE KIM SON KYU NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
SOFIYAN HADI SHIN DONG JUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BIMA CANDRA ELISA DEWANTI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close 439 - before closing road
Inform JO HSE Incharge
PEBRIYANTI PARK CHOON HO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
KAFITA PUTRI SARINI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NOVI KEVIN MUHALING NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN RALINA NOEL KUSUMA Half Close 499 - before closing road
Inform JO HSE Incharge
DEAVATI WAHYU K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
WITO TAFERRY UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
SYARIFAH MUH FUAD ALI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ANANIAS W BAI KI YONG NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEAVATI WAHYU K NOEL KUSUMA Half Close 470 - before closing road
Inform JO HSE Incharge
YERMIA KIM TAE GYUN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
GALUH LEE KYUNG HUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NOVI KEVIN MUHALING NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
RISMA YUNITA MIKHAEL F.K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NUGROHO WIRA BUANA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ADE PUTRA S DWIKY DARMAWAN NOEL KUSUMA Half Close 535 - before closing road
Inform JO HSE Incharge
DEAVATI WAHYU K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN RALINA NOEL KUSUMA Half Close 499 - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
KAFITA PUTRI ASFIASYAH NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI UTOMO NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close 601 - before closing road
Inform JO HSE Incharge
ANITA TIYANI Y NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
HANTU PARK JAE GYOUNG NOEL KUSUMA Full Close 645 - before closing road
Inform JO HSE Incharge
GALUH LEE KYUNG HUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
STEPHANI KIM TAE GYUN NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
NOVI KEVIN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PUTRI KIM CHUL NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
NUGROHO WIRA BUANA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
AFFIKAH ADAM NORRIEGA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEAVATI WAHYU K NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI MOH ADITYA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
JOLAN RIKY USMAN SANJAYA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PUTRI KIM CHUL NOEL KUSUMA Half Close 656 - before closing road
Inform JO HSE Incharge
DEWI ANGRIANI MOH ADITYA NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
JOLAN RIKY USMAN SANJAYA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
BAGOES DWI YOSUA PUTRA NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
SYARIFAH M. FUAD ALI NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
SYARIFAH IBNU FATONI NOEL KUSUMA Full Close - before closing road
Inform JO HSE Incharge
STEPHANI PARK SUNGBAE NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
GALUH LEE KYUNG HUN NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
ALYA SHEILAWATI UTOMO NOEL KUSUMA Half Close - - before closing road
Inform JO HSE Incharge
PRIMA LEE DO HUI NOEL KUSUMA Full Close - before closing road
Inform JO HSE Incharge
PUTRI KIM CHUL DAEHAN KOO Half Close 656 - before closing road
Inform JO HSE Incharge
FELIX FIRMAN JOHANSYAH NOEL KUSUMA Full Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI DAEHAN KOO Full Close - - before closing road
Inform JO HSE Incharge
YOHANES IBNU FATONI DAEHAN KOO Full Close - - before closing road
VALIDATION
STATUS

CLOSE
CLOSE
CLOSE
CLOSE

CLOSE
CLOSE
CLOSE

CLOSE
CLOSE

CLOSE

CLOSE
CLOSE

CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE

CLOSE

CLOSE

CLOSE
CLOSE
CLOSE

CLOSE

CLOSE
CLOSE
CLOSE
CLOSE
CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE
CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

CLOSE

OPEN

OPEN

OPEN

OPEN

OPEN

OPEN

OPEN

OPEN

OPEN

OPEN

OPEN

You might also like